1. Methods to improve the outcome of an innovation tournament include:
a. Increase the number of opportunities generated.
b. Shift the average quality of the opportunities generated.
c. Increase the variance in the quality of opportunities generated. (wacky ideas)
d. a and c, but not b
e. a, b and c
2. What does the following relationship mean?
Activity B must finish exactly 2 days after the finish of A.
Activity B can finish at least 2 days after the finish of A
Activity B can finish at most 2 days after the finish of A.
None of the above.
3. To achieve the objectives, a project manager must focus most critically on
a. Managing the trade-offs in scope, cost, and time
b. Meeting schedule requirements
c. Coordinating the actions of the team members
d. Meeting budget requirements
4. To achieve the objectives, a project manager must focus most critically on
Managing the trade-offs in scope, cost, and time
Meeting schedule requirements
Coordinating the actions of the team members
Meeting budget requirements
5. Regardless of the criteria differences among different types of projects, the most important criterion for project selection is
How the project will balance risk within the project portfolio
The profit objective
The project's fit to the organization strategy
Compliance with external regulations