Draw the activity on node project network

Assignment Help Basic Statistics
Reference no: EM131142223

Complete in Excel exactly as the directions state
Using the information in the table below:

a. Draw the Activity On Node project network.

b. Complete the forward and backward pass, find Earliest Start and Earliest Finish, Latest Start and Latest Finish and Slack for each activity.

Show all of your numbers on the network drawing.

c. Identify the critical path clearly and determine the total project time.

d. Draw a Gantt chart for the network using the Earliest Starts and duration times for each activity

Activity

Immediate Predecessor

Time

(months)

Start

-

0

A

Start

12

B

A

14

C

Start

10

D

C

17

E

C

18

F

C

12

G

D

15

H

E

8

I

F

7

J

I

12

K

B

9

M

G

3

N

H

11

P

H, J

8

End

K, M, N, P

0

Reference no: EM131142223

Questions Cloud

Draw a high-wage earner''s budget constraint : What happens to her incentives to work? Is it possible that imposing the tax actually will reduce the tax revenues the government receives from the rich?
Which is least likely to be represente in a byzantine mosaic : Which is least likely to be represented in a Byzantine mosaic? Which feature of Hagia Sophia was not part of the original design? The pagan god most often associated with Christ was.
Determine the approach flow rate and cycle length : If the capacity of the approach equals the number of arrivals per cycle, determine the approach flow rate and cycle length.
How communication strategies work in conjunction : Project how marketing to segment of the stay-at-home dads will affect the buying behavior of their children in years to come. Determine two ways to counteract or foster the positive or negative influences for products that you believe may be affec..
Draw the activity on node project network : Draw the Activity On Node project network.- Identify the critical path clearly and determine the total project time.
Determine the arrival rate : Determine the arrival rate assuming that it is unchanged over the duration of the observation period (from the beginning to the end of this 5.78-vehicle-minute delay cycle).
Determine the complete queue clearance : The saturation flow rate of the approach is 1800 veh/h, the cycle length is 60 seconds, and the effective green time is 40 seconds. Determine the total vehicle delay until complete queue clearance.
How would your comments reflect on the lakeside plaza : Assume these were your grandparents and the wedding they wished to attend were your own. Would you share details of this incident with those you know? Would you use the Internet to share the details with them? How would your comments reflect on th..
Which is not used in making stained glass windows : Which is not used in making stained glass windows? Which is not a feature of the Divine Comedy? Which of the following had the least influence on Giotto? A typical Romanesque portal does not contain which element?

Reviews

Write a Review

Basic Statistics Questions & Answers

  Statistics-probability assignment

MATH1550H: Assignment:  Question:  A word is selected at random from the following poem of Persian poet and mathematician Omar Khayyam (1048-1131), translated by English poet Edward Fitzgerald (1808-1883). Find the expected value of the length of th..

  What is the least number

MATH1550H: Assignment:  Question:     what is the least number of applicants that should be interviewed so as to have at least 50% chance of finding one such secretary?

  Determine the value of k

MATH1550H: Assignment:  Question:     Experience shows that X, the number of customers entering a post office during any period of time t, is a random variable the probability mass function of which is of the form

  What is the probability

MATH1550H: Assignment:Questions: (Genetics) What is the probability that at most two of the offspring are aa?

  Binomial distributions

MATH1550H: Assignment:  Questions:  Let’s assume the department of Mathematics of Trent University has 11 faculty members. For i = 0; 1; 2; 3; find pi, the probability that i of them were born on Canada Day using the binomial distributions.

  Caselet on mcdonald’s vs. burger king - waiting time

Caselet on McDonald’s vs. Burger King - Waiting time

  Generate descriptive statistics

Generate descriptive statistics. Create a stem-and-leaf plot of the data and box plot of the data.

  Sampling variability and standard error

Problems on Sampling Variability and Standard Error and Confidence Intervals

  Estimate the population mean

Estimate the population mean

  Conduct a marketing experiment

Conduct a marketing experiment in which students are to taste one of two different brands of soft drink

  Find out the probability

Find out the probability

  Linear programming models

LINEAR PROGRAMMING MODELS

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd