Reference no: EM132780873
The Longley Corporation Ltd is considering whether to introduce activity based costing to determine the cost of each of its four products. The company is currently using a conventional costing system whereby the total overhead costs ($1,650,000) are allocated on the basis of the number of direct labour hours. The table below provides information in relation to the cost of each of the products and the extent to which each of the products consume various resources.
PRODUCTS A B C D TOTAL
Output (units) 16000 4000 7000 12000 39000
RESOURCE USE PER UNIT
Raw Materials 3 4 5 10 219000
Labour Hours 2 1 1.5 3 82500
Machine Hours 1 2.5 2 2 64000
UNIT PRODUCTION COSTS
Raw Materials $12 $16 $20 $40 $876000
Direct Labour $28 $14 $21 $42 $1155000
OVERHEAD ACTIVITIES
Machining (per hour) $10 $10 $10 $10 $640000
Engineering Set-ups 3 6 7 4 $60000
Component Receipts 40 55 65 40 $360000
Orders Packaged 13 17 11 9 $280000
Distribution Deliveries 15 35 35 15 $310000
Required:
Problem (a) Calculate the cost of each of the four products if the conventional costing approach is used.
Problem (b) Determine the TOTAL OVERHEAD COST ALLOCATED TO EACH PRODUCT IN RESPECT TO EACH OVERHEAD ACTIVITY if activity based costing were to be used.
Problem c) Determine the TOTAL COST PER UNIT of producing each product if activity based costing were to be used.