Test if the system operates in the production environment

Assignment Help Computer Networking
Reference no: EM13946129

You may use the annotated sample testing plan discussed below:

The following is an annotated sample testing plan outline following the "IEEE Standard for Software Test Documentation-IEEE Std 829-1998" (https://www.ruleworks.co.uk/testguide/IEEE-std-829-1998.htm).

1. Introduction. This section could have the following subsections:

a. Objectives: High level description of the scope, approach, resources, and schedule of the testing activities. It should also include a concise summary of the test plan objectives, the products to be delivered, major work activities, major work products, major milestones, required resources, and master high-level schedules, budget, and effort requirements.

b. Background

c. Scope: This section specifies the plans for producing updates to this software testing plan document itself and the methods for distribution of updates along with version control and configuration management requirements.

d. Reference

e. Definitions and Notations

2. Test items. The following documents need to be referred in this section: requirements specification, design specification, users guide, operations guide, installation guide, features, defect removal procedures, and verification and validation plans.

The following subsections could be included in this section then.

a. Program Modules

b. Job Control Procedures

c. User Procedures

d. Operator Procedures

3. Features to be tested

4. Features not to be tested

5. Approach. Testing approaches should be described in sufficient detail to permit accurate test effort estimation. This section should identify the types of testing to be performed and the methods and criteria to be used in performing test activities. The specific methods and procedures for each type of testing should be described in details. The criteria for evaluating the test results and the techniques that will be used to judge the comprehensiveness of the testing effort should also be discussed.

This section could include the following subsections:

a. Unit Testing

b. Integration Testing

c. Conversion Testing: Test whether all data elements and historical data is converted from an old system format to the new system format.

d. Job Stream Testing: Test whether the system operates in the production environment.

e. Interface Testing

f. Security Testing

g. Recovery Testing: Test whether the system restart/backup/recovery operations work as specified.

h. Performance Testing

i. Regression Testing

j. Acceptance Testing

k. Beta Testing

6. Pass/Fail criteria. One of the most difficult and political problems is deciding when to stop testing. The example criteria for exiting testing include (but are not limited to): scheduled testing time has expired (very weak criteria), some predefined number of defects discovered, all the formal tests have been executed without detecting any defects (tester may lose motivation under this criteria), or a combination of the above. This section may include the following subsections:

a. Suspension Criteria: when to suspend all or a portion of the testing activity on test items associated with the plan?

b. Resumption Criteria: the conditions that need to be met to resume testing activities after suspension.

c. Approval Criteria: The conditions for the approval of test results and the formal testing approval process. This section should also define who needs to approve a test deliverable, when it will be approved, and what is the backup plan if an approval cannot be obtained

d. Metrics: "You cannot control what you cannot measure" (see [Tom DeMarco]). A metric is a measurable indication of some quantitative aspect of a system. It is able to be measured, and it is independent (of human influence), accountable, and precise. A metric can be a "result", or a "predictor". A result metric measures a completed event or process (e.g., total elapsed time to process a business transaction). A predictor metric is an early warning metric with a strong correlation to some later result (e.g., predicted response-time through statistical regression analysis when more terminals are added to a system). The motivation for collecting test metrics is to make the testing process more effective.

7. Testing process

a. Test Deliverables: example test deliverables include (but are not limited to): test cases, testing report logs, test incident reports, test summary reports, and metrics' reports.

b. Testing Tasks and Dependencies: The sequence of tasks in the project work plans should be analyzed for activity and task dependencies.

c. Responsibilities: this will include the groups (e.g., developers, testers, operation staff, technical support staff, data administration staff, and the users) responsible for managing, designing, preparing, executing, witnessing, checking, and resolving test activities.

d. Defect recording/tracking process: Defect control procedures need to be established to control this process from initial identification through to reconciliation.

e. Configuration procedures. Assembling a software system involves tools to transform the source components, or source code, into executable programs. Example tools are compilers and linkage editors. Configuration build procedures need to be defined to identify the correct component versions and execute the component build procedures.

f. Issue resolution procedures. Testing issues can arise at any point in the development process and must be resolved successfully. The primary responsibility for issue resolution lies with the project manager who should work with the project sponsor to resolve them.

g. Resources

h. Schedule

8. Environmental requirements

a. Hardware

b. Software

c. Security

d. Tools: the special software tools, techniques, and methodologies employed in the testing efforts should be listed along with the purpose and use of each tool. Plans for the acquisition, training, support, and qualification for each tool or technique should be included also.

e. Publications

f. Risks and Assumptions

9. Change management process.

a. Change request process: Change control is the process by which a modification to a software component is proposed, evaluated, approved or rejected, scheduled, and tacked.

b. Version control process: A method for uniquely identifying each software component needs to be established via a labeling scheme. Software components evolve through successive revisions, and each needs to be distinguished. A simple way to distinguish component revisions is with a pair of integers 1.1, 1.2, etc., which define the release number and level number

10. Plan approvals. This should include the names, signatures, and dates of the plan approvers

Reference no: EM13946129

Questions Cloud

Estimate the velocity boundary layer thickness : Consider a 0.25-m-long vertical plate that is at 70°C. The plate is suspended in quiescent air that is at 25°C. Estimate the velocity boundary layer thickness and maximum upward velocity at the trailing edge of the plate.
Find the probability that returns will exceed 55% : Estimate descriptive statistics for each investment via Excel. Compare the two investments. Be sure to comment on the central tendency, variability and shape of these two investments (Note: use the most appropriate measure when comparing the varia..
Articles found in various business journals : Part A Select a firm that is publicly traded. This ensures you can access the needed data and information from published financial disclosures and articles found in various business journals such as Strategic Finance, Management Accounting Quarter..
Explain the principles and requirements of uk law : In your role as information manager you are giving a one-day workshop on data protection and privacy legislation to managers. Develop a set of ten slides which explain the principles and requirements of UK law.
Test if the system operates in the production environment : This section specifies the plans for producing updates to this software testing plan document itself and the methods for distribution of updates along with version control and configuration management requirements.
Inner surface of a circular tube : The final step of a manufacturing process in which a protective coating is applied to the inner surface of a circular tube involves passage of dry, atmosphere air through the tube to remove a residual liquid associated with the process. Consider a..
Best strategy for monitoring the performance of sql server : What can be done within the database itself to increase performance? Be sure to cite your sources.
Discusses the market share of the firm : Overall market share; Discusses the market share of the firm and its top competitors by providing details on current percentages for each firm and describing the trend over time
How fast data be transferred between the computer and disk : Bandwidth (how fast can data be transferred between the computer and disk?)

Reviews

Write a Review

Computer Networking Questions & Answers

  What was the most important aspect of the csiro patent

Investigate the history of the CSIRO Wifi patent which was recently up-held in courts in the United States. This patent covers significant aspects of the OFDM implementation which is used in modern Wifi devices.

  Provide a document that addresses all issues

XUMUC is has the WAN links in place to the new locations in the Houston Region. XUMUC currently has 2 other Regions San Francisco and Denver. Originally, XUMUC was only in one region (San Francisco).

  Compare the video voice and data formats recognize at least

compare video voice and data formats. identify at least three bandwidth techniques and how you would manage them with

  Design and document an ip addressing scheme

Design and document an IP addressing scheme to meet ElectroMyCycle's needs. Specify which IP address blocks will be assigned to different modules of your network design.

  The 2 main types of communications media used for network

the 2 main types of communications media used for network connections are wired connections and wireless connections.

  Define the subnet

Define the subnet (based on: rooms, floor, department, or other criteria). For each subnet, explain which devices/groups/users/rooms will be on this subnet, define the network address, subnet mask, and available IP addresses to be used by computers o..

  Part athis part consists of 40 multiple choice questions

part athis part consists of 40 multiple choice questions. each question has one and only one correct answer. you need

  Difference between server-side and client-side scripting?

difference between server-side and client-side scripting?

  Implement buffer overflow in cthe effect of launching new

implement buffer overflow in cthe effect of launching new applications is the growth of vulnerabilities to attacks. the

  Collaboration systems at isuzu australia limited

Summarize the main reason(s) that prompted Isuzu Australia Limited (IAL) to use collaboration technologies.

  Explain the flaw in the following reasoning

Identify and briefly explain any four key requirements that need to be examined when considering deploying a WLAN technology. [300words]

  Define the causal order for the transitions of a system

Define the causal order for the transitions of a system with synchronous communication. Define clocks for such systems, and give a distributed algorithm for computing a clock.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd