Draw the activity on node project network

Assignment Help Basic Statistics
Reference no: EM131142223

Complete in Excel exactly as the directions state
Using the information in the table below:

a. Draw the Activity On Node project network.

b. Complete the forward and backward pass, find Earliest Start and Earliest Finish, Latest Start and Latest Finish and Slack for each activity.

Show all of your numbers on the network drawing.

c. Identify the critical path clearly and determine the total project time.

d. Draw a Gantt chart for the network using the Earliest Starts and duration times for each activity

Activity

Immediate Predecessor

Time

(months)

Start

-

0

A

Start

12

B

A

14

C

Start

10

D

C

17

E

C

18

F

C

12

G

D

15

H

E

8

I

F

7

J

I

12

K

B

9

M

G

3

N

H

11

P

H, J

8

End

K, M, N, P

0

Reference no: EM131142223

Questions Cloud

Draw a high-wage earner''s budget constraint : What happens to her incentives to work? Is it possible that imposing the tax actually will reduce the tax revenues the government receives from the rich?
Which is least likely to be represente in a byzantine mosaic : Which is least likely to be represented in a Byzantine mosaic? Which feature of Hagia Sophia was not part of the original design? The pagan god most often associated with Christ was.
Determine the approach flow rate and cycle length : If the capacity of the approach equals the number of arrivals per cycle, determine the approach flow rate and cycle length.
How communication strategies work in conjunction : Project how marketing to segment of the stay-at-home dads will affect the buying behavior of their children in years to come. Determine two ways to counteract or foster the positive or negative influences for products that you believe may be affec..
Draw the activity on node project network : Draw the Activity On Node project network.- Identify the critical path clearly and determine the total project time.
Determine the arrival rate : Determine the arrival rate assuming that it is unchanged over the duration of the observation period (from the beginning to the end of this 5.78-vehicle-minute delay cycle).
Determine the complete queue clearance : The saturation flow rate of the approach is 1800 veh/h, the cycle length is 60 seconds, and the effective green time is 40 seconds. Determine the total vehicle delay until complete queue clearance.
How would your comments reflect on the lakeside plaza : Assume these were your grandparents and the wedding they wished to attend were your own. Would you share details of this incident with those you know? Would you use the Internet to share the details with them? How would your comments reflect on th..
Which is not used in making stained glass windows : Which is not used in making stained glass windows? Which is not a feature of the Divine Comedy? Which of the following had the least influence on Giotto? A typical Romanesque portal does not contain which element?

Reviews

Write a Review

Basic Statistics Questions & Answers

  Determine the monthly break-even volume

The Evergreen Fertilizer Company produces fertilizer. The company's fixed monthly cost is $25,000, and its variable cost per pound of fertilizer is $0.15.

  The thicknesses of six pads designed for use in aircraft

the thicknesses of six pads designed for use in aircraft engine mounts were measured. the results in mm were 40.93

  What proportion of faculty consume coffee in range of cups

A standard deviation of 1.5. The distribution is normal. What proportion of faculty consume an amount between 4 & 6 cups?

  Assignments of probability

1. An experiment has four possible outcomes A, B, C, and D. Check whether the following assignments of probability are possible:

  Possibility of losing the lawsuit

Your client is being sued. You have asked the client's lawyer about the possibility of losing the lawsuit. The client, meanwhile, has asked you to describe what would happen to his or her financial statements.

  Compute the likelihood that she indeed has the cancer

A pair of dice is rolled. The sum of the faces on top is observed. What are the expectation, variance, and standard deviation of the observed sum? The Expectation and Variance Template attached to the main posting is optional and recommended.

  A farmer was interested in determining how many

a farmer was interested in determining how many grasshoppers were in his field. he knows that distribution of

  Significant effect on memory

Are the data sufficient to that the herb has a significant effect on memory? Use a two-tailed test with α = .05.

  Dispersed distribution basics

In 2010, the average age of students at UTC was 22 with a standard deviation of 3.96. In 2013, the average age was 24 with a standard deviation of 4.08. In which year do the ages show a more dispersed distribution? Show your complete work and supp..

  What is the standard error for the sample mean

Distributed with a mean of 1 centimeter and a standard deviation of 0.1 centimeter. A random sample of 12 computer chips is taken. what is the standard error for the sample mean?

  Problem regarding the weibull distribution

Consider a random sample X1 ,X2 ,• • • , X,, from the Weibull distribution with p.d.f. f( x; 0, -r) = 0-rxi - 1e-0xr, 0 x oo, where O 0, 0 -r, zero elsewhere. (a) If -r is known, find the m.l.e. of 0.

  The number of power outages at a nuclear power plant has

the number of power outages at a nuclear power plant has poisson distribution with a mean of 0.8 outage per month. what

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd