Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Hat are the advantages and disadvantages of hardwired, What are the advanta...

What are the advantages and disadvantages of hardwired and micro programmed control? Advantages of hardwired control i. Operate at high speed ii Each state of this coun

Define the register length, Q. Define the Register Length? Register Le...

Q. Define the Register Length? Register Length: Asignificant characteristic related to registers is length of a register. Generally the length of a register is dependent on it

Cisc approach - cisc architecture, CISC Approach - CISC architecture: ...

CISC Approach - CISC architecture: The main goal of CISC architecture is to finish a task in as few lines of assembly as possible as. This is gain by building processor hardwa

Explain about interrupt-processing sequence, Q. Explain about Interrupt-Pro...

Q. Explain about Interrupt-Processing Sequence? The occurrence of an interrupt fires a numbers of events both in processor hardware and software. Figure below displays a sequen

What are the ways to truncate guard bits, What are the ways to truncate gua...

What are the ways to truncate guard bits? 1. Chopping 2. Von Neumann rounding 3. Rounding procedure.

What is race-around problem and how can you rectify this, What is Race-arou...

What is Race-around problem? How can you rectify this? The clock pulse which remains into the 1 state whereas both J and K are equal to 1 will reason the output to complement a

Process of minimax algorithm, Process of Minimax algorithm: Our aim is...

Process of Minimax algorithm: Our aim is just to write the best of best score on the top branches of the tree that player one can guarantee to score if he chooses that move.

Strings made of left curly braces, In a logical system, a judgement is a st...

In a logical system, a judgement is a statement that is either true or false. So far, you are most familiar with the type of judgement "A is true", which is often simply abbreviate

What are the static and dynamic hazards in logic circuits, If for a short p...

If for a short period of time circuits goes to some dissimilar logic level then it is assumed to have then it is known as static hazard e.g. If the final logic value of output of a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd