Perform a status assessment of the project iteration, Project Management

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the iteration plan. All activities must result in some change to the project's artefacts - this is the only possible measurement of progress. Back up claims of successful activity completion by including the generated or updated artefact with the status assessment.

Generate another iteration plan for the second inception iteration (IIP2). This iteration plan must aim to achieve the Life Cycle Objective Milestone by April 8. Plan IIP2 AS IF all activities in IIP1 were successful. Then ADD all incomplete and unsuccessful work items in IIP1 to the work scheduled for IIP2. This is necessary to avoid project schedule slippage.

Also, since Inception Iteration 2 completes the Inception phase, you must also plan to review the Inception phase and the project as a whole in 2 further status assessment documents. This is because the phase objectives are at a higher level than the iteration objectives, and require separate assessment. The same applies to project goals compared to phase goals. Allow perhaps ½ to 1 hour for these extra assessment tasks combined.

Posted Date: 3/26/2013 2:19:48 AM | Location : United States







Related Discussions:- Perform a status assessment of the project iteration, Assignment Help, Ask Question on Perform a status assessment of the project iteration, Get Answer, Expert's Help, Perform a status assessment of the project iteration Discussions

Write discussion on Perform a status assessment of the project iteration
Your posts are moderated
Related Questions
What do you mean by Gates and Milestones? Gates and milestones: Milestones are a completion of main interim objectives for a project for example the key stages of a pro

Differences between wbs and product breakdown structure, Project Management


Question: (a) "TQM requires the whole organization to adopt the culture of quality. In a TQM organization quality will dictate the decisions, tasks and processes." In the lig

outline role of the project manager

what is the maniipulated variable in a wood experiment

Backward Integration A strategy in which an organization builds competitive benefits by controlling the provider of the raw materials needed to make its products.

Definitions of management Several definitions of management have been given by different scholars. Mary Follet defined management as "having work done through others." Another

The product development cycle starts with the assessment of the customers needs and ends when the design is finally released for bulk production. The main steps in th

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this s