Determine the loosening costs in the following situation

Assignment Help Other Engineering
Reference no: EM13753808

21.Track-Type Tractors Dozing

Determine average hourly production of a D8N/8SU (Hydraulic with tilt

cylinder) coal, an average distance of 400m down a 15% grade, using a slot dozing technique. Estimated material weight is 1600 kg/Lm3. Material density =1392 kg/Lm3. Operator is average. Job efficiency is 50 min/hr (check the notes for production curve, table for correction factors).

Uncorrected maximum production     458 Lm3/hr

 

22.Track-Type Tractors Ripping

Determine the loosening costs in the following situation: Machine D11R Tractor with No. 11 single shank ripper in coal Rip spacing 1600mm

Ripper penetration 500mm Rip distance 150m

Rip time           4.32 minutes Manoeuvre time                        0.35 minutes

 

Seismic velocity          2500 m/s (assume this is a realistic value for coal, graphs available to check).

Working rate per hour                         $ 120

What is the effect of the seismic velocity of rock on dozer ripping operations?

 

23.Motor Grader

A Motor grader will travel at an average speed of 10km/hr along a haul road to clear the shoulder for a distance of 20km on one side. It is expected that proper clearing will require three passes, and that the machine has the usual efficiency factor of 0.6. Calculate the production expected from this grader performing this task.

 

24.Dragline

Rated Capacity of a Dragline Bucket

Calculate the rated capacity of a dragline bucket, given the following information:

Height at front = 2m

 Height at rear = 2.25m

Length at top = 5.9m

Length at bottom = 5.4m

Width of front top = 3m

Width of rear top = 3m

 Width of front base = 3m

Width of rear base = 3m

Factor for capacity loss due to bucket design = 0.20

 

25.Wheel Loader

Application                  Dozer pile less than 3m high dump to hopper

Production Required Material

Density

 

232.05 metric ton per hour poorly fragmented rock

1700kg/m3

Loading is constant with a hard level surface for loader manoeuvring. Show calculations and procedure to select an appropriate loader for this task.

Reference no: EM13753808

Questions Cloud

Describe the marketing strategies and tactics : Briefly overview the marketing activities you are involved in implementing. Describe the marketing strategies and tactics your marketing activities relate to
How were marketing and non-marketing personnel briefed : How were marketing and non-marketing personnel briefed and Summaries stakeholder briefings regard ng their implementation roles
Operations and information management : Operations and Information Management Assignment: You are asked to provide a critical discussion on the implementation of lean which addresses the following questions: Is there a best way to implement lean? Are all organisations suitable for lean imp..
Determine the corrected production for the dozer : Determine the corrected production for the dozer for downhill dozing on a 5% slope, with a 50 minute working hour and an average operator as per the correction factors below.
Determine the loosening costs in the following situation : Determine the loosening costs in the following situation: Machine D11R Tractor with No. 11 single shank ripper in coal Rip spacing 1600mm
Define stripping ratio and give three examples : Define stripping ratio and give three examples of the units it may be expressed in.
Operations that are associated with surface mining : List all the major mining operations that are associated with surface mining.
Draw a plan of a typical strip mine : Draw a plan of a typical strip mine showing all operational features and equipment.
Why were oracles sought and recorded in ancient greek world : Why were oracles sought and recorded in the ancient greek world?

Reviews

Write a Review

Other Engineering Questions & Answers

  Draw a ds1 frame and label it in detail

What is the data rate of a single channel on a T1 connection that does not use bit robbing?

  What would be stakeholders in a project

What would be stakeholders in a project

  Make a program that will determine the number of terms

write a program that will determine the number of terms in the series that are needed to approximate the function to a specified accuracy. Prompt the user to enter values for x and for an epsilon, where epsilon is the accuracy desired. Use a funct..

  Spatial and temporal analysis of travel patterns

Spatial and temporal analysis of travel patterns of no-car households - Identify spatial gaps in public transport supply based on social needs of no-car household owners.

  New keynesian model with technology shocks consider a new

new keynesian model with technology shocks consider a new keynesian economy with equilibrium conditions given bywhere

  Gain over temperature ratio

gain and output noise power, Third Order Intermodulation Products, G/T specification, G/T ratio, 2G system architecture, polar orbiting satellites and geostationary satellites, INTELSAT and INSAT satellites, RF communication system

  Design a coal overburden throw

Design a coal overburden throw/cast blast for the situation - Blast length 900 m

  Measurement models goal programming outranking

I would like to use the each following methods to answer the (same question) as attached : VALUE MEASUREMENT MODELS GOAL PROGRAMMING OUTRANKING (ELECTRE I)

  Project management for engineering

economic feasibility of the projec, restrictions are the economics of the project based,  technical feasibility for the project

  Draw on relevant theoretical and management concepts

Draw on relevant theoretical and management concepts covered through the course and describe the problem or issue and critically analyse the issue including considerations of relevant policy and ecological factors

  Design project

Specify a fire wall of appropriate resistance which utilizes masonry. Provide a construction detail of how it is to be constructed. Please note this is a load bearing wall - FSE 445 Design Project

  Calculate the change rates in orbital elements

Provide a qualitative sketch of the co-rotating coordinate system of Neptune/Triton and calculate the location of the origin of this coordinate system.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd