Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Pre-os and runtime sub-os functionality, In a raw Itanium, a 'Processor Abs...

In a raw Itanium, a 'Processor Abstraction Layer' (PAL) is incorporated in system. When it's booted PAL is loaded in the CPU and provides a low-level interface which abstracts a nu

Difference between visual check and parity check, Difference between Visual...

Difference between Visual check and Parity check Visual check This is checking for errors by comparing entered data with original document (NOTE: this is not the same as

How many input ANDand OR gates are required, How many two input AND gates a...

How many two input AND gates and two input OR gates are required to realize Y = BD+CE+AB ? Ans. Here three product terms, therefore three AND gates of two inputs are needed.

What is linked list, Q. What is Linked List? A linked list is a data st...

Q. What is Linked List? A linked list is a data structure formed by zero or more nodes linked by pointers. Every node has two parts as shown in Figure below. One of them is inf

Explain automated and manual systems, Q. Explain Automated and Manual syste...

Q. Explain Automated and Manual systems? Automated and Manual systems: The system that doesn't need human intervention is known as'Automated system'. In this system whole proce

Critical path analysis, Given the information provided in Table 1: ...

Given the information provided in Table 1: Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool); Prepare

Describe about the digital cameras, Describe about the Digital cameras ...

Describe about the Digital cameras The microprocessor would be used to control the below functions, for instance: - shutter speed - lens focus - Flash - Aperture (l

I2c protocol bus , I²C TECHNOLOGIES The I2C protocol bus is two bi-dire...

I²C TECHNOLOGIES The I2C protocol bus is two bi-directional wires, serial data (SDA) and serial clock (SCL), that transmit information between the devices connected to the bus.

Explain the importance of computer architecture, Explain the importance of ...

Explain the importance of Computer architecture Computer architecture courses cover application, organization, architecture, logic and transistor layers. However, four other la

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd