Earned value analysis, Computer Engineering

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.

Posted Date: 3/19/2013 3:02:04 AM | Location : United States







Related Discussions:- Earned value analysis, Assignment Help, Ask Question on Earned value analysis, Get Answer, Expert's Help, Earned value analysis Discussions

Write discussion on Earned value analysis
Your posts are moderated
Related Questions
Discuss about the Electronic computer The first general function programmable electronic computer was the Electronic Numerical Integrator and Computer (ENIAC), built by John V

Explain the violating basic security principles There are drawbacks to permitting users to access the Intranet as well as not permitting them. A simple consideration such as a

documentation for dbms report

A certain amount of side tone is essential in telephone communication. Ans: It is true that a specific amount of side tone is necessary in telephone communication.

What is metadata? Metadata is data that explains another data. Class definition is metadata. Models are inherently metadata as they explain the things being modeled.

Unions allow the same area of memory to be accessed as different data types. The insurance example above would not work. Unions are useful (often in embedded programming) when i

Design a serial 2’s complementer with a shift register and a flip-flop

Q. What is microcomputer system? The microcomputer has a single microprocessor and a number of RAM and ROM chips as well as an interface unit which communicates with several ex

given a string S convert it to palindrome by doing character replacement.convert S to palindrome with minimum character replacements