Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Assembly lenguange , what is the work of pin daigram in 8086 microprocessor...

what is the work of pin daigram in 8086 microprocessor in assembly

Digital logic, write a short note on the tri state ttl inverter

write a short note on the tri state ttl inverter

What is command prompt interface, Q. What is Command Prompt Interface? ...

Q. What is Command Prompt Interface? Operating System gives a text based interface called command prompt.  With the help of command prompt commands can be issued to perform fil

Show smtp and electronic mail, One of the very useful things about Internet...

One of the very useful things about Internet is that it enables almost instantly exchange of electronic message (e-mail) across the worlds. E-mail is a standard as well as popular

Conversion of decimal number 82.67 to its binary equivalent, Conversion of ...

Conversion of Decimal number 82.67 to its Binary Equivalent Ans. Firstly see the integer part 82 and determine its binary equivalent  as The Binary equivalent is (101001

Define clock rate, Define clock rate? The clock rate is given by, R=1/P...

Define clock rate? The clock rate is given by, R=1/P, where P is the length of single clock cycle.

Uml, what is uml ?

what is uml ?

Write 8086 initialisation routine required to program 8255, Write 8086 init...

Write 8086 initialisation routine required to program 8255 for mode 1 with Port A and Port B as output Ports and Port C as an input port. Indicate all the relevant signals.

Flow-between matrix layout problem, Solve the problem in page 346 of the pa...

Solve the problem in page 346 of the paper on cell formation by Boctor using the MIP method.  Use 4 cells and no more than 3 machines per cell. Solve the problem using the MIP m

Alignment with your indents, Use Microsoft SQLServer to make the following ...

Use Microsoft SQLServer to make the following queries.  You should also download the Pirate Sports DM-DD that gives the fields for every table.  Be sure to use proper alignment wit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd