Project contracts, Project Management

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  

Posted Date: 9/27/2012 7:41:08 AM | Location : United States







Related Discussions:- Project contracts, Assignment Help, Ask Question on Project contracts, Get Answer, Expert's Help, Project contracts Discussions

Write discussion on Project contracts
Your posts are moderated
Related Questions
Define the inventory procurement cost and inventory carrying cost. Inventory Procurement Cost and Inventory Carrying Cost: Inventory is a detailed list of such movable it

Normal 0 false false false EN-IN X-NONE X-NONE

Question 1: (i) What are the various aspects you would consider while planning to build a new international airport? (ii) With relevant arguments discuss the necessity or

What do you mean by fixed costs? Fixed Cost: Cost may be described as the amount of expenditure incurred upon, or attributable to a specified thing. Fixed costs are such

MIL standards were introduced in 1974. In 1975 BSI 5179 in these parts drawn from the contents of defiance standards 05-21 series. This standard was not written in man

Describe different types of supporting project activities for estimating. Estimate the given supporting project activities are as follows: 1.    Project management 2.    Team lea

Do you think Acorn’s solution was good? Why or why not?

QUESTION (a) The project organization structure clearly identifies the relationship between project team members through defining their duties, responsibilities and lines of au

Rules Rules are prescriptions for how members of a group ought to or not to behave. They are specific and allow no discretion. In any group situation, and more so in the formal

Strategy is developed at different levels in large organisations. The process starts with the corporate strategy which is then translated into the strategy for the business divisio