Give the answer of muliple choice question

Assignment Help Operation Management
Reference no: EM131382401

1.How is project scope defined?

A)The length of your project and how much it will cost

B)The deliverables or outputs during the course of the project

C)The range of resources you have available and their capabilities

D)What you expect to deliver to your customer when the project is complete

E)The range of customer expectations

 

2.There are 5 steps involved when defining a project, which of the following is the first?

A)Establish project priorities

B)Define the project scope

C)Verify the budget available

D)Assign team members to work on the project

E)Determine the required completion date

 

3.Which of the following is NOT true regarding scope creep?

A)It is when the cost of the project is more than expected

B)It is the tendency for the project scope to expand over time

C)It most likely caused by a scope statement that is too broad

D)It can have both positive and negative impacts on a project

E)It can lead to added costs and possible project delays

 

4.In reviewing the project plan, Susan sees that the first prototype must be completed by October 12. This would be best classified as a

A)Project target

B)Limit item

C)Milestone

D)Project objective

E)Critical goal

 

5.There are 5 steps involved when defining a project, which of the following is the second?

A)Analyze the strategic plan

B)Analyze the current budget plan

C)Establish project priorities

D)Select team members

E)Define the major objectives to meet the customer's needs

 

6.One of the primary jobs of a project manager is to manage the trade-offs associated with the project. Which of the following is NOT one of the basic classifications of project priorities?

A)Profit

B)Cost

C)Time

D)Performance

E)All of these are basic classifications

 

7.Scott has just been given a project that has a specific completion date. After a discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as

A)Constrain

B)Enhance

C)Accept

D)Limit

E)Optional

 

8.The _________ is used to assist in making project trade-offs between schedule, budget, and performance objectives.

A)Responsibility matrix

B)Work breakdown structure

C)Project priority matrix

D)Work package

E)Criterion matrix

 

9.The highest element in the hierarchical breakdown of the WBS is

A)A work package

B)Sub deliverables

C)A cost account

D)Major deliverables

E)The project

 

10.All of the following are ways the WBS helps in managing projects EXCEPT

A)With cost and time estimates the WBS makes it possible to plan, schedule and budget the project

B)It provides management with information appropriate to each level

C)It can be used to define communication channels

D)It allows the project manager to establish the overall objective of the project

E)As it is developed, organizational units and individuals can be assigned responsibility of work packages.

 

11.There are 5 steps involved when defining a project, which of the following is the last?

A)Code the WBS for the information system

B)Assign the cost account to a manager

C)Assign the work package to a manager

D)Develop the responsibility matrix

E)All of these are included in the final step

 

12.The WBS is best suited for projects that have a tangible outcome. Which of the following is used when the final outcome of the project is less tangible or is a product of a series of steps or phases?

A)Responsibility matrix

B)Organization breakdown structure

C)A work breakdown structure is still effective for these types of projects

D)Priority matrix

E)Process breakdown structure

 

13.The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called:

A)Scope erosion

B)Scope creep

C)Project bloat

D)Scope enhancement

E)Project add-ons

 

14.Which of the follow is least likely to be included in a work package?

A)How long the work package should take to complete

B)A description of work to be performed

C)Overhead expenses

D)How much the work package should cost to complete

E)The person responsible for the work package

 

15.Having a strong communication plan can go a long way toward mitigating project problems. A communication plan should address all of the following EXCEPT

A)When the information will be communicated

B)How information should be communicated and to whom

C)What methods will be used to gather and store information

D)What information needs to be collected and are there limits as to who has access to it

E)All of these should be addressed in a communication plan.

Reference no: EM131382401

Questions Cloud

Develop the full allowable tensile load : Design the fillet welds parallel to the applied load to develop the full allowable tensile load of the 6-in.-by- 3 8 -in. ASTM A36 steel plate shown. The electrode is an E70.
Give the answer of muliple choice question : Bill is working on a project involving the upgrading of a management information system. The project is being managed by the information systems department with the coordination of other departments occurring through normal channels. He is working..
Design an end connection using longitudinal welds : Design an end connection using longitudinal welds and an end transverse weld to develop the full tensile capacity of the angle shown. Use A36 steel and E70 electrodes.
Create a formula with structured references : Create a formula with structured references to calculate the percentage of the list price. Format the field with Percent Style with one decimal place.
Give the answer of muliple choice question : How is project scope defined?There are 5 steps involved when defining a project, which of the following is the first?One of the primary jobs of a project manager is to manage the trade-offs associated with the project. Which of the following is NOT ..
Calculate number of days between listing date and sale date : In cell J2, enter a formula to calculate the number of days between the listing date and sale date. Use the Subtotal feature to calculate the average selling price, percentage of asking price, and days on market by city.
What percent of all ticket holders are no-shows : What's the probability that a customer who didn't show had an advance-purchase ticket?
What’s the probability that chuck is on the job : You go to Dan's for supper one night and hear a dish break at the sink. What's the probability that Chuck is on the job?
What is the probability that leah’s first flight was delayed : Are the first flight leaving on time and the luggage making the connection independent events? Explain.

Reviews

Write a Review

Operation Management Questions & Answers

  Complete the assurance of learning exercises

Complete the Assurance of Learning Exercises 6A and 6B on page 205 of the textbook. Use the completed SWOT and SPACE matrices to draw conclusions regarding both the long term and short term strategies you would recommend in light of your findings. Su..

  Out of stocks as characterized by system dynamics

Identify how queues are different than items flowing into and out of stocks as characterized by system dynamics. Provide two specific examples of items flowing through a general system of stocks and two specific examples of items flowing into and out..

  Socio cultural influences and technological influences

The major components of a Broad environment are : Socio cultural Influences, Technological Influences, Economic Influences, and Political Influences. Give an example of a trend in each area that could affect the welfare of a business organization.

  Plant has four operators to be assigned to four machines

Define the decision variables and determine the objective function for the following problem. A plant has four operators to be assigned to four machines. The time (minutes) required by each worker to produce a product on each machine is shown in the ..

  Explain the logic of the laststatement

In this instance, you can narrow the set of choices, but you probably wouldn't make a recommendation without an additional piece of information. Explain the logic of the laststatement.

  Discuss responsibility of gm towards its employees

Based on GM's current condition, do you think it is ethical to reduce the number of employees? What responsibility does GM have towards its employees? Does GM have the same responsibility to the employees of its suppliers?

  Media conglomerates are getting bigger and bigger with more

media conglomerates are getting bigger and bigger with more and more media companies concentrating into fewer hands. do

  Critical aspects of value added by the workers

In jobs you have had, what have been the critical aspects of value added by the workers? Could they have been automated? What would have been lost if they had been automated?

  Marketing on major product modification

Assume that you are a project manager at a biotechnology company, working with managers from research, production, and marketing on a major product modification. You notice that every memo you receive from the marketing manager has been copied to sen..

  Design a high-performing supply chain organization

How does "Design a High-Performing Supply Chain Organization" apply to your current or previous workplace? Does it characterize the organization? Would a greater emphasis on Discipline 3 enhance the ability of the organization to achieve its performa..

  Write a report addressing a quantitative analysis

write a report addressing a quantitative analysis (QA) project. Here, you are asked to select a business of interest and develop QA best practices that can be developed and implemented to increase revenues and/or to decrease costs.

  Compute the availability of this machine

Compute the availability of this machine. The question states that all times must be in the same units. If I'm using the formular MTBF/MTBF+MTR how do I solve problem.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd