QuestionIn erection of false work, for a rectangular panel inside a false work would it be braced all along two diagonals?
AnswerWhile a rectangular panel is focus to the eccentric load or the lateral load, it tends to distort into a parallelogram with one diagonal shortening and other elongating.
Supposedly, it is enough to brace along one of diagonals if one diagonal is only allowed to brace inside the rectangular panel, it must be not braced in diagonal in compression as under severe lateral loading diagonal might buckle leading to failure of structure. But, in actual situation lateral loads could come from both sides of panel and therefore it should be there braced in both diagonals.
define couple
Sight Distance: Sight distance is the distance along a road at which a driver has a visibility of objects and can safely stop his vehicle or overtake another vehicle. Sto
Classification Based on Mode of Growth: On the basis of mode of growth trees are classified as (a) Exogeneous and (b) Endogeneous (a) Exogeneous Trees: These trees grow outwa
Using an optical square how would you perform a rectangular tie?
Q. What is Preset in bridge bearing? 'Preset' is a method to decrease the size of upper plates of sliding bearings in order to save cost. Normal length of an upper bearing plat
design of treatment plant
A retaining wall with its face inclined at 75° with horizontal is 10 m high and retains soil inclined at a uniform surcharge angle of 10°. If the angle of internal friction of the
Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below. Assume that the intersection wi
Q. How can a temporary diversion to laid a cross flowing river in case of disruption to rail traffic over a major bridge lasting over 6 months. Ans.- Temporary diversion
Cut and Fill Calculation Using Cross Section Method
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd