Earned value analysis, Computer Engineering

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.

Posted Date: 3/19/2013 3:02:04 AM | Location : United States







Related Discussions:- Earned value analysis, Assignment Help, Ask Question on Earned value analysis, Get Answer, Expert's Help, Earned value analysis Discussions

Write discussion on Earned value analysis
Your posts are moderated
Related Questions
What are the two ways of producing a list within a transaction? By submitting a separate report. By using leave to list-processing.

Important part of Process - canonical genetic algorithm: In such a scenario evolution or random mutations are often highly deleterious or can say harmful to the organism it me

Q. Explain about Microprocessors? Microprocessors have instruction sets ranging from 20 to several hundred instructions, known as microprograms, which are stored in ROM to init

Define macros.   A macro is a pre-processor directive which is a program that processes the source code before it passes by the compiler. These are placed in the source program

Define system space.  Management routines are part of the operating system of the computer. It is suitable to assemble the OS routines into a virtual address space.

Automatic typewriter : It is a power-driven machine, which automatically types a standard pro forma from a previously punched or stencilled master. When the master is placed on th

What is the difference between, page directive include, action tag include? Ans) One difference is whereas using the include page directive, in translation time it is making t

Q Develop a menu driven program to perform Binary addition and subtraction on two numbers that are inputted. Check that entered numbers are in base 2 or not else error messag

Name some popular storage devices In contrasts with storage, which 1) retains data and programs irrespective of whether they are currently in use or not, (2) retains data

What is cyclomatic complexity? Cyclomatic complexity is a computer science metric (measurement) developed by Thomas McCabe used to generally calculate the complexity of a progr