A contractor brought 10,000 cubic yard of soil to site to create a ramp. The water content of the soil is 30%. According to the engineer, the soil is too wet, and should be dried to 20% water content before it can be placed and compacted. The contractor will have to leave the pile of soil at the site to get dried. If 60,000 lbs of water evaporates from the pile each day, how long the contractor will have to wait before he can place the soil?

Specific gravity of soil is 2.6, and the degree of saturation is 90%. Assume that the overall volume does not change due to drying.

Reference no: EM13564911

Questions Cloud

How many vehicles per minute must the attendant process : Vehicles begin to arrive at a remote parking lot after the start of a major sporting event. They are arriving at a deterministic but time-varying rate of "3.3-0.1t" where 't' is in minutes. the parking lot attendant processes vehicles ( collects fee ..
What is the average annual mass loading of pcb from : A lake has an area of 1000 ha. The concentration of the toxicant PCB in rainfall is 100 ng/l and the average annual rainfall is 70 cm. What is the average annual mass loading of PCB from the precipitation to the lake in kg/year.
Develop the best equipment plan for the operation : A particular project has 650,000 cubic yards of material weighing 2600 lb/cy. your company has given you up to 10 - 657G tandem powered auger loaded scrapers to use to move the material. the 657g scrapers cost 160/ea per hour to operate and maintain
Evaluate the total magnetic flux through the cylinder : A long, straight wire carrying a current of 2.00 A is placedalong the axis of a cylinder or radius 0.500 m and a length of 3.00m. Determine the total magnetic flux through the cylinder
How long the contractor will have to wait before he can : A contractor brought 10,000 cubic yard of soil to site to create a ramp. The water content of the soil is 30%. According to the engineer, the soil is too wet, and should be dried to 20% water content before it can be placed and compacted. The contrac..
Find the total magnetic flux through the cylinder : A long, straight wire carrying a current of 2.00 A is placedalong the axis of a cylinder or radius 0.500 m and a length of 3.00m. Determine the total magnetic flux through the cylinder
Determine the posted speed limit to the nearest 5 mph : A building is located 19 ft from the centerline of the inside lane of a curved section of highway whose radius is 400 ft. The road is level and e = 10. Determine the posted speed limit (to the nearest 5 mph) considering the following conditions:
Determine the improvement in efficiency and circulation rate : Now you want to improve the efficiency and circulation rate. You suggest operaing the cycle utilizing two reversible tubines with saturated vapor exit streams. All conditions remain the same except that the feed to the first turbine is steam at 450 C..
Estimate the flow rate of water required to make the outflow : A mixing chamber has two steady streams and one steady stream. The properties of the first stream is superheated steam at T1 = 400oF, h1 = 1,239 Btu/lbm and flow rate m1 = 20 lbm/h. The second stream is compressed liquid at T2 = 70oF, h2 = 38 Btu/lbm..

Reviews

Write a Review

Civil Engineering Questions & Answers

  How many cubic yards of soil must be excavated from pit

A 1000 cubic yard embankment is to be built using soil from a borrow pit. The properties of embankment and the borrow pit soil are given below: Embankment: Dry unit weight = 115 pcf; Water content = 15%

  Determine what is the expected efficiency of the system

A disinfection process for potable water treatment is described by first order kinetics with a rate constant of 0.08 minute. An ideal plug flow reactor is used with a hydraulic residence time of 1 hour. What is the expected efficiency of the syste..

  Estimate the min do and the critical location in river

After initial mixing, the DO concentration in the river is 9.5mg/L and the temperature is 15ºC. If the ultimate BOD of the mixed river water is 30mg/L,

  Find velocity of bullet immediately after passing through b

A 30 g bullet is fired with a horizontal velocity of 450 m/s through 3-kg block B and becomes embedded in carrier C which has a mass of 30 kg. After the impact, block B slides 0.3m on C before coming to rest relative to the carrier.

  Determine that a building solution complies with performance

In accordance with BCA, what are the assessment methods and how may they be used to determine that a building solution complies with the performance requirements?

  Determine the heat transfer rate from the compressor

In a refrigeration system Refrigerant 22 enters the compressor at 150 kPa and -10 C. It leaves the compressor at 1.0 MPa and 90 C. Assume the mass rate of flow through the compressor is 0.016 kg/s

  Determine the veolicty of the cart at the instant package

A 20-lb package is thrown with a speed of 9 ft/s onto the 100-lb cart at the given angle of 30 degrees. It slides on the smooth cart and strikes the spring. If the spring has a spring constant k= 200 lb/in

  Select the lightest steel wide flange section with a yield

A simply supported beam is to span 15 feet. It will support a uniformly distributed load of 2 kips per linear foot over the full span and a concentrated load of 60 kips at midspan. Total deflection is not to exceed span/240.

  Find the minimum theoretical wall thickness

A flow of 600cfs is measured at a depth of 3.4 ft in trapezoidal channel with bottom width of 25ft and side slopes of 3:1(h:v). The channel reach has a slope of .002. Estimate the channel roughness.

  Determine internal shear and moment at specified location

Write a computer program that can be used to determine the internal shear and moment at any specified location x along the beam, and plot the shear and moment diagrams for the beam.

  What is the specific discharge in this rectangular channel

A large concrete channel holds a hydraulic jump in which the subcritical depth of flow is 2.5 m.  If 40 percent of the specific energy in the flow is lost through the hydraulic jump, what is the specific discharge in this rectangular channel?

  Find the distance traveled before the particle comes to rest

the velocity of a particle is given by the relation v=100-10x, where v is expressed in meters per second and x in meters. Knowing that x=0 at t=0, determine (a) the distance traveled before the particle comes to rest

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd