Budgeted cost of work performed (bcwp), Project Management

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.
Posted Date: 9/27/2012 4:01:21 AM | Location : United States







Related Discussions:- Budgeted cost of work performed (bcwp), Assignment Help, Ask Question on Budgeted cost of work performed (bcwp), Get Answer, Expert's Help, Budgeted cost of work performed (bcwp) Discussions

Write discussion on Budgeted cost of work performed (bcwp)
Your posts are moderated
Related Questions
A good leader is not necessarily a good manager.” Discuss this statement & compare leadership With management.

The individual is a central feature of organisational behavior and a necessary part of any behavioral situation. According to the study findings, that organisational value has help

C ustomer value There is a considerable debate within the business world on whether the companies will have to deliver value for the shareholders or the customers. There are m

Q. How do I get started? At one as well as the same time this step is possibly the most important and least understood of all the steps in the project management process. Entir

Question 1: Using the "Matrix" system of authority and responsibilities, describe the various organisational systems which may be applied to the management of projects. Disc

A) Hierarchical planning in Operations/Production management and types of time frames in each hierarchy. (B) Explain who role players are in each level and what they are respons

Question 1: a. State the purposes of Malcolm Baldrige Quality Award b. Compare Balridge award criteria with TQM. A Purpose of MBNQA Question 1: What do you meant by qu

Combined Layout The application of the principle of product layout, process layout or fixed location layout in their strict meanings is difficult to come across. A combination

Purpose of Automated Storage and Retrieval Systems The main purposes of installing ASRS are as follows: 1. Increase Storage Capacity : ASRS ordinarily  increase the  stora

This project requires you to choose an organisation of your own choice and discuss on the following with respect to your chosen organisation: External Environment Mega