Earned value analysis, Computer Engineering

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.

Posted Date: 3/19/2013 3:02:04 AM | Location : United States







Related Discussions:- Earned value analysis, Assignment Help, Ask Question on Earned value analysis, Get Answer, Expert's Help, Earned value analysis Discussions

Write discussion on Earned value analysis
Your posts are moderated
Related Questions
Classification according to part of instruction and data: According to the parts of instruction and data, following parts are identified under this classification: Scal

Q. Library of functions of parallel virtual machine? PVM offers a library of functions libpvm3.a, that application programmer calls. Every function has some specific effect in

Register Transfer Micro-operations These micro-operations as the name proposes transfer information from one register to another. The information doesn't change during these mi

What is a Data Class? The Data class verifies in which table space the table is stored when it is formed in the database

What is the function of ALU? Most of the computer operations (arithmetic and logic) are performed in ALU. The data needed for the operation is brought by the processor and the

What are the Benefits of Web-Based Spreadsheets? The spreadsheets can be accessed from any Internet-connected computer, not just the computer originally formed the spreadsh

Logic-based Expert Systems : Expert systems are agents that are programmed to make decisions just about real world situations are place together by utilising knowledge illicit

Q. How to Changing the Directory in DOS? You can change the directory. After changing the directory, the new directory becomes the default directory. For example, you change th

Let's attempt to answer a fundamental question: 'How does the Computer execute a Program?' Let's describe this with the help of an example from higher level language domain. Pr

Q. Explain the following: a) Gray code b) Parity code c) Overflow Q. Give the counting up to 30 in Base 5. Q. Convert (175.6)8 into Gray code and Excess-3 code.