Determine total slack time for all tasks

Assignment Help Civil Engineering
Reference no: EM131033859

Microsoft Project is a software which includes project work, project teams, schedules and Finance. It is also designed to assist users to develop concrete goals for project teams and clients by creating tables and the allocation of resources and management of budgets (Rouse, M 2015). There are many reasons for making scheduled plan for any project. So one of them is to determine the time of activities and project completion date. The scheduled plan include network diagrams and Bar Chart.

Network diagrams are a schematic representation which displays the project schedule and connect between these activities. Also It is a graphical diagram which shows the performance of the tasks necessary to complete a project and clearly conceive the flow of tasks & relationships (Emanuele Della Valle 2010).

A Gantt chart is a horizontal bar chart which is developed as a production control tool in 1917 by Henry L. Gantt. It provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project (Rouse, M 2007).

Aim

This report is done to create a new project plan for producing and formatting a Programme with time constriants and the aim of report lab are:

• Creating a formatted Bar Chart and network diagrams
• Adding overlaps between tasks
• Analysis Effect of constraints
• Slack (Float) analysis
• Changing critical and non-critical tasks duration (Dawood, M 2016)

Laboratory Data & Results Discussion

1- Started Microsoft Project 2010 Program and created a Blank Project with adjusting Auto Schedule and change the start of project date to 01-Dec-2016 .

2- select the standard calendar than make (Only Friday and Saturday as nonworking days per week) than adjust the annual holidays( Oman National day on 18 Nov and AL Nahda day on 23 July) repeating , say 5 years by clicking

3- entered the data as given in excel sheet in the Microsoft project by added the task name , duration and successor is shown in (Dawood, M 2016).

Requirements

Q1- after adjusting the project by applying the required data is given in table (1) and display the project summary task by entered the data in Microsoft Project as shown in Figure (1). We found the duration of project is 16 days and due date is 22- 12- 2016

Q2- show critical task in red color by using format tab / the critical task box/ Test Style / Item to change / critical task then the critical task appears in red color as shown in Figure (2). *the difference in critical and non critical task in a system is critical task are processes that the computer needs to operate correctly they are must have programs. Non critical talk are task that are running or can run but is not a crusial part if the task is deleted or ended then the OS should still fuction properly

Q3- Applied Finish No Earlier Than constraint with a constraint date of 01-Feb-2017 to task Bridge railing (task 21) by double click to the task 21 /advance / Constraint type / Finish No Earlier Than / constraint date/ 01-Feb-2017 as shown in figure (2). The Project duration is 68 days and due date is 03-March -2016.We observe that is no change in project duration because due date of project is more that the constraint date (Dawood, M 2016).

* Time constraints refer to the limitations on the start and end times of each task in a project's critical path, which is the sequence of tasks that cannot be delayed without delaying the entire project (Basu. C 2014).

Q4- determine Total Slack time for all tasks by insert new column (Total Slack ) and increase duration of Construct Central Pier (task 12) task by 5 days. Since it 's a critical task increasing days effected the project to became the duration of project is 66 days and due date is 3 - 2 - 2017 as shown in figure (3).

*Slack or Float provide flexibility in the project schedule. There are two types :-

*Total Float : The total amount of time that a schedule activity may be delayed from its early start without delaying the project finish date and determining the difference between the early finish dates and late finish dates.

*Free Float : The amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities

Q5- We formatted the noncritical tasks as by clicking format tab / format / bar style then we changed middle pattern, start shape and end shape as shown in figure (8) (Dawood, M 2016).

Q6- insert the task name above the bar and task duration below the bar (in Gantt chart) by clicking format tab / format / bar style then select text and changed top(Name) & bottom (duration) as shown in figure (5) and figure (6).

Q7- We formatted the critical task as274_Create a new project plan.jpgin Network Diagram by clicking View / Network Diagram/ format / box style then changed style setting for critical and border shape as shown in figure (10)

Q8- by double click in the task 11 / predecessor / (SS)/ lag (5days), we Change the relationship between Foundation Right Abutment (task 11) task and its predecessor to Start to Start (SS) relationship with 5 days lag and observe the there is no change in project duration and due date of the project as shown in figure (8)

Q12- Compare the results of manual calculation & MS Project

After calculation manually in AON & Gantt Chart , we found the duration of project in initial data is 71 days ( Figure 12,13). In other hand , the project duration in Microsoft Project is 71 days. The critical activities in manual (AON & Gantt Chart) is task ( 1,6,9,12,13,14,17,21,22) and the critical activities in MS Project is also same task (1, 6,9,12,13,14,17,21,22) .

We observe the result of manual calculation and the result of Microsoft calculation is no difference between them is same result and the critical activities is same in both.

In this lecture, we have observed changed in the projects duration and due date. We found the duration of project by initial data is 68 days and the due date is 03- March-2016 and after that we show the critical task in red color to identify which task is critical task .when we add Total Slack time for all the tasks and increase duration of the task 12 by 5 days , the duration change to 73 days and due date is 10-March -2016. So we observe that any change in duration of the critical task it will effect to the duration of project. In addition ,we have learned and understand the Network Diagram and Gantt Chart in manual and by using Microsoft Project and we resulting that the duration of project and critical task is same in both.

Reference no: EM131033859

Questions Cloud

Which facilities capital costs of money is an allowable cost : Describe two to three (2-3) circumstances in which facilities capital costs of money is an allowable cost. Determine the single most significant advantage of having facilities capital costs as an allowable cost under the circumstances you described. ..
Problem regarding the cost of employee benefits : Reisleven Corporation has undertaken a cost study of its operations. One area of concern to the company is the total cost of labor, particularly the cost of employee benefits. Prepare a list of the different kinds of costs that a company might inc..
Consider the reaction: ch4(g) + 2 o2(g)® co2(g) + 2 h2o(g) : CalculateDrxnH andDrxnS for this reaction at 2000°C using the temperature dependent heat capacity values provided in table below:
Difference in depreciation-facilities capital cost of money : Suppose you have been working with the federal government for a period of time, and you decide to form a small company. Explain the difference between depreciation and the facilities capital cost of money. Specify the key advantages of having facilit..
Determine total slack time for all tasks : Determine Total Slack time for all tasks by insert new column (Total Slack ) and increase duration of Construct Central Pier (task 12) task by 5 days.
Discuss available preventative health services : Select one of the Healthy People 2020 initiatives and discuss available preventative health services (immunizations, health screenings, etc.) relevant to the initiative, as well as health promotion strategies to be implemented by the advanced prac..
Entirely different organization-still be outstanding leader : Could an outstanding leader in one organization move into an entirely different organization and still be an outstanding leader? For example, could a great football coach with evident leadership abilities be hired as a CEO of a large company such as ..
Is the acid strong or weak : Select the Lewis structure for the ion formed by the acid when it ionizes.
How would you use active listening in a job interview : How would you use active listening in a job interview to ‘interview' the interviewer? How will you find out as much as possible about the job and organisation

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate the energy needed to bring the soil

We are digging a hole to build a building. Calculate the energy needed to bring the soil to surface level. Remember the sides of the excavation lie at 45 degrees. Else, the whole would be constantly refilling itself.

  Calculate the amount you will have from the investment

You have just received $10,000 witch which you can do anything. You have decided to invest the money over a long period of time and then use it to make a down payment on a vacation home.

  Determine how many balloons would be taken

To float a 160 pound man using helium balloons (assume 0.52 cubic feet per inflated balloon). How many balloons would it take. Assume density of air is 1.29 kg/cubic meter and the density of helium is 0.179 kg/cubic meter.

  What policies were implemented during

what policies were implemented during and after WW1,WW2,Cold war?

  Find the pressure at the forward and rear corners along the

A closed box with horizontal base 6m x 6m and height of 2m is half-filled with water and is accelerated Ax=4.9 m/sec^2 and Ay=-2.4 m/sec. find the pressure at the forward and rear corners along the bottom.

  Set aside the sale of bungalow

Three days later, Abu sees his solicitors and executed the transfer of his said bungalow to Abdul Samad at the said value. Two month later, Abdul Samad expelled Abu from the religious group. Abu now wants to set aside the sale of his bungalow.

  How large of an area would one need to cover with solar cell

Given that the average power plant produces 667 MW of electricity per year, there are 492 coal plants in the US, and a solar constant of 1.361 KW/m^2, how large of an area would one need to cover with solar cells to replace our dependence on coal ..

  How many months will take to have the clay settle 3 inches

A 10 ft layer of normally consolidated saturated clay is found at depth of 20 ft beneath a formation of partially saturated sandy silt with unit weight of 115 lb/ft cubed. Void ratio of the clay is 1.5 and specific gravity is 2.6.

  Determine how many combinations of 2 books can be selected

A customer randomly select 2 of 10 books to purchase. How many combinations of 2 books can be selected

  How to specify the number of plates that can be stored

A plate storage system for a self-serve salad bar in a restaurant. As plates are added to or withdrawn from the stack, the spring force and stiffness are such that the plates always protrude above the tabletop by about 60 mm.

  Which process requires more energy completely vaporizing

Which process requires more energy: completely vaporizing 1 kg of saturated liquid water at 1 atm pressure or completely vaporizing 1 kg of saturated liquid water at 8 atm pressure?

  Write down a mass balance expression for a chemical release

Write down a mass balance expression for a chemical release in a lake given the following: the lake is completely mixed, in-flow and out-flow are equal, degradation of the chemical is occurring through biodegradation (k1) and chemical transformati..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd