Grouted or Penetration Macadam:

This is a specification where the binder is sprayed on a compacted layer of stone aggregates and is allowed to penetrate and bind the aggregates. A layer of intermediate aggregates, called key aggregates, is spread on the layer and rolled. A seal coat is provided to seal the surface.

For a 50 mm compacted thickness, the quantity of coarse aggregates is 0.60 cu m per 10 sq m area, the quantity of binder is 50 kg per 10 sq m, and the quantity of key aggregates is 0.15 cu m per 10 sq m. The seal coat is similar to the seal coat provided for a PC.

The advantage of penetration macadam is that it does not require a mixing plant. The advantage is that it uses a high quantity of binder. The specification is hardly used now-a-days.


Related Discussions:- Grouted or penetration macadam

Can all utility detectors detect depth of utilities, Question Can all u...

Question Can all utility detectors detect depth of utilities ? Answer In Hong Kong, underground utility detectors are as a rule separated into two categories- electro

Premix, how we can do good premix

how we can do good premix

What do you mean by settlement cracks, Q. What do you mean by Settlement Cr...

Q. What do you mean by Settlement Cracks? Settlement cracks normally take place in diagonal position. Sometimes vertical cracks may also take place (Figure (a)). Settlement cra

#title Design a gravity-flow sanitary sewer , i have to Design a gravity-f...

i have to Design a gravity-flow sanitary sewer to serve and i need it to be done asap

Defaults for precast concrete pipes made by spinning, Q. Defaults for preca...

Q. Defaults for precast concrete pipes made by spinning? Small diameter precast concrete pipes are generally manufactured by spinning method. The spinning method fundamentally

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Pavement width - geometric design of roads, Pavement Width: The pavem...

Pavement Width: The pavement widths commonly adopted are : Single lane                 :           3.75 m Intermediate lane     :           5.5 m Two lane

Vectors application, how does vectors apply mathamatical in civil engineeri...

how does vectors apply mathamatical in civil engineering

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd