Calculate the schedule and cost variances for each subtasks

Assignment Help Accounting Basics
Reference no: EM132376755

Cost Management & Control

Question 1

• BCWS (PV) = $1000
• BCWP (EV) = $800
• ACWP (AC) = $700
• What is the status of the project?

Question 2
• A project is scheduled to spend $100K for each of the first four weeks of the project. The actual expenditures at the end of week four are $ 325K. What would be the status of the project if the budgeted cost of the performed work is
$300K.

Question 3

1170_figure.jpg

Question 4

827_figure1.jpg

Question 5

903_figure2.jpg

Question 6

1031_figure3.jpg

Question 7

In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project, and comment on project performance.

Question 8
On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI and SPI for the project. What is your assessment of the project on day 51?

Question 9
For the subtasks shown in the table below
a. Calculate the schedule and cost variances for each subtasks
b. Calculate the estimate at completion (EAC)

Task

Status

BCWS

BCWP

ACWP

SV

CV

1

Completed

100

100

100

2

Completed

50

50

55

3

Completed

50

50

40

4

Not Started

70

0

0

5

Completed

90

90

140

6

Not Started

40

0

0

7

Started

50

50

25

8

Not Started

0

0

0

Total

 

450

340

360


Question 10
• The data identified below was listed in a project's latest status report:
- BCWS= $36,000
- BCWP= $30,000
- ACWP= $33,000
- BAC= $120,000
• Original length of the project = 10 months Using these data answer the following:
a. What are the values for CPI and SPI
b. What is the Expected cost at Completion (EAC)?
c. How much money will be needed from time of the report to complete the project?
d. What is the cost variance at completion (VAC)?
e. Using SPI, what is the new expected length of project?

Reference no: EM132376755

Questions Cloud

How much depreciation should fun travels airline : If the plane travels 52,000,000 miles the first year, how much depreciation should Fun Travels Airline record under the units-of-production method?
Enforce governance and compliance in organization : What is governance and compliance? Why is it necessary to enforce governance and compliance in an organization?
What should be the average beta of the new stocks : What should be the average beta of the new stocks added to the portfolio? Do not round intermediate calculations. Round your answer to two decimal places.
Required rate of return : Assume that the risk-free rate is 4% and the required return on the market is 13%. What is the required rate of return on a stock with a beta of 1.4?
Calculate the schedule and cost variances for each subtasks : Managing Projects - Calculate the schedule and cost variances for each subtasks and Calculate the estimate at completion (EAC)
Analysis of each of the steps in DDoS attack scenario : Use the four steps of the NIST computer security process to write a summary and analysis of each of the steps in a DDoS attack scenario.
Two potential investments in the tv manufacturing industry : You are considering two potential investments in the TV manufacturing industry. PLASMA Corporation has had a 35% annual growth rate and a current price
How much money must emily set aside now to achieve that goal : How much money must Emily set aside now to achieve that goal? It may be help-ful to construct a timeline to visualize the details of this problem.
Establishment of federal-state and local government laws : What are the issues and root causes that necessitates the enactment and/or establishment of Federal, state and local government laws,

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd