Question

What is the reason that vibrators not used in concrete compaction in piling works?


Answer

Concrete for piles must be a high-slump self-compacting mix that is capable of flowing between reinforcement cages with simplicity. As concrete is designed to be self-compacting, vibrators are not used for given that additional compaction. Furthermore, concrete in piles is compacted by power derived from free falling. Though, if vibrators are used, vibrated concrete can be compacted to sides of concrete casings and hinders lifting up of casings.

 


Related Discussions:- Concrete compaction in piling works

STRENTH OF MATERIAL, WHY WE ARE USING MAMENT OF INERTIA IN STRAIN ENERGY ST...

WHY WE ARE USING MAMENT OF INERTIA IN STRAIN ENERGY STRUCTURE

Use plain dumb-bell type and center-bulb sort, Question While selection...

Question While selection of waterstop, shall engineers use plain dumb-bell type , center-bulb sort ? Answer Plain dumb-bell kind is used for joint site where sm

Transportation Engineering, can u help with assignment and how much per ass...

can u help with assignment and how much per assignment

Designing of service reservoirs, Question In designing of service res...

Question In designing of service reservoirs , straight reinforcement in walls of reservoirs is placed at external layer. Give some specific and main reasons?   Answer

Design the transverse reinforcement, Figures (a) and (b) respectively give ...

Figures (a) and (b) respectively give details of a simply-supported bridge beam and its (idealised) cross-section. In addition to the dead load of 25 kN/m (including self weight),

Bridge loadings, Bridge Loadings: Loadings of bridges have been standa...

Bridge Loadings: Loadings of bridges have been standardized by the Roads Congress. The major features of the various load classes are given below : Bridges and culvert

Protection of lorry on the line, i. On single line by one or two men as req...

i. On single line by one or two men as required following and proceeding the lorry at a distance of 600 m. on the BG and 400 m. on the MG & NG carrying a banner flag across the tra

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd