Perform a status assessment of the project iteration, Project Management

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the iteration plan. All activities must result in some change to the project's artefacts - this is the only possible measurement of progress. Back up claims of successful activity completion by including the generated or updated artefact with the status assessment.

Generate another iteration plan for the second inception iteration (IIP2). This iteration plan must aim to achieve the Life Cycle Objective Milestone by April 8. Plan IIP2 AS IF all activities in IIP1 were successful. Then ADD all incomplete and unsuccessful work items in IIP1 to the work scheduled for IIP2. This is necessary to avoid project schedule slippage.

Also, since Inception Iteration 2 completes the Inception phase, you must also plan to review the Inception phase and the project as a whole in 2 further status assessment documents. This is because the phase objectives are at a higher level than the iteration objectives, and require separate assessment. The same applies to project goals compared to phase goals. Allow perhaps ½ to 1 hour for these extra assessment tasks combined.

Posted Date: 3/26/2013 2:19:48 AM | Location : United States







Related Discussions:- Perform a status assessment of the project iteration, Assignment Help, Ask Question on Perform a status assessment of the project iteration, Get Answer, Expert's Help, Perform a status assessment of the project iteration Discussions

Write discussion on Perform a status assessment of the project iteration
Your posts are moderated
Related Questions

Question 1: (a) What is a TNA, and why is it conducted? (b) What are the key stages to conduct a Training Needs Assessment? (c) Having undertaken an organization-wide TNA

M a n a ging Project Quality as per PMI Project Management Institute (PMI) is a global organisation for the project management profession; it is engaged in setting professi

S is enrolled on T Company's management development programme.  Although S has a financial background, the aim of the management development programme is to help him to gain a bett

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the it

Limitations of Group Technology or Cellular Manufacturing Group Technology is a great concept. But all good concepts do have their own limitations and need proper care in their

what is a benefit of a kaizen event?


Dr. Sherry Bird is employed by Dental Associates. Dental Associates recently installed a computerized job-order costing system to help monitor the cost of its services. Each patien

Explain about the process of managing risk. A process of managing risk: 1. Risk committee establish to address risk issues categorised for example usual risk audits, to estimat