Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Illustrate fdma and tdma concepts., Mobile Computing 1. What is Wireles...

Mobile Computing 1. What is Wireless Protocol Requirements and also explain in brief medium access control protocol. 2. Illustrate FDMA and TDMA concepts. 3. What are the

Boolean algebra, Prove the following Boolean identities using the laws of B...

Prove the following Boolean identities using the laws of Boolean algebra (A + B)(A  + C) = A + BC Ans. (A+B)(A+C)=A+BC LHS AA+AC+AB+BC=A+AC+AB+BC OR  A((C+1)+A(B+1))+BC

Define strategy procedure, Q. Define Strategy Procedure? The strategy p...

Q. Define Strategy Procedure? The strategy procedure is called when loaded into memory by DOS or whenever controlled device request service. The major purpose of the strategy i

What do you mean by memory mapped i/o, What do you mean by memory mapped I/...

What do you mean by memory mapped I/O? In Memory mapped I/O, there is no particular input or output instructions. The CPU can manipulate I/O data residing in interface register

Difference between relocatable and self relocatable programs, Difference be...

Difference between relocatable and self relocatable programs. A relocatable program is one which can be processed to relocate it to a selected area of memory. For illustratio

What is the significance of nonactionattribute, In general, all public proc...

In general, all public processes of a controller class are treated as action processes. If you require prevent this default behaviour, just decorate the public process with NonActi

Rdbms, what is physical data structure in internals of rdbms?

what is physical data structure in internals of rdbms?

Computer Architecture, As an advocate of CISC architecture to RISC architec...

As an advocate of CISC architecture to RISC architecture, what are the merits and demerits of CISC to RISC architecture

Explain classification based on grain size, Explain Classification Based On...

Explain Classification Based On Grain Size This categorization is based on distinguishing the parallelism in a program to be executed on a multiprocessor system. The concept is

Where do you set automatic correlation options, Automatic correlation from ...

Automatic correlation from web point of sight can be set in recording options and correlation tab. Here we can enable correlation for the whole script and choose either issue onlin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd