Populate the gantt chart using given table

Assignment Help Project Management
Reference no: EM13839746

Download the spreadsheet, gantt-chart_L.xls, from the Files area of this course.

Open the spreadsheet and read the terms of use (on the 2nd worksheet tab)

Use the data from the following table to populate the Gantt chart. You can either treat these as individual tasks, or just make these subtasks of a single task. Either way, you'll need to read the instructions in the spreadsheet to add some rows.

Description

Task

Must follow

Expected Time (Days)

Meetings for ideas

P

None

9

Information Searching for the game

Q

P

12

Draft design of the gameplay

R

Q

3

Write up the story lines

S

R, Z

7

Write up the specification of the game

T

P

11

Draft the proposal

X

None

8

Finalize the proposal with members

Y

X

14

Design the main characters

Z

T, Y

5


(This particular set of tasks is from Jamson Chan, formerly available at https://mh-ict.vtc.edu.hk/~mtchan/cgd/ganttChartExercise2.doc)

Leave the start date for the entire project as September 7, 2015. You may set the amount completed to any reasonable value, or just leave it at 0. Put your name in the spreadsheet replacing the field Project Lead. You should only change data fields, not formulas. The data fields are all colored light green. If you think you need to change some other color field, talk to the instructor first.

In a separate document, write a paragraph or two about why you think your Gantt chart is correct. What do you like about this way of creating a Gantt chart? What do you dislike? What are some limitations that you see with this approach? What should happen when you change the length of time for Task P, Meetings for ideas, from 9 to 15 days? What actually happens?

For extra credit, read the Help section (gray colored area on the spreadsheet) and fix the spreadsheet so that it can automatically adjust dates based on the lengths of prior tasks. If you complete this, add a brief description of your changes to your report. This is worth up to an additional 2 points on this assignment.

Attachment:- gantt-chart_l_0.xls

Reference no: EM13839746

Questions Cloud

Compute the incremental income after taxes : 1) Compute the incremental income after taxes that would result from these projections: 2) Compute the incremental Return on Sales if these new credit customers are accepted:
Decision case impact the validity of the board : If auditing of financial statements is required for the protection of public investors, should not all PCAOB members be taken from the investment community that uses audited financial statements. Why or why not
What is the anngle of the particles direction of travel? : what is the anngle of the particles direction of travel?
Compare classical conditioning and operant conditioning : Compare and contrast classical conditioning and operant conditioning. According to the research you have undertaken, which theory is more effective in marketing?
Populate the gantt chart using given table : Use the data from the following table to populate the Gantt chart. You can either treat these as individual tasks, or just make these subtasks of a single task. Either way, you'll need to read the instructions in the spreadsheet to add some rows
What is length of runway required for the plane to take off : What is the length of runway required for the plane to take off
Algebraic time value of money equations : Please use Excel financial functions or algebraic time value of money equations in your Excel cell formulas to answer these questions in your spreadsheet in order to receive credit for correct answers.
Explore some option of msgbox style : Problem 1: Write a sub routine to display the following message. The message should at the top of all other window, and it should prevent the user from doing anything in any application until one of the buttons is clicked.
Conduct a scenario analysis - what is its expected npv : Suppose that the project would be allocated $10,000 of existing overhead costs. Should these costs be included in the cash flow analysis? Explain.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd