Earned value analysis, Computer Engineering

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.

Posted Date: 3/19/2013 3:02:04 AM | Location : United States







Related Discussions:- Earned value analysis, Assignment Help, Ask Question on Earned value analysis, Get Answer, Expert's Help, Earned value analysis Discussions

Write discussion on Earned value analysis
Your posts are moderated
Related Questions
What is the difference among super class and subclass in programming? Ans) A super class is a class that is inherited in programming while the sub class is a class that does th

The subsequent step in Karnaugh map is to map truth table in the map. Mapping is done by putting a 1 in respective square belonging to 1 value in truth table. This mapped map is us

If quicksort is so quick, why bother with anything else? If bubble sort is so bad, why even mention it? For that matter, why are there so many sorting algorithms?

How do you get workflow automation into e-business environment? In order to run smoothly, organizations frequently standardize processes across the organization and support use

What is recursion?  A recursive procedure should have two properties.  What are they? Recursion means function call itself repeatedly.         Properties : (1) There

How can it be achieved in designing e-cash based system? E-cash is essentially an online solution.  The buyer must validate the coins by the issuer in order to get the purchase

Classification according to level of processing According to this classification, computer operations are classified as arithmetic operations and instruction implementation. Ne

Hashed strings can often be deciphered by 'brute forcing'. Bad news, eh? Yes, and particularly if your encrypted passwords/usernames are floating around in an unprotected file some

Q. What is Tape Backup? Magnetic tapes are used these days in computers for the below purposes: Backing up data stored in disks. It is essential to regularly save data s

There are three primary colours in pigments - Red, Yellow and Blue. There are two ways to produce more colours:   Physical Mixing: Physically mix colours to produce a new colour