Meyer Corporation uses the percentage-of-completion method to account for work performed under long-term construction contracts.
Meyer began work under contract #7031-21, which provided for a contract price of $3,600,000. Additional data is as follows:
2008	 2009
Costs incurred during the year	$ 500,000	$1,664,000
Estimated costs to complete, as of December 31	1,500,000	-0-
Billings during the year	580,000	2,875,000
Collections during the year	525,000	2,670,000
Instructions:
a)	What portion of the total contract price would be recognized as revenue in 2008 and in 2009?
b)	Prepare a complete set of journal entries for 2008 under the (1) percentage-of-completion method, and (2) completed-contract method.