A compressible 12-ft clay layer beneath a building is overlain by a stratum of sand and gravel and underlain by impermeable bedrock. The total expected primary consolidation settlement of the compressible clay layer due to the building load is 4.60 in. The coefficient of consolidation (cv) is 9.04 X 10^(-4) inches^(2)/minute.
1) How long will it take for 90% of the expected total primary consolidation settlement to take place?
2) Compute the amount of primary consolidation settlement that will occur in 1 year.
3) How long will it take for primary consolidation settlement of 1 inch to take place?
An incompressible fluid flows horizontally in the x-y plane with a velocity given by v = 20 (z/h)^(1/3),where z and h are in meters and h is a constant.
A rectangular channel leading from an upstream lake has a bottom width of 20 ft, bottom slope of 0.0002, a Manning roughness factor of 0.016, a discharge of 403 cfs, and normal depth of 6.24 ft.
Saturated liquid water at 1.0 MPa is throttled adiabatically to a pressure of 0.4 MPa. If the change is kinetic energy is negligible, what percentage of the water evaporates during this throttling process?
Water enters a very wide rectangular channel (Manning's n = 0.0149) at a velocity of 12.2 ms-1 and a depth of 0.61 m. An H3 curve forms downstream and the water jumps to a depth of 2.4 m some distance downstream.
Calculate the percentage of change in total volume with respect to its initial volume when a specimen of this clay is completely dried from a water content of 80%. Assume that the clay remains saturated from liquid limit to shrinkage limit.
A wrought iron water line connecting two reservoirs at 20°C has a length of 1500 m, a diameter of 75 cm, two elbows (90º, long-radius, flanged), a fully open gate valve, and a reentrant pipe entrance.
Provide the function prototype for the following function if it is to be declared as a friend function of class Planet. Include the class declaration and the proper access attribute, but you are not required to add any additional class data or fun..
A trough is 5 feet long and 1 foot high. The vertical cross-section of the trough parallel to an end is shaped like the graph of y=x6 from x=?1 to x=1 . The trough is full of water. Find the amount of work in foot-pounds required
Compute the water table profile drawn in part B. Provide a detailed description of your methodology, and limit your solution to include only 4 image wells. Plot the profile, and provide drawdown amounts at X = -400 m, -200 m, -100 m, 100 m, 200 m,..
The overpass structure is to be level, centered 26 feet above the railroad, and 180 feet long. How much existing highway (in feet) must be reconstructed to provide appropriate vertical alignment
The boat is travelling along a circular path with a speed v=(0.0625t). Determine the magnitude of its acceleration when t=10s
The pressure in the steam condenser of a nuclear power plant is 1 psia. Calculate the absolute pressure head, the gage pressure, the gage pressure head, the vacuum pressure, and the vacuum pressure head under standard conditions.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd