Budgeted cost of work performed (bcwp), Project Management

Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management is the budgeted cost of work that has truly been done in carrying out a scheduled task in a particular time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed parts of open work packages, plus the applicable part of the budgets for level of effort and apportioned effort. BCWP is an Earned value management word and it is dissimilar from:

  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been assigned to complete a scheduled task within a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been used up, rather than the budgeted cost.

As example of the difference assume that a schedule contains:

  • a work "Test hardware" that is budgeted to cost $1000 to be done, and
  • is probable to begin at the start of January 1 and
  • Finish at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,

  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.

Assume that by the end of January 5, the work is just only 30% complete. In this situation,

  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.

Also, assume that to reach the 30% complete level at the finish of January 5, $250 was actually spent.

  • Then, the ACWP would be $250.
Posted Date: 9/27/2012 4:01:21 AM | Location : United States







Related Discussions:- Budgeted cost of work performed (bcwp), Assignment Help, Ask Question on Budgeted cost of work performed (bcwp), Get Answer, Expert's Help, Budgeted cost of work performed (bcwp) Discussions

Write discussion on Budgeted cost of work performed (bcwp)
Your posts are moderated
Related Questions
Problem 1: a) ‘Project Management is closely linked with the management of change' Explain why. b) Elaborate on two models of change. Explain the relevance, applicability

What types of errors disclosed in Trial Balance? A Trial Balance discloses the given types of errors as illustrated follows: a. An item posted two times. b. A mistake int

What is Project Portfolio Matrix? Choose three Projects A, Project B, Project C from any organization or where you are currently working as a Functional Manager. 1) Develop Project

what do you understand by the term analystical methods of production

o Is the business problem that the project addresses clearly defined? o Is the list of stakeholders (ie people affected) by the project complete and correct? o Is the scope o

Describe the follow-up phase, in short. Follow-up phase: Although this is extremely significant, the follow-up phase is frequently neglected. Throughout this phase, the w

Name an approach to systems implementation?  Matrix operation.

Quality Measurement Procedure: Quality as a strategic issue implies (i) acceptance of the importance of customer requirements throughout the organization,  (ii) the identifica

Calculate the elapsed time of the critical path project when A Critical path of ACDEFGIJ is given below and the elapsed time of the project is 25 weeks. Th

I need a thesis statement as if it were for a paper written on • Managing project resources: time, cost, quality, risk, and scope. This needs to be plagiarism free.