Budgeted cost of work performed (bcwp), Project Management

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.
Posted Date: 9/27/2012 4:01:21 AM | Location : United States







Related Discussions:- Budgeted cost of work performed (bcwp), Assignment Help, Ask Question on Budgeted cost of work performed (bcwp), Get Answer, Expert's Help, Budgeted cost of work performed (bcwp) Discussions

Write discussion on Budgeted cost of work performed (bcwp)
Your posts are moderated
Related Questions
What are the purposes of budgets in risk management? The purpose of budgets: P   Planning R  Resource employment or responsibility accounting I   Integration and/o

Question: (a) Past projects have shown that cost escalation is a common phenomenon with respect to the amount by which actual costs increases overrun the initial estimated cos

Question: a) Why are GSD projects more difficult to manage than single site collocated projects? b) Which agile practices would be easier to adopt, and which would be challe

what are the objective of the project alignment session program?

what is a benefit of a kaizen event?

Calculate the elapsed time of the critical path project when A Critical path of ACDEFGIJ is given below and the elapsed time of the project is 25 weeks. Th

Factors of Quality The implications here are that quality is to be viewed in its totality and not restricted only to the quality of production or products or some aspects

Question: (a) Describe why risk management is a crucial component of project management. (b) Critically show the different responses to risks that should be developed ear

What are the disadvantages of critical path analysis? Disadvantages of critical path analysis (CPA): a. Supposes a trade off among time and money but most staff cost coul

Q. What is a project life cycle? If a project is well prearranged it will progress logically through several phases. There are four standard stages to a typical project. The fi