Budgeted cost of work performed (bcwp), Project Management

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.
Posted Date: 9/27/2012 4:01:21 AM | Location : United States







Related Discussions:- Budgeted cost of work performed (bcwp), Assignment Help, Ask Question on Budgeted cost of work performed (bcwp), Get Answer, Expert's Help, Budgeted cost of work performed (bcwp) Discussions

Write discussion on Budgeted cost of work performed (bcwp)
Your posts are moderated
Related Questions
R Company produces a range of hair and beauty products. T, the Finance Director, and P, the Marketing Director, are reviewing the outcome of some product portfolio analysis which h

Number of post-release defects (found by clients in field operation), categorized by level of severity Ratio of defects found internally prior to release (by inspections and tes

Question 1) Describe any ten overall functions of the purchasing department Question 2) Describe any five principles of plant layout Question 3) Describe the any

Product Based Layout Also called the straight line layout or layout for serialized manufacture, product layout involves the arrangement of machines in one line depending upon

Define the role of initiation phase in the project management. Initiation phase: The initiation phase is the starting of the project. In this phase, the concept for the p

i want to know about the codes of a beauty parlour management website.

what is the maniipulated variable in a wood experiment

What is the purpose of the privatisation of public sector undertakings? Purpose of the privatisation of public sector undertakings: There have been purposes which have und

Task As the project manager you are required to present an initial project report to the project sponsor that shows how you propose to implement this project. As the project manag

1)  Compare your chosen Whole Healing System and Modality by considering: a)  When and by who were they 'invented'? b)  How have the therapies changed over time? c)  What