Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Number used as operand data type, Q. Number used as operand data type? ...

Q. Number used as operand data type? Numbers: All machine languages comprise numeric data types. Numeric data generally use one of the three representations: o Floating po

How many bits must be decoded for 128 × 8 ram chips, How many bits must be ...

How many bits must be decoded for chip select? What is the size of decoder when 128 × 8 RAM chips are required to provide a memory capacity of 2048 bytes? Ans. All higher order l

What do you mean by directives, Q What do you mean by Directives? Assem...

Q What do you mean by Directives? Assembly languages support numerous statements. This allows you to control the way in which a source program assembles and list. These stateme

Illustrate master-slave flip-flop, Q. Illustrate Master-Slave Flip-Flop? ...

Q. Illustrate Master-Slave Flip-Flop? Master slave flip-flop comprise two flip-flops. One is master flip-flop and other one is known as slave flip-flop. Fig below shows impleme

Describe about second generation computers, Q. Describe about Second Genera...

Q. Describe about Second Generation Computers? Silicon brought advent of second generation computers. A two state device termed as a transistor was created from silicon. Transi

Input-output-processor interconnection network (iopin), Input-Output-Proces...

Input-Output-Processor Interconnection Network (IOPIN) This interconnection network is used for communication between I/O channels and processors. All processors commune with a

Illustration of parallel programming environments, Q. Illustration of paral...

Q. Illustration of parallel programming environments? Let's discuss illustrations of parallel programming environments of Intel paragaon XP/S and Cray Y-MP software. The Cra

Determine the bit value and bitstrings , Testing Your Program All progr...

Testing Your Program All programs must be thoroughly tested before they are released to users. Create some sample input files of a small size and manually figure out what the o

For what purpose Karnaugh map is used, Karnaugh map is used for the purpose...

Karnaugh map is used for the purpose of ? Ans. Karnaugh map is used for, to minimize the terms in a Boolean expression.

Features of an expert system, The heart of an experts systems is the ...

The heart of an experts systems is the powerful corups of knowledge that accumulates during system building. The knowledge is explicit and organized to simplify decisio

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd