Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Analyse the website design, Briefly analyse and compare the two website des...

Briefly analyse and compare the two website designs, applying in turn each of the six design principles. This will result in six brief paragraphs. As part of each analysis, expl

Examples of artificial neural networks, Examples of artificial neural netwo...

Examples of artificial neural networks: Now here as an example consider a ANN that has been trained to learn the following rule categorising the brightness of 2x2 black and wh

Describe attributes and properties of system, System Analysis & Design ...

System Analysis & Design 1. Describe attributes, properties, and characteristics of system. 2. What do you mean by Organizational Aspects of System Life Cycles? Explain.

Queueing process, explain in detail about queueing process

explain in detail about queueing process

How a physical addressing is performed in wan, How physical addressing is p...

How physical addressing is performed in WAN? WAN networks operate as similar to a LAN. All WAN technology classifies the exact frame format a computer uses while sending and re

Explain pre-emptive scheduling, Explain Pre-emptive scheduling? Pre-em...

Explain Pre-emptive scheduling? Pre-emptive scheduling: in its approach, center processing unit can be taken away from a process if there is a require while in a non-pre-empt

Communication traffic and message queues, The Communication Traffic gives a...

The Communication Traffic gives a pictorial view of the communication traffic in the interconnection network with respect to the time in progress. The Communication Traffic shows t

Compute the positive integer and square root, Question: Q1) Write a cod...

Question: Q1) Write a code that asks the user for a positive integer, computes the square root of that integer, and return the result to the user. The computational error needs

Rank the list elements in terms of distance, Q. Rank the list elements in t...

Q. Rank the list elements in terms of distance? Rank the list elements in terms of distance from each to last element in given linear linked list. A parallel algorithm for t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd