Part 1:

Top management has accepted the schedule created at the end of Part. Prepare a brief memo that addresses the following questions:

1. How much will the project cost? What is the most expensive activity?

2. What does the cash flow statement tell you about how costs are distributed over the life span of the project?

Include a monthly cash flow for the project.

Once you are confident that you have the final schedule, save the file as a baseline.
Hint: Save a backup file just in case without baseline!

Part 2:

Part A

Today's date is July 8, 2015, the milestone date for the completion of the Prototype. You are charged with preparing a status report for top management. Table A2.8 summarizes progress on the Red Zuma project:

TABLE: Red Zuma Project Update

 

Task Name

Act. Start

Act. Finish

% Comp.

Phys. % Comp.

Act. Dur.

Rem. Dur.

1

1 Red Zuma

Fri 1/9/15

NA

46%

0%

125.85 days

146.4 days

2

 1.1 Market Analysis

Fri 1/9/15

Thu 2/12/15

100%

0%

25 days

0 days

3

 1.2 Product Design

Fri 2/13/15

Wed 4/1/15

100%

0%

35 days

0 days

4

 1.3 Manufacturing Study

Fri 2/13/15

Fri 3/6/15

100%

0%

16 days

0 days

5

 1.4 Product Design Selection

Thu 4/2/15

Fri 4/17/15

100%

0%

13 days

0 days

6

 1.5 Detailed Marketing Plan

NA

NA

0%

0%

0 days

15 days

7

 1.6 Manufacturing Process

NA

NA

0%

0%

0 days

30 days

8

 1.7 Detailed Product Design

Mon 4/20/15

Wed 6/24/15

100%

0%

49 days

0 days

9

 1.8 Build Prototypes

Wed 6/10/15

NA

39%

0%

9 days

14 days

10

 1.9 Lab Test Prototypes

NA

NA

0%

0%

0 days

10 days

11

 1.10 Field Test Prototypes

NA

NA

0%

0%

0 days

15 days

12

 1.11 Finalized Product Design

NA

NA

0%

0%

0 days

20 days

13

 1.12 Final Manufacturing Process

NA

NA

0%

0%

0 days

10 days

14

 1.13 Order Components

NA

NA

0%

0%

0 days

7 days

15

 1.14 Order Production Equipment

NA

NA

0%

0%

0 days

14 days

16

 1.15 Install Production Equipment

NA

NA

0%

0%

0 days

35 days

17

 1.16 Celebrate

NA

NA

0%

0%

0 days

1 days

Submit a professional status report to Robin Lane that addresses the following questions:

1. How is the project progressing in terms of cost and schedule?

2. What activities have gone well? What activities have not gone well?

3. How much of the project has been accomplished (PCIB)?

4. What is the forecasted cost at completion (EACf)?

5. What is the estimated completion date?

6. How is the project doing in terms of priorities (see Part 1)?

Report and interpret relevant Earned Value metrics in your report.

Include a Tracking Gantt chart as well as an Earned Value Table with your memo.

Part B

You have told Robin Lane that based on what you know now you need to revise the estimates for some of the remaining activities. Detailed Product Design is expected to take 3 days longer than planned. Build Prototypes is expected to take 2 days less than planned and Finalized Product Design is expected to take 3 days longer than planned. Final Manufacturing Process is expected to take 2 days less than planned, while Install Production Equipment is now expected to take only 30 days.

You also report that Detailed Marketing plan will be completed before the end of the New Year. She is insisting that the project be completed by January 17th in order to be ready for the Las Vegas show. She is willing to spend $50,000 from Management Reserves to expedite shipping if necessary. $25,000 would reduce the shipping of components by 5 days and/or $25,000 would reduce the shipping of manufacturing parts by 5 days (Hint: Adjust lag).

Prepare a memo to Robin that addresses the following questions:

1. What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost?

2. Would you recommend authorizing the expenditure of $50,000? Explain.

3. What, if any other recommendations, would you make so that the project can achieve Robin's deadline? Justify your recommendations.
Include a Tracking Gantt chart with variance schedule that depicts your final recommendations and revised schedule.

Hint: After adjusting the Installation of Production Equipment and Finalized Product Design, level outside of slack to eliminate any resource over allocation problems.

Verified Expert

The solution document contain 2000 words which discussed about red zuma project. It has solution for part-3, Party 4a and part 4b memos with cash flow schedule and table.

Reference no: EM13985025

Questions Cloud

What is the magnification : The lens is made of a material with an index of refraction of 1.5. If an object is placed 10 cm to the left of the lens where will the image be formed? What is the magnification? Is the image is real? Is the image inverted? Draw a ray diagram for ..
What is the minimum diameter the wire should have : The elastic limit for the wire is 2.0 x 108 Pa. What is the minimum diameter (in mm) the wire should have to support her?
Conditional expectation in bridge : Let X be the number of clubs in the hand of North and Y the number of clubs in the hand of South in a bridge game. Write a general formula for E.X jY D y/, and compute E.X jY D 3/. Can you compute E.Y jX D 3/?
Ethics and information technology : The APA style three page paperon ethics and information technology and how it touch the ethics of using technology how complicated making ethical decisions about its use truly is. Portents of this cannot be overstated as you know simply by living in ..
How costs are distributed over the life span of the project : How much will the project cost? What is the most expensive activity - what does the cash flow statement tell you about how costs are distributed over the life span of the project?
Discuss the concept of video sharing : Explain how to market with article directories, e-books, and white papers. Discuss the concept of video sharing. Explain benefits of marketing with online videos
How is metamaterials not an existing tag : I understand how one can obtain a -ve ρ by constructing a solid-solid system with vastly different speeds of sound? How is metamaterials not an existing tag?
What is the electric field potential at a point p : Two point charges of +2.00 μC and +4.00 μC are placed at the origin and at y = -0.300m, as shown in Figure 20-8. What is the electric field potential at a point P at a position x = 0.400 m due to the charges?
Experiment of picking one word at random : Consider the experiment of picking one word at random from the sentence

Reviews

Write a Review

Project Management Questions & Answers

  Business communication - routine and goodwill emails

Describe why you chose to emphasize these principles and why you wrote your message as you did. Discuss your objectives and how you used the background readings.

  Conflict managementchannels of communicationgive three

conflict managementchannels of communicationgive three examples of behaviors that indicate the existence of conflict

  Functional pure project and matrix team structuresthere are

functional pure project and matrix team structuresthere are three different team structures. they are functional pure

  Discuss the various methods for selecting projects which

project integration management please respond to the followingdiscuss the various methods for selecting projects. which

  Project managementwhat is the importance of a variance to a

project managementwhat is the importance of a variance to a project budget schedule or specification? how does a pm

  Management role in productionjoe a newly appointed manager

management role in productionjoe a newly appointed manager for best made mfg. lasted a mere 3 weeks before being placed

  Give your opinion after reviewing the scope planning and

1.identify at least four of the key decisions made during the pre-initiating and initiating processes. do you think

  What is the definition of total quality management

What is the definition of total quality management?

  Vision of the project advancement corporationas the project

vision of the project advancement corporationas the project manager for advancement corporation you act as the ceos

  Judgment in matter of the project by project manager

How important is it for a project manager to have expert judgment in the subject matter of the project?

  Prepare information systems-related activities to maximize

a written project plan revised business requirements document project plan powerpoint presentation and a finalized

  Project management and decision makingrespond to the

project management and decision makingrespond to the following in discussion- who approves and reject changes to the

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd