Q. Wichita Carpenter, Inc. has five items of furniture to sand also varnish the next day. The times for these two operations are shown in the subsequent table. Mr. Carpenter supervises all refinishing also does not go home until the last operation is finished.
Order Time (hrs)Sanding VanishingA 2.25 1.25B 2.00 2.25C 1.00 2.00D 2.50 2.00E 1.75 1.75
a) Construct a Gantt chart to describe the total time required to process all five orders given the subsequent sequence: A, B, C, D, E.
Evaluate your priority sequences in a) on average flow time from now, average lateness (with no credit for being early) and average days early (with zero days early for a job that is late).
The line graph for projected monthly sales at Juan's Records shows a steady increase or 5 albums per month during the year. In January, 100 albums were sold. Describe how many are expected to be sold during the year.
Determine the economic order quantity, the reorder point, total annual cost using the EOQ, if cost per tire is $35.00, holding cost is 20% of tire cost per year, demand is 1000 per year ordering cost is $20.00.
You plan to form sub-teams to work every of these elements, every headed by a sub-team leader. describe how would you setup your WBS. Elucidate what are some considerations you made when you decided on this structure.
Explain why did SNOP fall out of favour with healthcare field. Illustrate what are 4 approaches taken by HIM professionals to address complexities brought on by introduction of PPS and DRGs.
Consider an organization where you work or have worked. Discuss the risk balance or policy which senior management plays for a risky project. If you have not worked in such an environment, discuss a present project which has appeared in the news ..
Illustrate what changes in work situation account for increase in productivity and decrease in controlled rejects.
The solution offers step by step guidance on how to formulate the problem mathematically. It comprises a solution to problem instance using Excel Solver.
Your current equipment is fully depreciated and can produce the 2,000 units per year at a margin of only $4.00 per unit. Should you purchase the new equipment. Under illustrate what conditions.
Elucidate what is the optimal solution. describe how many workers should be assigned to every type of machine. Every product needs the subsequent processing times (in hours) on every of 3 machines.
Elucidate what should be the optimal batch size (Q) of clay tigers to be produced also shipped to the stores in every order. Keep 4 digits after decimal points in calculations.
To minimize total cost, explain how many units should be ordered each time an order is placed. If the holding cost per unit was $6 instead of $5, illustrate what would the optimal order quantity be.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd