Project contracts, Project Management

Understanding Project Contracts 

Project contracts invariably involve construction and therefore we will discuss contracts necessarily involving construction in this section. In addition to construction, other areas of work like design, engineering and procurement are involved in project contracts, but all these up front areas of work have to be followed by construction and subsequent commissioning of the project. In this section we will discuss about contracts combining some or all of these areas. 

A construction contract between Principal and Contractor can be formed by: 

  •   Negotiation. 
  •   Competitive tendering. 
  •   Combination of both. 

Mode 1  contract is formed by direct negotiation by the principal with one contractor. This mode is adopted only when work is very urgent, or when the principal believes that only one contractor is capable of building the project, or when the principal believes that time and money spent on tendering is wasteful. This  is practically non existent in government contracts, but can occur, although rarely, in private industry.  

Mode 2 competitive tendering is inviting for bids from several contractor to extract the best performance from the contractors. Competitive tendering exists invariably in public contracting. 

Mode 3  is an approach to negotiate with two or three bidders for securing the best possible price. When this is a post-bid negotiation, there is a danger that the lowest price bid agreed in the contract may not be realised on account of the contractor as he may have been coerced to accept a low price for getting the contract. The danger is that the cost risk gets transferred either to the principal through claims under the contract or to subcontractors.

Whatever be the mode of contracting adopted, we will now discuss contracts from the viewpoint of the scope of design and construction. When the two areas of work that is, design and construction is involved in a project, a third dimension of work viz. coordination necessarily arises. This combination means that the project manager must thoroughly understand the contracting strategies that can be adopted to ensure the ultimate achievement of the project deliverables. 

There are two broad methodologies in this section viz D-B-B (Design, Bid, Build) and D-B (Design and Build).  

Posted Date: 9/27/2012 7:41:08 AM | Location : United States

Related Discussions:- Project contracts, Assignment Help, Ask Question on Project contracts, Get Answer, Expert's Help, Project contracts Discussions

Write discussion on Project contracts
Your posts are moderated
Related Questions
Read the BEC case study on pages 126–129 of the textbook, and perform the following tasks:   Create a feasibility report for the project in a Word document. Create

Computerized Relative Allocation of Facilities Technique (CRAFT): The previous difficulty can now be alleviated because of the availability of computer software packages like

Question 1: Explain the force Content and Structure of People Management System Explanation of structure Explanation of content Balance between content and struct

explain any ten management inervention

Question: (a) (i) What do you meant by "a change of scope" in a project? (ii) Unplanned changes (for e.g, unplanned expenses) might occur during the implementation phase of

For an initial secure order under HUD guidelines, are you authorized to remove exterior debris automatically?

QUESTION (a) The project lifecycle refers to a logical sequence of activities to accomplish the project's goals and objectives. Regardless of the scope or complexity any projec

You are an accountant who has been approached by two people, Bill and Steve, for some advice.  Bill and Steve are planning to open a furniture store in Toronto.  They plan to rent

How quickly are group norms established in a meeting?