Establish logic network with checkpoints

Assignment Help Basic Computer Science
Reference no: EM131245013

Table 11-8 identifies twenty-six steps in project planning and control. Below is a description of each of the twenty-six steps. Using this information, fill in columns 1 and 2 (column 2 is a group response). After your instructor provides you with column 3, fill in the remainder of the table

1. Develop the linear responsibility chart. This chart identifies the work breakdown structure and assigns specific authority/responsibility to various individuals as groups in order to be sure that all WBS elements are accounted for. The linear responsibility chart can be prepared with either the titles or names of individuals. Assume that this is prepared after you negotiate for qualified personnel, so that you know either the names or capabilities of those individuals who will be assigned

2. Negotiate for qualified functional personnel. Once the work is decided on, the project manager tries to identify the qualifications for the desired personnel. This then becomes the basis for the negotiation process.

3. Develop specifications. This is one of the four documents needed to initially define the requirements of the project. Assume that these are either performance or material specifications, and are provided to you at the initial planning stage by either the customer or the user.

4. Determine the means for measuring progress. Before the project plan is finalized and project execution can begin, the project manager must identify the means for measuring progress; specifically, what is meant by an out-of-tolerance condition and what are the tolerances/variances/thresholds for each WBS base case element?

5. Prepare the final report. This is the final report to be prepared at the termination of the project.

Table 11-8

530_faf65c4e-3d94-43b6-ac16-a43df9d1a96d.png

678_4ff4708c-b335-48ec-af62-396890482a03.png

6. Authorize departments to begin work. This step authorizes departments to begin the actual execution of the project, not the planning. This step occurs generally after the project plan has been established, finalized, and perhaps even approved by the customer or user group. This is the initiation of the work orders for project implementation.

7. Develop the work breakdown structure. This is one of the four documents required for project definition in the early project planning stage. Assume that WBS is constructed using a bottom-up approach. In other words, the WBS is constructed from the logic network (arrow diagram) and checkpoints which will eventually become the basis for the PERT/CPM charts (see Activity 25).

8. Close out functional work orders. This is where the project manager tries to prevent excessive charging to his project by closing out the functional work orders (i.e., Activity 6) as work terminates. This includes canceling all work orders except those needed to administer the termination of the project and the preparation of the final report.

9. Develop scope statement and set objectives. This is the statement of work and is one of the four documents needed in order to identify the requirements of the project. Usually, the WBS is the structuring of the statement of work.

10. Develop gross schedule. This is the summary or milestone schedule needed at project initiation in order to define the four requirements documents for the project. The gross schedule includes start and end dates (if known), other major milestones, and data items.

11. Develop priorities for each project element. After the base case is identified and alternative courses of action are considered (i.e., contingency planning), the project team performs a sensitivity analysis for each element of the WBS. This may require assigning priorities for each WBS element, and the highest priorities may not necessarily be assigned to elements on the critical path

12. Develop alternative courses of action. Once the base case is known and detailed courses of action (i.e., detailed scheduling) are prepared, project managers conduct "what if" games to develop possible contingency plans.

13. Develop PERT network. This is the finalization of the PERT/CPM network and becomes the basis from which detailed scheduling will be performed. The logic for the PERT network can be conducted earlier in the planning cycle (see Activity 25), but the finalization of the network, together with the time durations, are usually based on who has been (or will be) assigned, and the resulting authority/- responsibility of the individual. In other words, the activity time duration is a function not only of the performance standard, but also of the individual's expertise and authority/ responsibility.

14. Develop detailed schedules. These are the detailed project schedules, and are constructed from the PERT/CPM chart and the capabilities of the assigned individuals.

15. Establish functional personnel qualifications. Once senior management reviews the base case costs and approves the project, the project manager begins the task of conversion from rough to detail planning. This includes identification of the required resources, and then the respective qualifications.

16. Coordinate ongoing activities. These are the ongoing activities for project execution, not project planning. These are the activities that were authorized to begin in Activity 6.

17. Determine resource requirements. After senior management approves the estimated base case costs obtained during rough planning, detailed planning begins by determining the resource requirements, including human resources.

18. Measure progress. As the project team coordinates ongoing activities during project execution, the team monitors progress and prepares status reports.

19. Decide on a basic course of action. Once the project manager obtains the rough cost estimates for each WBS element, the project manager puts together all of the pieces and determines the basic course of action.

20. Establish costs for each WBS element. After deciding on the base case, the project manager establishes the base case cost for each WBS element in order to prepare for the senior management pricing review meeting. These costs are usually the same as those that were provided by the line managers.

21. Review WBS costs with each functional manager. Each functional manager is provided with the WBS and told to determine his role and price out his functional involvement. The project manager then reviews the WBS costs to make sure that everything was accounted for and without duplication of effort.

