Earned value calculation

Assignment Help Operation Management
Reference no: EM132257088

Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $250,000 when complete. Its costs so far are $165,000. It is 50% complete. The activity has completed 7 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 65% complete. It was to cost $190,000 when finished. Its costs to date are $150,000.

Activity C is finished. It finished 2 weeks late. It cost $200,000 and it was planned to have cost $250,000.

Activity D is at the end of its fourth of a planned 6-week schedule. It has cost $350,000 so far. It was estimated to cost $500,000 when finished. It is approximately 55% complete.

Using these data, calculate the following.

1. Calculate the CV, SV, CPI, and SPI for each activity and the total project

2. What is your assessment of the project at this time?

Reference no: EM132257088

Questions Cloud

Describe the important physical and social features : In your paper, clearly identify the age group and developmental stage selected. Describe the important physical, emotional, cognitive, and social features.
Potential area of cost due to inadequate control : Which of the following is NOT cited as a potential area of cost due to inadequate control?
Design a quality assurance plan in the form of a flow chart : EG5104 Assignment - Management Project. Design a quality assurance plan in the form of a flow chart to not only address these issues but also improve them
Discuss about the counselling or psychotherapeutic framework : For this assignment you are required to choose a counselling or psychotherapeutic framework and to write about how this has been used in an applied way.
Earned value calculation : Earned Value Calculation. What is your assessment of the project at this time?
Create a powerpoint presentation on a CAM topic : Create a PowerPoint presentation of 3-4 slides (slide count does not include title and reference slides) on a CAM topic. Presentations should present.
What is make good supervisor : What's make good supervisor? How do you go about dealing with bad employees?
Factors to improve teamwork and success as supervisor : What are the factors to improve teamwork and success as a supervisor?
Field of continuous quality improvement researchers : In outline form identify THREE contemporary researchers who have contributed to the field of continuous quality improvement researchers

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd