Budgeted cost of work performed (bcwp), Project Management

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.
Posted Date: 9/27/2012 4:01:21 AM | Location : United States







Related Discussions:- Budgeted cost of work performed (bcwp), Assignment Help, Ask Question on Budgeted cost of work performed (bcwp), Get Answer, Expert's Help, Budgeted cost of work performed (bcwp) Discussions

Write discussion on Budgeted cost of work performed (bcwp)
Your posts are moderated
Related Questions
Change Management Plan for an Organisation Explain: (i) Background to organization (one page max) (ii) Analyse the organization situation by conducting a force field anal

P roject value The organisations add value to the business through the series of processes. Increasingly such processes are usually undertaken within the context of the projec


Group Technology or Cellular Manufacturing (CM) Layout In group Technology /Cellular Manufacturing ( C M ) Machines are grouped into cells and the cells function somewhat like

Electronic Document Delivery Systems: The systems employing electronic technology for the receipt of requests and supply of documents are known as Electronic Document Delivery

Quality is customer defined: Quality of service or service excellence is a desire to maintain or strengthen the commitment to the library's philosophy of service to users. Qua

Explain about the Break Even Analysis. Break Even Analysis: Break even Analysis means that at some point within the operations, total revenue equivalent to total cost. Break ev

Quantitative Layout Analysis - Correlation Chart  In this technique we draw a gird with rows presenting alternative solutions. Plant item can be a ground floor (G >F) First fl

Question 1: "HRM is regarded by some personnel managers as old wine in new bottles". (Armstrong, 1987). Discuss. Question 2: "The contribution of HR function is insig

Q. Why do projects always seem to take longer than expected? Usually this is because it is relatively easy to assign time allowances to all the activities that have been though