Perform a status assessment of the project iteration, Project Management

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the iteration plan. All activities must result in some change to the project's artefacts - this is the only possible measurement of progress. Back up claims of successful activity completion by including the generated or updated artefact with the status assessment.

Generate another iteration plan for the second inception iteration (IIP2). This iteration plan must aim to achieve the Life Cycle Objective Milestone by April 8. Plan IIP2 AS IF all activities in IIP1 were successful. Then ADD all incomplete and unsuccessful work items in IIP1 to the work scheduled for IIP2. This is necessary to avoid project schedule slippage.

Also, since Inception Iteration 2 completes the Inception phase, you must also plan to review the Inception phase and the project as a whole in 2 further status assessment documents. This is because the phase objectives are at a higher level than the iteration objectives, and require separate assessment. The same applies to project goals compared to phase goals. Allow perhaps ½ to 1 hour for these extra assessment tasks combined.

Posted Date: 3/26/2013 2:19:48 AM | Location : United States







Related Discussions:- Perform a status assessment of the project iteration, Assignment Help, Ask Question on Perform a status assessment of the project iteration, Get Answer, Expert's Help, Perform a status assessment of the project iteration Discussions

Write discussion on Perform a status assessment of the project iteration
Your posts are moderated
Related Questions
How is Inventory procurement costs expenditure connected? Inventory procurement costs that consists of expenditure connected along with as a. Its Receiving quotations b.


Kilbridge and Wester Method of line Balancing Kilbridge and Wester propose this method. Here numbers are assigned to each operations describing how many predecessors it has.

Project management Process According to PMBoK, project management is the application of knowledge, skills, tools and techniques to project activities in order to meet or exceed

How is Economic Order Quantity depended on costs? Economic Order Quantity depends on two costs as illustrated below: - Inventory procurement costs that consist of expenditur

Question: (a) A famous man once said: "If you do not know where you are going, how will you know how you will reach your destination". This sentence captures the importance of

Tools and Techniques of layout planning - Line Balancing Line balancing is the phases of assembly line study that nearly equally divides the work to be done among the workers

Study of the Load impact on power flow with (constant power, constant impedance, constant current, induction motor) and use the PowerWorld simulator.

Question 1: Distinguish between innovation and renovation within the parameters of facilities planning and design. Question 2: Although security and safety at the work

How are the management skills required for a successful manager? Management Skills: The skills needed of a successful manager, while he is working into a industry,