Earned value analysis, Computer Engineering

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.

Posted Date: 3/19/2013 3:02:04 AM | Location : United States







Related Discussions:- Earned value analysis, Assignment Help, Ask Question on Earned value analysis, Get Answer, Expert's Help, Earned value analysis Discussions

Write discussion on Earned value analysis
Your posts are moderated
Related Questions
When entering word into the cell, press Alt-Enter to insert a line break. When you do so, Excel will automatically give text wrapping to the cell. To reformat existing cells s

Macroscopic and Microscopic approaches - Thermodynamics: Thermodynamic studies are undertaken by following two different approaches.  l. Macroscopic approach (Macro mean big)

How to draw the pipe and filter using data flow and it components and connectors

SPMD is actually a "high level" programming model that can be built upon any combination of the previously mentioned parallel programming models. A single program is executed by al

How can you pass a struct by reference in e?   The question is phrased in a tricky way because passing by reference is the default and only possible way to pass structs in e. I

Human intelligence in culture: Understand human intelligence in culture  "AI" can be seen as just the latest tool in the philosopher's toolbox for answering questions about

To execute sparse matrix dynamically, Which data structure is used Linked List data structure is used to execute sparse matrix dynamically

Define Apple MobileMe Calendar The MobileMe Calendar is a web-based calendar that can be accessed from any computer linked to the Internet, Mac or Windows. What makes it more u

Q. Show the properties of Frame Tag? This tag is used for placing an HTML file in the frame created. We should now tell browser what to put in every frame.

Design an algorithm (using pseudocode) that takes in as an input, two 2-D int arrays that are assumed to be 2 black-and-white images: initialImage x, whose dimensions are IxJ, and