On February 5, Devon entered into a written agreement with Gordon whereby Gordon agreed to drill a well on Devon's property for the sum of $5,000 and to complete the well on or before April 15. Before entering into the contract, Gordon had made test borings and had satisfied himself as to the character of the subsurface. After two days of drilling, Gordon struck hard rock.
On February 17, Gordon removed his equipment and advised Devon that the project had proved unprofitable and that he would not continue.
On March 17, Devon went to Gordon and told Gordon that he would assume the risk of the enterprise and would pay Gordon $100 for each day required to drill the well, as compensation for labor, the use of Gordon's equipment, and Gordon's services in supervising the work, provided Gordon would furnish certain special equipment designed to cut through hard rock. Gordon said that the proposal was satisfactory.
The work was continued by Gordon and completed in an additional fifty-eight days. Upon completion of the work, Devon failed to pay, and Gordon brought an action to recover $5,800.
Devon answered that he had never become obligated to pay $100 a day and filed a counterclaim for damages in the amount of $500 for the month's delay based on an alleged breach of contract by Gordon. Explain who will prevail and why.
What is the purpose of the tool
: What is the purpose of the tool?What features does the tool have?What industries benefit most from this type of tool?What similar tools are available from competing BI solution provides?
|
Is barbara bound by her acceptance of the offer
: Barbara cashed the check, collected on the note, and one month later sued Alan for $3,000. Is Barbara bound by her acceptance of the offer?
|
Discuss and explain whether there is valid consideration
: Discuss and explain whether there is valid consideration for each of the following promises:- A and B entered into a contract for the purchase and sale of goods. A subsequently promised to pay a higher price for the goods when B refused to deliver ..
|
Advantages and disadvantage of a redesigned joint
: Redesign the right member for increased load capacity by means of improved adhesive bonding. Consider the force flow concept and comment on the advantages and disadvantage of a redesigned joint.
|
Explain who will prevail and why
: Devon answered that he had never become obligated to pay $100 a day and filed a counterclaim for damages in the amount of $500 for the month's delay based on an alleged breach of contract by Gordon. Explain who will prevail and why.
|
Analyze three specific potential malicious attacks
: Analyze three (3) specific potential malicious attacks and / or threats that could be carried out against the network and organization.Explain in detail the potential impact of the three (3) selected malicious attacks.Propose the security controls t..
|
What contract if any exists between snyder and union
: The Snyder Mfg. Co., being a large user of coal, entered into separate contracts with several coal companies.- What contract, if any, exists between Snyder and Union?
|
Which is the most reliable test method
: High strength carbon steels (HSLA) are limited to a relatively low yield strength/hardness in subsea use, due to hydrogen embrittlement. Which is the most reliable test method? This may be based on earlier thesis work, and published literature
|
Design a spring for the iron arms
: Design a spring for the Iron Arms which would allow children to use it effectively. The maximum spring force should be 25-50% of the adult version and have infinite fatigue life.
|