Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

What about page footer, By default, this page is quite barren. Though, go e...

By default, this page is quite barren. Though, go explore the Query Page some more; you will search that you can store numerous queries on the server, so if you regularly run a cer

What is the purpose of putchar function, What is the purpose of putchar fun...

What is the purpose of putchar function Putchar writes one character to the standard output file, stdout. Syntax #include int putchar(int c); The putchar macro wr

Define the concept of typing of object oriented analysis, Define the concep...

Define the concept of Typing of object oriented analysis Typing enforces object class such that objects of different classes cannot be interchanged.  Or we can say that, class

Find the average of two values, Q. Find the average of two values? Find...

Q. Find the average of two values? Find the average of two values which are stored in  ; Memory locations named FIRST and SECOND  ; And puts result in memory location AVG

Explain about the e-commerce over extranets, Explain about the e-commerce o...

Explain about the e-commerce over extranets. Extranets are regarding “joining up” the supply chain-suppliers, distributors, resellers and customers are enabling business-to bus

Determine the simplified sop boolean expression, The Karnaugh map for a SOP...

The Karnaugh map for a SOP function is given below in figure. Determine the simplified SOP Boolean expression. Ans. F= B'C' + A'C'D + B'D'

When do you do load and performance testing, We perform load testing once w...

We perform load testing once we are completed with interface (GUI) testing. Modern system architectures are large and difficult. Whereas one user testing primarily on functionality

What is the advantages for linux, What is the advantages for Linux? ...

What is the advantages for Linux? Runs on old Hardware Low-Cost Linux is fully customizable in all its components Powerful Linux runs on low-end, cheap hardware

Define both fork and vfork, How and when race conditions happen in process ...

How and when race conditions happen in process control? How can it be avoided? b. Differentiate among following functions giving related syntax: (i) fork and vfork (ii) w

Returns the information about tasks running, Returns the information about ...

Returns the information about tasks running int info = pvm_tasks( int where, int *ntask, struct pvmtaskinfo **taskp ) struct pvmtaskinfo {  int ti_tid; int ti_pt

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd