Construct the control chart, Operation Management

Telephone inquiries of 100 cell phone company customers are monitored daily at random.  Incidents of incorrect information or other nonconformities (such as rudeness to customers) are recorded.  The data for last two weeks is as follows:

Day

Number of "nonconformities"

1

5

2

10

3

27

4

17

5

12

6

7

7

12

8

25

9

15

10

10

a. What is the appropriate control chart(s) to construct with this data?

b. What are the ± 3 sigma upper and lower control limits?

c. What does the control chart tell you about the phone company's operators?

Posted Date: 2/24/2013 11:59:04 PM | Location : United States







Related Discussions:- Construct the control chart, Assignment Help, Ask Question on Construct the control chart, Get Answer, Expert's Help, Construct the control chart Discussions

Write discussion on Construct the control chart
Your posts are moderated
Related Questions
Matthew Yachts, located in Montauk, Long Island, manufactured sailing yachts of all descriptions. The company had begun by building custom-designed yachts for a largely New York-ba

Historical Development of Operations Management Evidence of formal management of operations can be traced back as far as the Babylonian kingdom of Hammurabi, around 2100 BC bu

The XYZ Paint Shop owns and operates a dozen shops in northern Illinois. Their signature paint is diamond polished candy apple red lacquer. Sales (X, in millions of dollars) is rel

In one paragraph supported by your text and other research, describe the criteria you would use if you were a manager charged with evaluating corporate contributions to decide whet

#quwhat is operations process design?what are the factors that effect a process design?estion..



Wally and Beaver were general partners in a car dealership. Using the partnership name, Wally entered into a contract to purchase 30 used cars from Car Lots. Car Lots was not aware

What issues can organizations experience when implementing large database systems and data warehouses? What best practices would you recommend to an organization to mitigate these

Which of the following items best depicts the Define Scope process? A. It begins by determining product scope / deliverables and culminates in a project scope statement. B. It be