22. Establish a project plan. This is the final step in detail planning. Following this step, project execution begins. (Disregard the situation where project plan development can be run concurrently with project execution.)

23. Establish cost variances for the base case elements. Once the priorities are known for each base case element, the project manager establishes the allowable cost variances that will be used as a means for measuring progress. Cost reporting is minimum as long as the actual costs remain within these allowable variances.

24. Price out the WBS. This is where the project manager provides each functional manager with the WBS for initial activity pricing.

25. Establish logic network with checkpoints. This is the bottom-up approach that is often used as the basis for developing both the WBS and later the PERT/CPM network.

26. Review base case costs with director. Here the project manager takes the somewhat rough costs obtained during the WBS functional pricing and review and seeks management's approval to begin detail planning

Reference no: EM131245013

Questions Cloud

Should pert network design be dependent on elements : Would you agree or disagree that the cost of accelerating a project rises exponentially, especially as the project nears completion
Is research used in your facility : Is research used in your facility? If so, what type of research and how is this different than other nursing roles? Find out if there is a research committee at your facility. Is research an important component of clinical practice?
What are the major difficulties with pert : Is PERT/cost designed to identify critical schedule slippages and cost overruns early enough that corrective action can be taken?
Watch the two youtube videos : Watch the two youtube videos. - Compare and contrast what you saw. - Then look at the number of views each video has - who has more? Why do you think?
Establish logic network with checkpoints : Establish logic network with checkpoints. This is the bottom-up approach that is often used as the basis for developing both the WBS and later the PERT/CPM network.
What role companys culture play in executing managerial task : Discuss what is involved in performing the eight key managerial tasks that shape the process of implementing and executing strategy. Explain what role a company's culture plays in executing these managerial tasks.
How and why the suggestions could be implemented : Introduction Creates an innovative introduction that makes the audience care, using a relatable example or an intriguing idea
Find the pole locations and determine the transfer function : Find the pole Locations (e.g., using MATLAB), and plot the pole locations in the s-plane. Identify the angle of the complex. poles in the s-p]ane and verify that they correspond to a 3-order Butterworth filter.
Discuss how the two sets of control charts are different : Discuss notable out-of-control conditions displayed in the completed x¯ and R (average and range) control charts. Only consider points outside the control limits. Do not consider runs, set of points within certain zones, and so forth.

Reviews

Write a Review

Basic Computer Science Questions & Answers

  What is the order of the functions

What is the order of the functions

  Extract the boundary string from the content-type

extract the boundary string from the Content-Type.

  Assistance in creating an entity relationship design

Assistance in creating an entity relationship design that captures/tracks information of researchers within all universities in a given state. Information of interest includes researcher name, title, position; university name, location, enroll..

  Heirarchy of legal importance for types of law

We have common law, statutory law, and administrative law. In a healthcare setting which of these do you deem to be the most important source of law? If you were to categorize the heirarchy of legal importance for these types of law, how would yo..

  The shuffled deck should be represented by a two-dimensional

Write a small program that will read in 52 cards from a file, shuffle the cards, print the unshuffled deck to the screen, and print the shuffled deck into new file.The unshuffled deck of cards should be represented in the program by three-dimensional..

  Effort required for various project

Estimation of the effort required for various project tasks is one of the toughest assignments for a project planner. In an organization, who is the best judge for the effort needed for specific tasks? Please explain the basis for your answer.

  Calculate the total of the scores by using while loop

Write a program to calculate the average of the class by following steps: 1. Ask user input how students in the class 2. Use random function to generate the score (between 0 and 100) for each student and calculate the total of the scores by using ..

  Design and implement own version

For this question, you are required to design and implement your own version of the Position ADT and the Node List ADT. You are not allowed to use any of the built-in classes or interfaces provided by Java, which provide similar operations.

  Program to display the sum on the screen

Write the code to add together the numbers stored in the first and second elements in a one-dimensional int array named nums. Display the sum on the screen.

  What are the inputs for a bottom-up software project plan

What are the inputs for a bottom-up software project plan? What precautions are taken while creating a project plan to tackle different risks? What kinds of project plans are devised for iterative models of software development?

  Determine the magnitude and direction of the shearing stress

A layer of water flows down an inclined fixed surface with the velocity profile shown in Fig. P12.2. Determine the magnitude and direction of the shearing stress that the water exerts on the fixed surface for U = 3 m/s and h = 1 m.

  Indexing for different query types

This group assignment provides an opportunity to gain some practical experience with indexing. The "experiment of the week" assignments are intended to be more open, with your group picking the specific topics to investigate. Basically, this gives..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd