Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Draw a diagram to illustrate the design pattern, Problem: (a) What show...

Problem: (a) What shows a Pattern a Pattern? (b) Which pattern is given below? Justify your answer. public class A { private static A instance = null; private A() {

Explain sample instruction format of mips instruction, Q. Explain Sample In...

Q. Explain Sample Instruction Format of MIPS instruction? All MIPS instructions are of same size and are 32 bits long. MIPS designers chose to keep all instructions of same len

First-order inference rules, First-Order Inference Rules: Here now we ...

First-Order Inference Rules: Here now we have a clear definition of a first-order model is that we can define soundness for first-order inference rules in the same way such we

Simplify the expression by using karnaugh map, Simplify   the   following  ...

Simplify   the   following   expression   into   sum   of   products   using   Karnaugh   map F(A, B, C, D) = ∑ (1,3,4,5,6,7,9,12,13) Ans. Simplification of the giv

Explain the term- scan insertion, Explain the term- Scan Insertion Sca...

Explain the term- Scan Insertion Scan Insertion is completed by a tool and results in all (or most) of your design's flip-flops to be changed by special "Scan Flip-flops". Sca

What are the aspects of CAD, What are the aspects of CAD Increased use ...

What are the aspects of CAD Increased use of computers has led to many of the above affects. Other aspects to consider include: -  deskilling of the work force (for illustra

Answering systems- database query, Answering Systems / Database Query T...

Answering Systems / Database Query There are a large number of opportunities for get faster through parallelizing a Database Management System (DBMS). However, the actual purpo

Data analysis and results in e-commerce, There were 50 respondents to our s...

There were 50 respondents to our survey. The first component of the data examined here focuses on student's preference (ecommerce or traditional commerce). The Second compone

The maximum number of dimensions an array can have in c, The maximum number...

The maximum number of dimensions an array can have in C is C permits arrays of three or more dimensions. The exact limit is examined by the compiler.

Explain the random scan and raster scan displays, Define Random scan/Raste...

Define Random scan/Raster scan displays?  Random scan is a method in which the display is made by the electronic beam which is directed only to the points or part of the screen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd