Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

the entire pcd division, Will executing  SAP R/3 across the entire PCD div...

Will executing  SAP R/3 across the entire PCD division give the division with a competitive benefit?  Clarify  your answer carefully.

What is the principle of locality, What is "the principle of locality"? ...

What is "the principle of locality"? It's the nature of the processes that they refer only to the small subset of the total data space of the process. I.e. the process frequ

What is meant by maskable interrupts, A interrupt that can be turned off by...

A interrupt that can be turned off by the programmer is called as Maskable interrupt.

What is meant by branch instruction, What is meant by branch instruction? ...

What is meant by branch instruction? A branch instruction is an instruction which changes the contents of the PC with the branch target address. This address is usually get by

Definition of a micro controllers, Before we take a detailed look about the...

Before we take a detailed look about the Motorola 68HC11 series of micro controllers it is useful to define what is meant by a micro controller. As the name suggests a micro contro

Explain design parameters, Explain the following design parameters S, ...

Explain the following design parameters S, SC, TC, C, CCI, EUF, K, T S The various terms are given below: S: Total number of switching components A good design sh

What is monkey testing, What is Monkey testing? The monkey testing is ...

What is Monkey testing? The monkey testing is the process of testing here and there for judging the application trying to observe the accessing dissimilar functionalities is i

What is software and hardware interrupt, What is Software and hardware inte...

What is Software and hardware interrupt The software interrupts are program instructions. These instructions are inserted at desired location in a program. A program formed int

Explain the importance of object oriented modelling, Explain the importance...

Explain the importance of Object Oriented Modelling It is important to note that wi t h the growing complexity of systems, significance of modelling techniques increases. Beca

What are types of applets, There are two different parts of applets. Truste...

There are two different parts of applets. Trusted Applets and Untrusted applets. Trusted Applets are applets with predefined security and Untrusted Applets are applets without any

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd