Earned value analysis, Computer Engineering

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.

Posted Date: 3/19/2013 3:02:04 AM | Location : United States

Related Discussions:- Earned value analysis, Assignment Help, Ask Question on Earned value analysis, Get Answer, Expert's Help, Earned value analysis Discussions

Write discussion on Earned value analysis
Your posts are moderated
Related Questions
The Concept Development journal must contain: An introductory paragraph detailing what conclusions you have drawn from your research and how you intend to proceed. This should b

What is parsing? Parsing is the process of analyzing a text, formed of a sequence of tokens, to find out its grammatical structure regarding a specified formal grammar. Parsing

What is a crosstab query wizard? A wizard that helps us to show the data in a two-dimensional tabular format is the crosstab query wizard. You can use this to make queries that

Layout pages, can describe sections, which can then be overridden by particular views making use of the layout. Major and overriding sections is optional.

What is Traffic Engineering? Traffic engineering gives the basis for analysis and design of telecommunication network to carry a specified traffic at an exact loss probability

What is relational database? Relational database has data that is perceived as tables. A relational DBMS manages tables of data and associated structures that enhances the func

PS/2 connector (PS/2 keyboards): These were introduced with IBM's PS/2 computers and therefore are known as PS/2 connectors.  They have 6-pins but actually their wiring is just

Explain the term - Strong Typing and  Weak Typing Strong Typing : When any operation upon an object can be checked during compile time, when type is confirmed forcefully.