Question 1. The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.

Activity Duration Predecessors Resources

A 4 days -- 1 research engineer

B 3 days A 1 marketing specialist

C 5 days A 1 design engineer

D 3 days A 1 design engineer

E 3 days B 1 prototype builder

F 2 days D 1 test engineer

The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources are involved, and the quantity required.

(b) Given the owner's stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?

Question 2. The following data were obtained from an information systems project to upgrade and expand a local area network.

Activity Duration Predecessors Task Budget

A 3 days --- $4,920

B 6 days --- $7,680

C 3 days A $15,140

D 2 days B $4,980

E 3 days B $5,630

F 2 days C and D $2,270

At the end of Day 7, the status of the project is as follows.

Activity % Complete Actual Cost

A 100% $4,200

B 100% $8,740

C 100% $18,250

D 65% $2,600

E 10% $560

F 0% $0

(a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.

(b) As project manager, write a brief summary of the status of the project at this time.

Question 3. You are project manager for three different projects.

Project A: This project is in the execution stage of the project. It is behind schedule by 6 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed.

Project B: This project is behind schedule by 10 weeks. It was to have been completed in 2 months. The sponsor has additional funds to help complete the project on time if needed but does not want to increase risk to the project.

Project C: This project is scheduled to take 18 weeks to complete. You are in the planning stage of the project. You need to reduce the schedule for this project by 5 weeks. This project has a number of predecessors that were created by the project team's preference. The sponsor insists on having all the work done on time without unduly increasing risk or costs to the project.

For each of the project above, choose an appropriate schedule compression technique. Explain your choice.

Reference no: EM13769795

Questions Cloud

Discuss similarities anof two characte in given article : discuss similarities and differences of two characters. Compare and contrast essay about Don Anselmo from Juan A. A. Sedillo's "The Gentleman of Río en Medio" and Mrs. Higgins from Morley Callaghan's "All the Years of Her Life."
Create one z-specification for system : Create one (1) short Z-specification for this system using Visio or an equivalent such as Dia. Note: The graphically depicted solution is not included in the required page length.
Matrix of an irreducible recurrent markov chain : Suppose P = ? Pij ? is the transition probability matrix of an irreducible recurrent Markov chain {Xn}. Use the supermartingale convergence theorem (see Remark 5.1) to show that every nonnegative solution y={y(i)} to the system of inequalities , (MIS..
Hazards chemical-polymeric or explosive material : Describe an incident (fire, spill, explosion, etc) you have experienced (or research one on the Internet, professional journal, or scientific magazine article) that involved a polymeric or explosive material(s) and required mitigation.
Calculate the cost and schedule variances : Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.(b) As project manager, write a brief summary of the status of the project at this time.
Advantages and disadvantages of an investigative task force : What are the advantages and disadvantages of an investigative task force? Who, or what entities, should be involved in the decision to create an investigative task force? Assuming, on balance, that you favor a task force approach, what difficulties d..
Presto printing company sales for the month : Question 1:  Find the mean, median and mode of the following:  Presto Printing Company sales for the month of February.  (NOTE: The company is closed on Sundays.)
What does a woman''s appearance say about her personality : What does a woman's appearance say about her personality or worth? What does a man's appearance say about his personality or worth?
Determine the profile of the investor : Determine the profile of the investor for which this company may be a fit, relative to that potential investor's investment strategy. Provide support for your rationale.

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Validate the information

When all the information is valid, a confirmation screen is displayed. The operator visually confirms that the data are correct and either accepts the transaction or cancels it.

  Stage of ec purchase decision-making process

Banner advertising on Websites helps trigger a realization taht there is a gap between reality and a desired state, which occurs in the ______ stage of the EC purchase decision-making process.

  Write a brief statement on how you would address components

Assume that a security model is needed for the protection of information i your class. Using the CNSS model examine each of the cells and write a brief statement on how you would address the components represented in that cell.

  What is the addressing mode of the instruction

What is the addressing mode of the instruction

  Write a program that translates a name into pig latin

Use the pig latin rule of moving the first letter to the end of the word and adding "ay". Output the pig latin name on the screen. The name "Walt" translates into pig latin Altway. Karen to Arenkay, Steve to Tevesay.

  Explain how the web design department

Explain how the web design department will adhere to a code of ethics available for stakeholders.

  Passing an "in out" parameter to a procedure

In Ada, when passing an "in out" parameter to a procedure, the system is allowed to use either pass-by-reference or pass-by-value-result as it sees fit. Why?

  Define the balance for some of the accounts

Define the balance for some of the accounts to be less than $500 and some to be more than $500. After you have created your accounts print your account list, then withdraw $500 from all accounts and redisplay your list.

  Explain process of extracting contours from edge image

Assume that the edge points in an image are extracted using a robust edge detection. Explain the process of extracting the contours from this edge image.

  In the context of network management how can the similar

question 1. in the context of network management how can the same manageability features contribute simultaneously to

  Generate dropdown to create example c++ code

Submit your C++ source code that you generated from RAPTOR with comments added to each line or where necessary to explain program flow. Also submit the RAPTOR file (flowchart) of your working program.

  Design a program that ask for the price of each item

Design a program that ask for the price of each item, and then displays the subtotal of the sale, the amount of sales tax and the total. Assume the sales tax is 6 percent. Need help with this question.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd