Estimate the cost of construction for this project

Assignment Help Accounting Basics
Reference no: EM131012003

a. S-a-b-F P1(<24) = .95

b. S- d-e-F P2(<24) = .85

c. S- g-h-F P3(<24) = .90


only three) paths through a network (project), each with a probability of completion in less than 24 months as indicated:

a. S-a-b-F P1(<24) = .95

b. S- d-e-F P2(<24) = .85

c. S- g-h-F P3(<24) = .90

If the tasks are independent, what is the probability of the network being completed within 24 months? Note: S is the start node, F is the finish node2. You have been assigned to estimate the cost of installing fiber optic cable in a country in the Middle East. Fortunately, you have done a number of similar projects in this area in the past and you have accumulated the following parametric cost estimates based on this experience:Mobilization/demobilization Cost = $10,000Buried cable construction:

Cost per kilometer = $10,000 Sand

Cost per kilometer = $17,500 Sand & Clay

Cost per 100 meters = $ 5,500 RockOverhead cable installation:

Cost per kilometer = $ 7,500Cost per Road Crossing = $12,500

Cost per pipeline Crossing = $ 5,000The scope of the new project is as follows:Predominately sand 150 km

Predominately sand & clay 100 km

Rock 500 meters

overhead *****crossings 3

pipeline crossings 5Estimate the cost of construction for this project. Assume the estimates are fully loaded, ie they include labor, materials, applicable indirect costs such as overhead, etc

Reference no: EM131012003

Questions Cloud

Problem regarding the crab claws : Reconsider the data on claw closing force and claw size for three species of crabs, shown in Exercise 7.22. Display 10.18 shows output from the least squares fit to the separate lines model for the regression of log force on log height.
At what speed is fuel economy greatest : The fuel economy (in miles per gallon) of a certain car is E(x) = -0.01x2 + 0.52x +10.4, where x is the driving speed (in miles per hour, 20 ≤ x ≤ 60). At what speed is fuel economy greatest?
Galileo data-brain weight : Why is horizontal distance, rather than height, the response variable?
What is the linear cost function : You first decide to create a linear cost function based on this data. What is the linear cost function, and how much lemonade can Herman make according to this model?
Estimate the cost of construction for this project : Estimate the cost of construction for this project. Assume the estimates are fully loaded, ie they include labor, materials, applicable indirect costs such as overhead, etc
Ingestion rates of deposit feeders : Aquatic deposit feeders are organisms that feed on organic material in the bottoms of lakes and oceans. Display 9.21 shows the typical dry weight in mg, the typical ingestion rate (weight of food intake per day for one animal) in mg/day, and the p..
What is the average rate of change in the noise level : Freeway noise lessens as the distance from the freeway increases. What is the average rate of change in the noise level as you go from 70 to 90 yards away from the freeway?
Find parametric equations for the lone : Find parametric equations for the lone in which the two planes intersect. Find an equation of the plane that is perpendicular to the two planes and containing the point (5, 1, -2).
Solar radiation and skin cancer : The data in Display 3.11 are yearly skin cancer rates (cases per 100,000 people) in Connecticut, with a code identifying those years that came two years after higher than average sunspot activity and those years that came two years after lower tha..

Reviews

Write a Review

Accounting Basics Questions & Answers

  Transaction on net operating income

XYZ Company accepted a national credit card for a $3,000 purchase. The cost of the goods sold is $2,400. The credit card company charges a 3% fee. What is the impact of this transaction on net operating income?

  Determine the amount of the completed gift

Determine the amount of the completed gift, if any, arising from each of the following occurrences.

  Finished units of production require 7 pounds of raw

direct materials purchases budget lo 2roehler industrial has estimated that production for the next five quarters will

  Calculate its cost of capital

Nessumsar compay develops educational materials. It has a cost of debt after taxes of 6.8% and a cost of equity of 10.9%. The company finances with 45% debt. Calculate its cost of capital.

  The required volume of output to produce the motors will

green company uses part jr3 in manufacturing its products. it has always purchased this from a supplier for 40 each. it

  When a share of stock is first sold the amount received by

1. when a share of stock is first sold the amount received by the company may be different from the amount printed on

  Joes beginning and ending inventories contain unconfirmed

joes beginning and ending inventories contain unconfirmed profits on goods purchased from sam of 70000 and 90000

  Raw materials inventory problem

As of December 31, 2010, Stand Still Industries had $2,500 of raw materials inventory. At the beginning of 2010, there was $2,000 of materials on hand. During the year, the company purchased $305,000 of materials;

  Deduction for the lease payments

The lease will run for five years and the payments are $900 per month. During 2009, she uses her car 20% for business and 80% for personal activities. Assuming the dollar amount from the IRS table is $233, determine Lana's deduction for the lease ..

  Philanthropic organization

1. Free gift. A philanthropic organization sends out "free gifts" to people on their mailing list in the hope that the re- ceiver will respond by sending back a donation. Typical gifts are mailing labels, greeting cards, or post cards.

  Determine the inventory direct labor costs

Assuming that the company's $337,485 ending Finished Goods Inventory account for year 2011 had $137,485 of direct materials costs, determine the inventory's direct labor costs and its overhead costs.

  You plan to have 1000000 in your retirement account when

a-you plan to have 1000000 in your retirement account when you retire in 40 years. assume an average annual rate of

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd