Perform a status assessment of the project iteration, Project Management

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the iteration plan. All activities must result in some change to the project's artefacts - this is the only possible measurement of progress. Back up claims of successful activity completion by including the generated or updated artefact with the status assessment.

Generate another iteration plan for the second inception iteration (IIP2). This iteration plan must aim to achieve the Life Cycle Objective Milestone by April 8. Plan IIP2 AS IF all activities in IIP1 were successful. Then ADD all incomplete and unsuccessful work items in IIP1 to the work scheduled for IIP2. This is necessary to avoid project schedule slippage.

Also, since Inception Iteration 2 completes the Inception phase, you must also plan to review the Inception phase and the project as a whole in 2 further status assessment documents. This is because the phase objectives are at a higher level than the iteration objectives, and require separate assessment. The same applies to project goals compared to phase goals. Allow perhaps ½ to 1 hour for these extra assessment tasks combined.

Posted Date: 3/26/2013 2:19:48 AM | Location : United States







Related Discussions:- Perform a status assessment of the project iteration, Assignment Help, Ask Question on Perform a status assessment of the project iteration, Get Answer, Expert's Help, Perform a status assessment of the project iteration Discussions

Write discussion on Perform a status assessment of the project iteration
Your posts are moderated
Related Questions
Organisational Style: Whether the participative approach can  really work depends upon the type of organisation and its' functioning. An open organisation is more likely to en

Number of post-release defects (found by clients in field operation), categorized by level of severity Ratio of defects found internally prior to release (by inspections and tes

Explain the relationship between organisational competences and decisions relating to the contracting out of activities. Organisational competences A competence is an mehod

Define the revolution of changing in information technology. Conversely, revolution of changing in the field of information technology has posed some of challenges for various

Failure Cost of failure may result from either internal failure or external failure. Internal failures are those that occur before the product is delivered, internal failure co

J Company is a retailer of fashion goods operating in a highly competitive market place. The Board of the company has given the go-ahead to redesign the company's website to make i

Cycle time and Assign work elements and Delete the assigned elements A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in th

Re-work effort (hours, as a percentage of the creative coding hours) Re-worked LOC (source lines of code, as a fraction of the total delivered LOC) Re-worked software compone

Limitations of Group Technology or Cellular Manufacturing Group Technology is a great concept. But all good concepts do have their own limitations and need proper care in their

Tolerance and Surface Finish Design engineers are always blamed of specifying closer tolerances than necessary. It  is obvious that to achieve a tolerance of ± 0.001 mm is mor