Compute stefanis total standard cost per unit

Assignment Help Accounting Basics
Reference no: EM131589461

Assignment: Standard Costs and Balanced Scorecard

Q1. Stefani Company has gathered the following information about its product.

Direct materials. Each unit of product contains 4.5 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.5 pounds. Materials cost $5 per pound, but Stefani always takes the 2% cash discount all of its suppliers offer. Freight costs average $0.25 per pound.

Direct labor. Each unit requires 2 hours of labor. Setup, cleanup, and downtime average 0.4 hours per unit. The average hourly pay rate of Stefani's employees is $12. Payroll taxes and fringe benefits are an additional $3 per hour.

Manufacturing overhead. Overhead is applied at a rate of $7 per direct labor hour.

Instructions - Compute Stefani's total standard cost per unit.

Q2. Lewis Company's standard labor cost of producing one unit of Product DD is 4 hours at the rate of $12.00 per hour. During August, 40,600 hours of labor are incurred at a cost of $12.15 per hour to produce 10,000 units of Product DD.

Instructions -

(a) Compute the total labor variance.

(b) Compute the labor price and quantity variances.

(c) Repeat (b), assuming the standard is 4.1 hours of direct labor at $12.25 per hour.

Q3. Byrd Company produces one product, a putter called GO-Putter. Byrd uses a standard cost system and determines that it should take one hour of direct labor to produce one GO-Putter. The normal production capacity for this putter is 100,000 units per year. The total budgeted overhead at normal capacity is $850,000 comprised of $250,000 of variable costs and $600,000 of fixed costs. Byrd applies overhead on the basis of direct labor hours.

During the current year, Byrd produced 95,000 putters, worked 94,000 direct labor hours, and incurred variable overhead costs of $256,000 and fixed overhead costs of $600,000.

Instructions -

(a) Compute the predetermined variable overhead rate and the predetermined fixed over¬head rate.

(b) Compute the applied overhead for Byrd for the year

(c) Compute the total overhead variance.

Q4. Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017.

Costs and Production Data

Actual

Standard

Raw materials unit cost

$2.25

$2.10

Raw materials units used

10,600

10,000

Direct labor payroll

$120,960

$120,000

Direct labor hours worked

14,400

15,000

Manufacturing overhead incurred

$189,500


Manufacturing overhead applied


$193,500

Machine hours expa..ted to be used at normal capacity


42,500

Budgeted fixed overhead for June


$55,250

Variable overhead rate per machine hour


$3.00

Fixed overhead rate per machine hour


$1.30

Overhead is applied on the basis of standard machine hours. Three hours of machine time are required for each direct labor hour. The jobs were sold for $400,000. Selling and administrative expenses were $40,000. Assume that the amount of raw materials purchased equaled the amount used.

Instructions

(a) Compute all of the variances for (1) direct materials and (2) direct labor.

(b) Compute the total overhead variance.

(c) Prepare an income statement for management. (Ignore income taxes.)

Reference no: EM131589461

Questions Cloud

Examples of competitors : Firms like Wal-Mart, Target and K-Mart are often given as examples of competitors. Ironically, these firms are not what an economist
Diminished by entry in the long run : If a monopoly firm is earning profits, how much would you expect these profits to be diminished by entry in the long run?
Discuss the current importance of the miranda doctrine : Discuss the merits and current importance of the Miranda doctrine. What are the benefits and costs of this doctrine to society
Calculate quantity demanded and quantity supplied : Use Excel to calculate quantity demanded and quantity supplied for p = $70, 75,80....140 (in $5 increments).
Compute stefanis total standard cost per unit : ACC560 Assignment: Standard Costs and Balanced Scorecard. Compute Stefani's total standard cost per unit
What do you see as their strengths and weaknesses : WWhat does synthesize mean within the context of Bloom's taxonomy and Granello's 2001 article, "Promoting Cognitive Complexity in Graduate Written Work"?
Discuss a case concerning gay marriage : Discuss this case as it demonstrates the appellate process. How did it get to the Supreme Court
Excavates roadside ditches for laying drainpipe : Dirt Diggers (DD) is an excavating firm that excavates roadside ditches for laying drainpipe. Its output follows the following production function:
Is the organization of the work an important factor : Is the organization of the work an important factor? Does its organization help me understand it, hinder my understanding, or neither?

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd