Q. How to set Location of the bridge?

A bridge is normally located where the river section has minimum width so that the structure becomes shorter and economical. As far as possible it is aligned normal to the river. If satisfying these requirements involves a long detour, some compromise is made in siting a crossing. Care is also taken to avoid, if possible, sites where frequent changes occur in river course, tendency for aggradation or degradation is manifest and problems of bank erosion or difficult foundation conditions are required to be faced.

Approach banks in case of constricted bridges are generally aligned in line with the bridge axis and normal to the guide bunds. Approaches deviating towards downstream direction add to their safety from river loops approaching dangerously close while deviation in upstream direction exposes them more to river attack.

Location of the bridge with respect to Khadir width also determines the length and position of approach bank exposed to river attack. When bridge is constructed near one of the ends of the Khadir width and when the khadir edge consists of stiff material resisting erosion, cost of one guide bund can be saved. Longer length of the approach at other end however gets exposed and becomes vulnerable to river attack in this case. On the other hand central location of the bridge reduces length of approach open to river attack, minimises possibility of extreme obliquity of approach of the river towards the bridge but requires provision of guide bunds on both the flanks.

In general, bridge location and alignment are fixed to ensure normal approach of the river, equitable distribution of flow across bridge section and minimum possibility of river attack on approach banks.


Related Discussions:- How to set location of the bridge

Radial contouring, How we can find R.L. of instrument station without movi...

How we can find R.L. of instrument station without moving of instrument.

Determine the cost of compensation, The soil in a borrow pit has a void rat...

The soil in a borrow pit has a void ratio of 0.90. A fill-in-place volume of 20,000 m 3 is to be constructed with an in-place dry density of 18.84 kN/m 3 . If the owner of borr

Formation of pedestrian level winds around buildings, Q. Formation of pedes...

Q. Formation of pedestrian level winds around buildings? When a building blocks the wind blowing across it, part of the wind will escape over the top of the building. Some will

Online job, I am M tech in civil engg looking for online assignment job.

I am M tech in civil engg looking for online assignment job.

Compute the degree of saturation, The maximum dry density and optimum moist...

The maximum dry density and optimum moisture content of a soil from standard proctor's test are 18 kN/m 3 and 16% respectively. Compute the degree of saturation of the sample,

survey, what is fore bearing and back bearin

what is fore bearing and back bearing

Determine the uses of screw connectors, Determine the uses of Screw connect...

Determine the uses of Screw connectors Screw connectors are normally used  to splice large-diameter high-tensile strength bars. The bars are threaded at the ends and a sheet-me

Define the hazardous waste, Define the Hazardous Waste 1. Any waste or ...

Define the Hazardous Waste 1. Any waste or combination of waste that poses a substantial danger now or future to humans, plants, and animals without special precautions. 2.

Define project schedule financial analysis, The 6 monthly payment applicati...

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd