A construction firm has been commissioned to renew a portion of the Alaska crude-oil pipeline that has fallen into a state of disrepair. The project activities with the estimated times and their relationships are shown below:
a. Prepare a project network.
b. List the critical path activities and the expected project duration.
c. Determine the scheduling times and total slack for all activities.
d. In the contract, a bonus of $100,000 per day will be paid for each day the project is completed earlier than its expected duration. Evaluate the following alternatives to shorten the project duration and then make a recommendation:
1. Crash activity B by 4 days at a cost of $100,000.
2. Crash activity G by 1 day at a cost of $50,000.
3. Crash activity O by 2 days at a cost of $150,000.
4. Crash activity O by 2 days by drawing resources from activity N, thereby extending the time of N by 2 days.
Ethical issues of the movie margin call
: What are the ethical issues of the movie margin call?
|
Create a fun training environment
: Tim Trainer is asked to create a fun training environment. The business leader wants the employees to enjoy their working life and make sure that they feel fulfilled and rewarded at the after a training experience -- the key to improved performanc..
|
Make a recommendation for one common pto system
: Identify any additional information you would need to recommend a solution, and explain where you would likely find that information. Discuss any issues you would likely encounter if you were to merge the PTO system to a traditional leave system...
|
Find two examples of businesses in your local community
: Find two examples of businesses in your local community that attempt to disclaim liability for damage to or loss of bailed property (usually, the disclaimer is in the form of a sign behind a cash register, or language on a ticket stub.)
|
Find scheduling times and total slack for all activities
: In the contract, a bonus of $100,000 per day will be paid for each day the project is completed earlier than its expected duration. Evaluate the following alternatives to shorten the project duration and then make a recommendation
|
Find the bcnf of clinicplus and compare with bcnf of clinic
: Suppose Clinic is augmented to ClinicPlus by the addition of the attribute Appointment, which is unique for every tuple. - This can serve as a primary key. Find the BCNF of ClinicPlus and compare it with the BCNF of Clinic.
|
Information systems vulnerable to destruction
: Why are information systems vulnerable to destruction, error, and abuse?
|
Manage global team communication using technology
: Write a 1,050- to 1,400-word paper that describes how you would manage global team communication using technology.
|
Provides an introduction to research methods and methedology
: In this video, Dr Greg Martin provides an introduction to research methods, methedology and study design. Specifically he takes a look at qualitative and quantitative research methods including case control studies, cohort studies, observational r..
|