A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.Answer

There are two paths in this network.

There are four paths in this network.

There are five paths in this network.

There are 25 paths through this network.