Show the silt curtain touching seabed, Civil Engineering

Assignment Help:

Q. Show the Silt curtain touching seabed?

Silt curtains are impermeable vertical barriers extending from seawater surface to their designed depths. Curtains are held in a vertical position by carrier float on their top and a curtain weight at their bottom. A tension cable is designed at carrier float to resist stresses incurred by currents. Furthermore silt curtains are anchored to seabed to hold them in designed configuration. 

Essentially the depth of silt curtains must not be so long and touch the seabed since the bottom segment of the silt curtains will be trapped inside newly accumulated sediment, so resulting in the sinking of curtain. It is problematic to remove these sunken curtains. Furthermore reversal tidal and current actions can cause movement of bottom region of curtains that stir up the settled suspensions and create extra turbidity.


Related Discussions:- Show the silt curtain touching seabed

cement, what is the manufacturing process of regular portland cemen

what is the manufacturing process of regular portland cement

Vibrocoring in marine ground investigation, Vibrocoring in marine ground in...

Vibrocoring in marine ground investigation If only shallow marine ground geotechnical information is essential for design purpose, vibrocoring is certainly a good choice for s

Dynamic force transfer test of shock transmission unit, Define Dynamic Forc...

Define Dynamic Force Transfer Test of Shock Transmission Unit? This test mainly prove the lock up capability of the device. The STU shall be loaded in tension from zero to the

Material engineering assignment, select three materials metal and non meala...

select three materials metal and non mealat at least one of the selected materials shold change its property

Calculate the annual cost of alum - coagulation, Incoming water contains 2....

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO 3 - ). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and

CAD IN CIVIL ENGINEERING DRAWING LAB, EXPLAIN THE PROCEDURE FOR PREPARATIO...

EXPLAIN THE PROCEDURE FOR PREPARATION OF DRAWING USING AUTOCAD FOR RAPID SAND FILTER

Methods of design of prestressed concrete member, Methods of design of pres...

Methods of design of prestressed concrete member What are different approaches or methods of design of prestressed concrete members? What are important considerations  in th

Premix road, plz tell me the ratio of sand,aggregate,and asphalt.pl tell me...

plz tell me the ratio of sand,aggregate,and asphalt.pl tell me the mm of aggregate

Verify the coefficient of elastic uniform compression, Verify the coefficie...

Verify the coefficient of elastic uniform compression if a vibration test on a concrete block of 1 m cube gave a resonant frequency of 36 Hz in vertical vibration. The weight of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd