Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

TIME COMPLEXITY, calculate the time complexity of a=(b/c) operation in stac...

calculate the time complexity of a=(b/c) operation in stack

Mclr, 10 k Ohm pulls up on MCLR so that the ICD can force 0, +5, +13 volts ...

10 k Ohm pulls up on MCLR so that the ICD can force 0, +5, +13 volts on this pin. RB6 and RB7 used for PGC and PGD respectively between target and ICD2 module. Some of the requi

Convert logic circuit in a binary code, The logic circuit given below, conv...

The logic circuit given below, converts a binary code y 1 y 2 y 3 into Ans. Gray code is X1 = Y1,   X2 = Y1 XOR Y2  ,   X3 = Y1 XOR Y2 XOR Y3 For

State the term in detail $strobe, State the term in detail $strobe $str...

State the term in detail $strobe $strobe. This task is very similar to $display task except for a slight difference.  If many other statements are executed in same time unit as

What is microcomputers, Q. What is Microcomputers? Microcomputers have ...

Q. What is Microcomputers? Microcomputers have become a common part of everyday life. The cost ranging from a few hundred to about ten thousand dollars, today's 16- and 32-bi

Explain redundant array of independent disks levels, Q. Explain Redundant A...

Q. Explain Redundant Array of Independent Disks levels? One such industrial standard that exists for multiple-disk database schemes is called as RAID which implies Redundant Ar

Adding server-side include to the page, Step 1: Click on the icon in the ob...

Step 1: Click on the icon in the object tool bar Or Insert -> SSI Step 2: Select the file Step 3: Add the file Step 4: Provide the URL (where to be attached) Step

Write the html code to webpage to insert scrollable lists, Write the HTML c...

Write the HTML code to accomplish the web page to insert scrollable lists that will always display four entries of the list. The HTML code to accomplish the web page is given b

What is block started by symbol, What is BSS(Block Started by Symbol)? ...

What is BSS(Block Started by Symbol)? A data showing at the machine level, that has initial values when a program begins and tells about how much space the kernel assigns for t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd