Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Define side tone is essential in telephone communication, A certain amount ...

A certain amount of side tone is essential in telephone communication. Ans: It is true that a specific amount of side tone is necessary in telephone communication.

Explain functions of direct memory access, Q. Explain functions of direct m...

Q. Explain functions of direct memory access? Though CPU intervention in DMA is minimised however it should use path between interfaces that is system bus. So DMA involves an e

Determine the basic machine language instructions, Determine the basic Mach...

Determine the basic Machine language instructions Machine language instructions and data are in terms of 0s and 1s and are stored in the memory. It isn't possible to distinguis

What are the two ways in which the system using cache, What are the two way...

What are the two ways in which the system using cache can proceed for a write operation? Write by protocol technique Write-back or Copy-back protocol method

DBMS, DEFINE FILE ORGANISATION

DEFINE FILE ORGANISATION

Move a layout cell, If you need to line up the cells next to each other you...

If you need to line up the cells next to each other you can resize and move layout cells as you need. You can change size of a layout cell by using one of its resize handles. Yo

Message passing programming, Message passing is possible the most widely us...

Message passing is possible the most widely used parallel programming paradigm these days. It is the most portable, natural and efficient scheme for distributed memory systems. It

difference among primary and secondary storage device, In primary storage ...

In primary storage device the storage capacity is fixed. It has a volatile memory. In secondary storage device the storage capacity is not limited. It is a nonvolatile memory. Prim

Explain the term- wireless technologyand broadband, Explain the term- Wirel...

Explain the term- Wireless Technologyand Broadband Wireless Technology (WiFi) and Broadband Most areas in the world now provide broadband instead of dial up for connectin

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd