Perform a status assessment of the project iteration, Project Management

Assignment Help:

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the iteration plan. All activities must result in some change to the project's artefacts - this is the only possible measurement of progress. Back up claims of successful activity completion by including the generated or updated artefact with the status assessment.

Generate another iteration plan for the second inception iteration (IIP2). This iteration plan must aim to achieve the Life Cycle Objective Milestone by April 8. Plan IIP2 AS IF all activities in IIP1 were successful. Then ADD all incomplete and unsuccessful work items in IIP1 to the work scheduled for IIP2. This is necessary to avoid project schedule slippage.

Also, since Inception Iteration 2 completes the Inception phase, you must also plan to review the Inception phase and the project as a whole in 2 further status assessment documents. This is because the phase objectives are at a higher level than the iteration objectives, and require separate assessment. The same applies to project goals compared to phase goals. Allow perhaps ½ to 1 hour for these extra assessment tasks combined.


Related Discussions:- Perform a status assessment of the project iteration

Communication strategy, Communication Strategy: Communication str...

Communication Strategy: Communication strategy, beginners as a concept in the 1980s by communication expert Mary Munter, provides as the basis for all management communic

Cobit, compare cobit 4.1 with cobit 5

compare cobit 4.1 with cobit 5

What is a successful project, Q. What is a successful project? Since ea...

Q. What is a successful project? Since each project has an element of newness about it there will be difficulties and risks to be surmounted. These require decisions and may be

Explain portfolio management in project, Question: (a) Project plans ar...

Question: (a) Project plans are created in knowledge areas throughout the different phases of the project life cycle and are subsidiary components of the overall project manag

Characteristics of process planning, Characteristics of Process Planning ...

Characteristics of Process Planning Since a process is required to manufacture a product it is necessary to plan the process. Process planning comes after it has

What planning concerns in project management, Question 1: Harvey Maylor...

Question 1: Harvey Maylor discusses a ‘generic' life cycle to help in project management. Explain what is meant by project life cycle and critically discuss the benefits that

Determine the analogy method of estimating, The analogy method of estimatin...

The analogy method of estimating is frequently used to produce broad-brush evaluates at the start of a project. Why this method is mainly suited to such application? Determinin

Phases of value engineering process, P hases of value engineering process ...

P hases of value engineering process I nvestigation phase: This phase investigates the background information, the technical input reports, the field data, the functiona

Describe the major stages of hearts and minds programme, You should design ...

You should design a ‘hearts and minds’ programme associated with the implementation of a modern system for the recording and management of stock within a book-publishing company an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd