Evaluate the performance of each project proposal

Assignment Help Project Management
Reference no: EM134245

A multi-project organization is seeking to fund one project out of 3 project proposals (A,B,C). Following, key information about each project is provided to enable a multi-criteria decision making process that is detailed in the last section.

PROJECT A:

An analysis of the overall project risk resulted in classifying Project A as a "risky project" because it scores 8 in a risk scale of 10 (in the scale 1 = very low risk). 

Subject matter experts were asked the question: Do you think Project A has the capability to attract more projects from the current customer and from new customers? 8 out of 10 agreed it has attraction capability.

Project A's life cycle is expected to be 2 years. During these 2 years project A is expected to cost:

The market life cycle of the project A's deliverable is 5 years (i.e., a product/system life cycle of 7 years). Project A is expected to start to generate revenues at the beginning of year 3. The expected revenues of project A are:

Annual costs during the market life cycle are expected to be:

PROJECT B:

An analysis of the overall project risk resulted in classifying Project B as a "very low risk project" because it scores 1 in a risk scale of 10 (in the scale 1 = very low risk).

Subject matter experts were asked the question: Do you think Project B has the capability to attract more projects from the current customer and from new customers? 2 out of 10 agreed it has attraction capability.

Project B's life cycle is expected to be 7 years. During these years Project B is expected to cost:

The market life cycle of the Project B is 30 year (i.e., a product/system life cycle of 37 years).  Project B is expected to start to generate revenues at the beginning of year 2. The expected revenues of Project B are:

Annual costs during the market life cycle are expected to be:

PROJECT C:

An analysis of the overall project risk resulted in classifying Project C as a "low risk project" because it scores 3 in a risk scale of 10 (1 = very low risk).

Subject matter experts were asked the question: Do you think Project C has the capability to attract more projects from the current customer and from new customers? 7 out of 10 agreed it has attraction capability.

Project C's life cycle is expected to be 2 years. During these years Project C is expected to cost:

The market life cycle of the Project C is 5 year (i.e., a product/system life cycle of 6 years).  Project C is expected to start to generate revenues at the beginning of year 3. The expected revenues of Project C are:

 Annual costs during the market life cycle are expected to be:

Multi Criteria Decision Problem: Based on the information provided about each project proposal, please identify the best two projects to be funded by the multi-project organization using the AHP method covered in class. If there is a tie or a close call between two projects, please support your recommendation of which ones were the best with a brief statement.

Next, there are key assumptions you need to make to evaluate these project proposals:

The criterion that will be used to evaluate each project proposal are:

o  Capability to Attract More Projects
o  Net present Value (NPV)
o  Overall Project Risk

  • The following pairwise comparison scale must be used to evaluate the importance of each criterion
  • A panel of subject matter experts agreed that:

o  The Capability to Attract More Project is weakly more important than the NPV 
o  The Capability to Attract More Project weakly more important than the Overall Project Risk Factor
o  The Overall Project Risk Factor is absolutely more important than the NPV

  • With respect to the financial performance of the project as measured by the NPV, the multi-project organization is seeking to have the highest NPV from its project investment at the end of year 4 (i.e., 4 years after the beginning of the project). The interest rate (or minimum acceptable rate of return for the project) is assumed to be fixed at 5%. 
  • To evaluate the performance of each project proposal with respect to their NPV the following pairwise comparison table is provided:

1  Equal NPV
2  i has an NPV greater than j and the difference between i and j ranges from >$0 to ≤ 2M 
3  i has an NPV greater than j and the difference between i and j ranges from >$2M to ≤ 4M 
4  i has an NPV greater than j and the difference between i and j ranges from >$4M to ≤ 6M 
5  i has an NPV greater than j and the difference between i and j ranges from >$6M to ≤ 8M 
6  i has an NPV greater than j and the difference between i and j ranges from >$8M to ≤ 10M 
7  i has an NPV greater than j and the difference between i and j ranges from >$10M to ≤ 12M 
8  i has an NPV greater than j and the difference between i and j ranges from >$12M to ≤ 14M 
9  i has an NPV greater than j and the difference between i and j is over >$14M

1  =  Items i, j are of equal importance
3  =  Item i is weakly more important 
5  =  Item i is strongly more important  
7 =  Item i is very strongly more important
9 =  Item i is absolutely more important

To evaluate the performance of each project proposal with respect to their Overall

Project Risk Factor the following pairwise comparison table is provided:

To evaluate the performance of each project proposal with respect to their Capability to Attract More Projects the following pairwise comparison table is provided.

Reference no: EM134245

Questions Cloud

Prepare core elements of a business plan : Prepare core elements of a business plan for preparing this new venture that include these points:
What is mass of the ice cube : What is mass of the ice cube
What is the turntable rotation angular velocity : What is the turntable rotation angular velocity
An average temperature of the rest of the universe : An average temperature of the rest of the universe
Evaluate the performance of each project proposal : To evaluate the performance of each project proposal with respect to their Overall
What is the ratio of the amplitude : What is the ratio of the amplitude
What is pressure in the cylinder : What is pressure in the cylinder
What is instantaneous acceleration : What is instantaneous acceleration
Case study: small business owner to customer : Case Study: Small Business Owner to Customer-You're Fired

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd