Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Code Solution, Dear sir, I want to read Excel file and display it in grid v...

Dear sir, I want to read Excel file and display it in grid view(the headings in excel file should be grid view column heading).This should be coded in C# Windows forms Application

Differentiate between http and ftp, Differentiate between http and ftp. ...

Differentiate between http and ftp. HTTP and FTP were developed to make Internet transmission better. FTP is utilized to exchange files among computer accounts, to transfer

The major underlying concepts of object orientation, Objects, messages, cla...

Objects, messages, class, inheritance and polymorphism are the major concepts of object orientation.

Secondary storage - computer architecture, Secondary storage: Secondar...

Secondary storage: Secondary storage (or external memory) differs from primary storage in that aspect it is not accessible by the CPU directly. The computer typically uses its

Flip flop., the counter shown Q2Q1Q0=000 The status of Q2Q1Q0 after the pul...

the counter shown Q2Q1Q0=000 The status of Q2Q1Q0 after the pulse

Input-output-processor interconnection network (iopin), Input-Output-Proces...

Input-Output-Processor Interconnection Network (IOPIN): This interconnection network is designed for communication between I/O Channels and processors. Every single one proces

Canonical genetic algorithm - mating, Canonical genetic algorithm - Mating:...

Canonical genetic algorithm - Mating: In such a scenario this continues until the number of offspring that is produced is the required number. Further this required number is

Explain bernstein conditions for detection of parallelism, Bernstein Condit...

Bernstein Conditions for Detection of Parallelism For execution of a number of instructions or a block of instructions in parallel, it must be made certain that instructions ar

Explain the trackball and thumbwheel devices, Explain the Trackball and Thu...

Explain the Trackball and Thumbwheel devices  Joysticks A joystick consists of a small, vertical lever (called the stick) mounted on a base that is used to steer the screen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd