What is the estimated cost of the whole project, Project Management

Assignment Help:

Question 1:

(a) Using information from Table 1, build a network diagram for the project.

(b) Perform a Forward Pass on the network diagram and deduce the duration of the project.

(c) What is the estimated cost of the whole project?

(d) Perform a Backward Pass on the network diagram and deduce the float for each task.

(e) What can you say about flexibility in the project in the light of the above?

Question 2:

(a) What is the rationale behind earned value analysis in project monitoring and how is it helpful?

(b) Using information in Table 2, calculate the schedule variance and cost variance for each task in the project at timenow 30 days

(c) In light of calculations above, comment on the progress of the project with respect to the schedule. What is the expected duration of project if started (but incomplete) tasks continue on the same trend and if tasks which have not started yet proceed as per schedule?

(d) In light of calculations above, what is the expected cost of the project now?

(e) What corrective action would you recommend at this stage of the project?


Related Discussions:- What is the estimated cost of the whole project

What do you mean by post completion report, What do you mean by post comple...

What do you mean by post completion report? The post completion (PC) report: This report would be created at the closing or finish stage of a project. Post completion rep

Elements of total quality management, ELEMENTS OF TOTAL QUALITY MANAGEMENT ...

ELEMENTS OF TOTAL QUALITY MANAGEMENT (TQM): The philosophy of Total Quality Management is based on understanding customer needs and improving customer service and satisfaction

Construct a network diagram showing the critical path, ST is the operations...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

Benefits of Group Technology, Benefits of Group Technology 1.Reduced F...

Benefits of Group Technology 1.Reduced Flow Times: Compared to the earlier process layout, there are very few halts. Hence flow times are reduced considerably. 2.Process Tim

Explain about the term performance appraisal in organization, Explain about...

Explain about the term Performance Appraisal in organization. Performance Appraisal: This is a systematic and impartial assessment of an worker’s performance on the assign

Define incremental approach of system testing, Define the incremental appro...

Define the incremental approach by system testing. System test: In system testing, the developers are checking which the system gives the functionality described by the u

Processes and customer involvement, Processes and Customer Involvement ...

Processes and Customer Involvement Many processes are designed keeping in mind that value is provided by involving the customer in the delivery of the final product.  The invo

When is employer not liable to pay compensation to employee, When is an emp...

When is an employer not liable to pay compensation to an employee? Compensation: An employer is not liable to pay compensation to an employee under the given circumstanc

What are the benefits of doing a job safety analysis, Question: A sewer...

Question: A sewer line is to be connected to a school. This work will be carried out in a 2.4 meters deep excavation and will be routed through the playground, which was once

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd