What do you mean by the term dependency, Project Management

What do you mean by the term dependency? How can project dependencies be shown for planning reasons?

Dependency arises when, for illustration, task or deliverable 'A' should be completed before task or deliverable 'B can be begun. In a complicated project, the analysis of dependencies assists to classify streams of work which can be performed in parallel, therefore shortening the overall duration of the project. The usual way which dependencies are represented is onto a dependency diagram, also termed as a network diagram or a PERT chart. Microsoft Project also demonstrates dependencies on the bar/Gantt chart through vertical connections among task bars but it can get somewhat confusing onto a huge or complicated project.

Posted Date: 9/2/2013 7:44:29 AM | Location : United States







Related Discussions:- What do you mean by the term dependency, Assignment Help, Ask Question on What do you mean by the term dependency, Get Answer, Expert's Help, What do you mean by the term dependency Discussions

Write discussion on What do you mean by the term dependency
Your posts are moderated
Related Questions
Number of post-release defects (found by clients in field operation), categorized by level of severity Ratio of defects found internally prior to release (by inspections and tes



You are not expected to submit a formal proposal. However, you will be able to access Subject Tutors via HenleyConnect and you may seek feedback from them as to the suitability and

Question : (a) What are the distinguishing characteristics of a project? (b) What are the four types of consequences of risk? (c) Explain what you understand by the term

C Consultancy Company gives management consultancy to a range of organisations.  It employs staff who have dissimilar industry backgrounds and who also offer dissimilar specialisms

What are the disadvantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager

Product/Service and Volume Flexibility Ability to respond fast to the customer's needs known as flexibility.Two forms of flexibility are product/ Service and volume flexibilit

Risk Matrix Terminology  It is a term where table used in risk analysis in which rows show the risks and columns show their likelihood (probability) of occurrence and their imp

Combined Layout The application of the principle of product layout, process layout or fixed location layout in their strict meanings is difficult to come across. A combination