Good condition for top-down estimating

Assignment Help Accounting Basics
Reference no: EM13916712

1) The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
A. About the same
B. About twice as much
C. About three times as much
D. About four times as much
E. About five times as much

2) Resource shortages, in the form of people, equipment, or materials, is a good example of
A. Hidden interaction costs
B. Things going wrong on a project
C. Normal conditions not applying
D. Changes in project scope
E. None of these are correct

3) The accuracy of top-down estimates will typically be in the range of
A. Minus 50% to plus 50%
B. Minus 0% to plus 75%
C. Minus 20% to plus 60%
D. Minus 35% to plus 35%
E. Minus 10% to plus 30%

4) Design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are examples of:
A. Hidden interaction costs
B. Things going wrong on a project
C. Normal conditions not applying
D. Changes in project scope
E. None of these are correct

5) In practice, estimating processes are frequently classified as
A. Top down/bottom up
B. Rough/polished
C. Precise/order of magnitude
D. Draft/final
E. Both A and B are correct

6) Which of the following is a good condition for top-down estimating?
A. Cost and time important
B. Fixed price contract
C. Customer wants details
D. Internal, small project
E. All of these are good conditions for top-down estimating

7) Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
A. Padding estimates
B. Planning horizon
C. Project structure
D. People
E. Organization culture

8) A/an _________ activity has more than one dependency arrow flowing from it.
A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent

9) ________ activities are to be completed immediately following a particular activity.
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

10) When translated into a project network, a work package will become
A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

11) Activities which can take place at the same time are termed
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

12) The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

13) The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

14) Which of the following is not one of the steps in the risk management process?
A. Risk response development
B. Risk assessment
C. Risk identification
D. Risk tracking
E. Risk response control

15) One of the keys to success in risk identification is
A. Critical thinking
B. Optimism
C. Pessimism
D. A "can do" attitude
E. All of these are correct

16) The 1999 NASA Mars Climate Orbiter is an example of
A. Disaster avoidance through proactive risk management
B. Murphy's Law
C. Proper use of critical thinking
D. Mismanaged risk control
E. Using historical records to assess risk

17) A list of questions that address traditional areas of uncertainty on a project is termed a risk
A. Risk profile
B. Questionnaire
C. Research
D. Query
E. Checklist

18) One common mistake made early in the risk identification process is to
A. Not all possibilities are considered
B. Participants are over-optimistic
C. Participants are over-pessimistic
D. Focus on objectives and not on the events that could produce consequences.
E. Too much attention is given to past events

19) In the beginning the focus of risk management should be on risks that
A. Impact the whole project
B. Impact the critical path
C. Are known
D. Have the greatest cost impact
E. Have the greatest schedule impact

20) More common problems associated with managing multiproject resources include all of the following except
A. Inefficient resource utilization
B. Delays in one project cause delays in other projects
C. Reducing "downtime" created by lack of tasks to perform
D. Resource bottlenecks
E. All of these are common problems

21) Which of the following is not one of the types of project constraints?
A. Physical
B. Technical
C. Resource
D. Time
E. All of these are types of project constraints

22) In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost

23) . If resources are not adequate to meet peak demands, the resulting reschedule is termed
A. Resource-constrained scheduling
B. Time-constrained scheduling
C. Mandatory leveling
D. Project resource adjustment
E. Allocation

24) Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a _________ constraint.
A. Physical
B. Technical
C. Resource
D. Scheduling
E. Time

25) . In a resource-constrained project the third priority in assigning resources is usually given to activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost

Reference no: EM13916712

Questions Cloud

Disclose the extent of non-recurring revenue : Explain specifically why Qwest's failure to disclose the extent of non-recurring revenue violated the full disclosure principle in this situation.
What is error variance and how is it calculated : Q1. What is an F-ratio? Define all the technical terms in your answer. Q2. What is error variance and how is it calculated?
A separatory funnel and explain : Explain how use of 3 M HCl(aq) could separate it from the other components. To do so: show how acid would change the molecule; identify the phase in which this new species would be isolated in a separatory funnel and explain why it would be found the..
What is the probability that her partner will be selected : What's the probability that the attorney will be selected for the next case, assuming all registered attorneys are eligible? What is the probability that her partner will be selected in this scenario? What is the probability that the attorney OR her ..
Good condition for top-down estimating : The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
Check out writeaway hotels simulation at your student site : Check out the Writeaway Hotels simulation at your student site. If your instructor directs, follow the instructions to participate.
The ratio of numbers of mole of kmno4 : The ratio of numbers of mole of kmno4 and k2cr2o7 required to oxidised 0.1 mole sn2+ and sn4+ in acidic medium
Multiple independent-multiple levels of independent variable : Explain the difference between multiple independent variables and multiple levels of independent variables. Which is better?
How competitive advantage impact and influences organization : Describe how competitive advantage impacts and influences an organization or strategic group when referring to strategic management.

Reviews

Write a Review

Accounting Basics Questions & Answers

  The general ledger account for accounts receivable shows a

the general ledger account for accounts receivable shows a debit balance of 40000. the allowance for uncollectible

  Ignore the impact of income taxes in your calculationbased

columbus retail enterprises is evaluating the two investment proposals given belowinvestment proposala binvestment

  Expected sales for tents at sandys camping gear are 4200

expected sales for tents at sandys camping gear are 4200 6100 2200 3400 and 5300 for the next five quarters. at the end

  Abc is reviewing project that will cost 1431the project

abc is reviewing a project that will cost 1431.the project will produce cash flows 210 at the end of each year for the

  On june 30 2009 sideways movers had 243000 in current

on june 30 2009 sideways movers had 243000 in current assets and 211000 in current liabilities. on august 1 2009

  Three different partnership interests

Consider three people with three different partnership interests, and determine each individual's basis for partnership interest in the following three independent situations.

  Case study of martinez company

Martinez Company has decided to introduce a new product. The new product can be manufactured by either a capital-intensive method or a labor-intensive method. The manufacturing method will not affect the quality of the product. The estimated manuf..

  Use of guaranteed payments in partnership

What kind of situation would make guaranteed payments a logical way of starting a two-person partnership?

  Would the manager of the health club-spa be motivated to

would the manager of the health club-spa be motivated to undertake such an investment?compute the residual income for

  Super bakery inc created in1990 by former pittsburgh

super bakery inc. created in1990 by former pittsburgh steelers running back franco harris is a nationwide supplier of

  Among the principal topics related to the accounting for

among the principal topics related to the accounting for property plant and equipment of a company are acquisition and

  To record a bond investment between interest payment

1 temporary investments are recorded at their cost which would include brokers commissions.a. trueb. false2 the

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd