Earned value analysis, Computer Engineering

Assignment Help:

Senior management has requested a status update on the workstation installation project.  As a part of this update, managers have requested that you present an Earned Value analysis.

I have imagined three scenarios for project cost and schedule metrics that could have occurred for this project, shown in Table 3 below.  As of the end of the reporting period, according to the original schedule, you were expecting to have completed all work through Activity I.    

  1. Calculate the values indicated in Table 2 for each of the three scenarios and provide a verbal interpretation of what each answer means.  I have filled in the first answer as an example of what senior management expects.
  2. Provide a written interpretation of the results.  For each scenario: 
    1. What would be the implications for managing the project (e.g., corrective actions, if any)?
    2. What statement would need to be made to the project stakeholders?

Be sure to take into account all work completed to date in making your calculations, even if the work was not scheduled to be completed at this time (i.e., is ahead of schedule).  Use the assumption that the project can take credit for partially complete work. (Hint: for Scenario 3, take into account the partial work done on Task  J).

Use the ETC based on typical variances and the EAC using CPI methods for computing ETC and EAC (See pp. 181-187 of the PMBOK Guide and pp. 247-253 of Marchewka).  Note: there is an error in Marchewka on page 251 - ETC should be Estimate to Complete.

Some additional project notes (in response to questions posed by previous classes):

The deliverable is to fill out the matrix of earned value calculations for each of the three scenarios, given the information provided in Table 3.  I recommend that you use Excel or another spreadsheet program to do the calculations, using the standard formulas as shown in Marchewka and the PMBOK Guide. 

Each of the scenarios should give you slightly different results for most of the calculations, especially those for cost and schedule performance. 

Also, it is important that you use the ETC based on typical variances and the EAC using CPI calculations per the assignment instructions, otherwise you will arrive at different answers than I have calculated in the answer key.

I filled in the answer for the first calculation which, based on the assignment, indicated that the expected work to have been completed at this point in the hypothetical project was through Activity I.  In performing your calculations, assume that the percentages complete are correct for all activities as of the date you are preparing the table, and give credit for any work that has been partially completed, even if it is ahead of schedule.


Related Discussions:- Earned value analysis

Which header file is used for screen handling function, Which header file i...

Which header file is used for screen handling function:- The header files stdio.h having definitions of constants, macros and types, along with function declarations for stan

State the Process of sending signals to televisions, Determine about the Si...

Determine about the Signals to televisions Signals to televisions are now sent digitally thus need a computer to interpret as well as decode these signals into a sound/picture;

Define macros, Define macros.   A macro is a pre-processor directive wh...

Define macros.   A macro is a pre-processor directive which is a program that processes the source code before it passes by the compiler. These are placed in the source program

What is instruction cycle, What is Instruction Cycle A program residing...

What is Instruction Cycle A program residing in the memory unit of the computer having of a sequence of instructions.  The program is implemented in the computer by going throu

What is a parsing, what is parsin? Source programmed statements are ob...

what is parsin? Source programmed statements are observed as tokens, recognizing, building block of language the task of scanning the source statement and classifying the diff

Recent parallel programming models, A model for parallel programming is an ...

A model for parallel programming is an abstraction in addition its machine architecture is independent. A model is able to be implemented on different hardware and memory architect

Drawback of indirect addressing, Q. Drawback of indirect addressing? • ...

Q. Drawback of indirect addressing? • Drawback of this scheme is that it needs two memory references to fetch actual operand. First memory reference is to fetch the actual addr

What is process, What is Process? Process: A process is a program in ...

What is Process? Process: A process is a program in execution. It is an active entity, represented through the value of the program counter and the contents of registers o

Hyper-threading, Hyper-threading, officially known as Hyper-threading Techn...

Hyper-threading, officially known as Hyper-threading Technology (HTT), is Intel's trademark for their execution of the simultaneous multithreading technology on the Pentium 4 micro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd