Mechanical design 2, engineering, Other Engineering

Assignment Help:
Mechanical Design (48650) – Spring Semester 2012
Optimisation Assignment – BUILDING A ROAD
Teams of THREE to FIVE [3 to 5] – Worth 20% of the Semester Grade
Due: Thursday 23rd March 2012 by 23:59 pm
Where? My Assignment Box [No 15] situated in Building 2 between Floors 5 & 6 below the big computer lab on level 6. This is the only way to submit – it eliminates confusion.
Late submissions (without prior permission) will be penalised at -10% per day late. Submissions more than one week late will not be accepted.
Students organise themselves into teams; share out the work; plan a timetable with delivery dates; hold regular face to face meetings and issue minutes, and; show fellow team members how to do things. Acknowledge outside assistance from other students in the report.
1. Background
The cost of building a road depends upon many things. For the purposes of this assignment it will depend on total distance covered and quantity of material cut from a hill, the quantity of material to fill hollows and the net amount of excess earth trucked to/from the area to make up for that used internally. The area being considered covers the coordinates from x = -5 to x = +5 kilometres and from y = +5 to y = -5 kilometres. The height of a point (z in metres) within the area is found from the equation:
z = sin [(x-y2)?/14] + sin [(2x+y)?/9)] - 0.37 {illustrated in the contour map below}
Five pairs of roads can start from the West at x=-5 and y =+4, +2, 0, -2 and -4 always travelling eastward. The pair starting at y = +4 finish at y = 1 and y = -1: the pair starting at y = +2 finish at y = +5 and y = -2: the pair starting at y = 0 finish at y = -3 and y = +3: the pair starting at y = -2 finish at y = -5 and y = +1, and: the pair starting at y = -4 finish at y = +1 and -1. The roads run horizontally at z = zero metres.
The costs (in units of $100,000) are:
Road construction cost is 7/km Cost to fill a hollow is 3/km.metre
Cost to cut into a hill is 2/km.metre. Cost to truck net excess earth to/from the area is 3.5/km.metre
The cut or fill for each step is zav . ?s, where zav = (zleft + 2zmid + zright)/4 and ?s is the step road length.
2. Teams
Teams of three start at x = -5 and y = +4, 0 and -4. Teams of 4 start at x = -5 and y = +4, +2, 0 and -2. Teams of five will start at x = -5 and y =+4, +2, 0, -2 and -4. Each team member will do 2 roads starting at one point and a team will cover all roads allocated to them.
3. The Task
3.1 Maps: Produce a contour map better than that shown below and also a three-dimensional surface graph of the ground. Divide the x and y ranges into steps of 0.25 km.
[Hint; Look up the “range” naming function in “Help” – it allows you to easily write a general formula that can be written to any cell to calculate z and it will automatically step through the x- and y-ranges.]
3.2 Optimisation: Using an optimisation package such as “Solver” in Excel, determine the road path which gives the minimum cost for each starting and finishing point examined by the team. Plot the road route and z-elevation profile for each road. A small bonus will be awarded for the team with the lowest cost, viable solution.
[Hints: Move from x = -5 to x = +5 in steps of 0.5 km [or 0.25 km, preferably]. Determine the (i) the road distance for the step and it’s cost; (ii) the z at the half x-step co-ordinates; (iii) the “fill” or “cut” for that step; (iv) the cost of the fill or cut for that step; (v) the net fill or cut for the road and it’s cost; (vi) the total road cost, and; (vii) optimise the y-path to minimise total cost. Check for correct operation by putting all costs except road construction to zero – you should get a straight line road path. Warning! Try several initial path guesses to get the “best” path. “Play’ with the option settings in Solver.]

Related Discussions:- Mechanical design 2, engineering

Communication, Can u provide some information about simple wireless transmi...

Can u provide some information about simple wireless transmitter and receiver.

Calculate the relative load of mobile broadband subscribers, Question: ...

Question: (a) A mobile operator wants to weigh and allocate cost towards mobile broadband subscribers with mobile broadband at 80% of the traffic and 15% of the subscribers. H

Casting, Casting means the pouring of molten metal into a mould, where soli...

Casting means the pouring of molten metal into a mould, where solidification occurs. Advantages of Casting Process          (i) It is the cheapest method of fabrication.

Assgnment, Sulphuric acid can be made with concentration of 99%. However f...

Sulphuric acid can be made with concentration of 99%. However for different industrial process different concentrations are used. For a specific industrial requirement, 62% H2SO4

Asteroid belt, Why is there an asteroid belt? - Rocky planetismals survive...

Why is there an asteroid belt? - Rocky planetismals survived in the asteroid belt between Mars and Jupiter because they did not grow together into a planet. - Jupiter’s gravity, t

Class B audio amplifier, could help me to write a project specification of ...

could help me to write a project specification of class B audio amplifier, if I am going to do a project of class B audio amplifier?

Fire prevention – bays or zones, Fire prevention – bays or zones: To pr...

Fire prevention – bays or zones: To prevent the spread of a fire within an aircraft/engine nacelle, it is divided up into sections or zones, each being separated by a fireproof

Heat transfer, A heat recovery device involves transferring energy from hot...

A heat recovery device involves transferring energy from hot flue gases passing counter currently through an annular region to pressurized water flowing through the inner tube of t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd