Project contracts, Project Management

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  

Posted Date: 9/27/2012 7:41:08 AM | Location : United States







Related Discussions:- Project contracts, Assignment Help, Ask Question on Project contracts, Get Answer, Expert's Help, Project contracts Discussions

Write discussion on Project contracts
Your posts are moderated
Related Questions
When JF persuaded a leading retail supermarket chain to trial her 'home-made' chocolate dessert range she could not have anticipated how well it would sell. Now a year on she has f

o Is the domain model a complete representation of the relevant objects in the problem domain? o Are associations between problem domain objects captured? o Are specializatio

Define the Design phase of the project management. Design phase:   The list of needs which is developed within the definition phase can be utilized to make design alte

1.  Main functions: The web based site will be fully enabled for viewing via iPad and be fully accessible at the cafe seating only.  The menu will be fully automated to allow order

Each group is to produce a strategy development report on the Red Ocean strategy they will submit in the Blue Ocean Strategy Simulation Game Red Round, first year. Each group will

Question 1: (a) Elaborate on the drivers of the ‘Age of Project Management'. (b) Differentiate between the terms ‘Project Management' and ‘Line Management'. (c) Expla

Organisational Structures The project organisational structure facilitates coordination and implementation of project activities. It should be designed to include the essential

MBO process MBO is the process of collaborative goal setting between the manager and his or her subordinates. It assumes that goals are consistent or compatible from the highes

Arvin Automotive, a company that makes muffler assemblies for the Big Three, is committed to the use of Kanban to pull material through its manufacturing cells. Arvin has designed

Q.  What do project managers do? First of all project managers have to take responsibility for leading the project effort towards the stated and agreed upon goals and objective