Workshop drawings, Civil Engineering

Assignment Help:

Workshop Drawings 

(Contractor Scope)

1. Air Conditioning and Ventilation Systems:

Builder work drawings

Enlarged scale double line HVAC System Duct & piping layouts with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Detailed installation drawings

2. Piping Systems:

2.1 Potable Water, Steam, and Hot Water Systems

Builder work drawings 

Enlarged scale double line workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings as per manufacturer recommendations

Isometric single line diagrams

2.3 Sanitary and Rainwater

Builder work drawings 

Enlarged scale double line workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings as per manufacturer recommendations

Isometric single line diagrams

2.4 Compressed Air

Builder work drawings

Enlarged scale double line workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings as per manufacturer recommendations

Isometric single line diagram

2.5 Process Chilled Water, Cooling Water, Brine, Glycol water, Ice water

Builder work drawings

Enlarged scale double line workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings as per manufacturer recommendations

2.6 Technical Gases

Builder work drawings

Enlarged scale double line workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings as per manufacturer recommendations

2.7 Irrigation

Builder work drawings

Enlarged scale workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings

2.8 Fire Fighting

Builder work drawings

Enlarged scale workshop drawings with sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Sectional details complete as  in above 

Detailed installation drawings as per manufacturer recommendations

3. Electrical Systems:

3.1 Electric Substation

Builder work drawings

Enlarged scale workshop drawings with wires, conduits, back boxes, bus bars, medium voltage and low voltage switch gear, cables, cable trays, lighting fixtures, power sockets  and isolator switches sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule. 

Detailed installation drawings

3.2 Independent power supply (UPS)

Enlarged scale workshop drawings with wires, conduits, back boxes, cables, cable trays, data sockets, security systems outlets (if applied), notes, symbols, abbreviations, submittals, materials 

Detailed installation drawings

3.3 Power and Lighting Plans

Builder work drawings

Enlarged scale workshop drawings with wires, conduits, back boxes, bus bars, cables, cable trays, lighting fixtures, power sockets and isolator switches sizing, notes, symbols, abbreviations, hungers, supports, submittals, materials and equipments schedule 

Detailed installation drawings


Related Discussions:- Workshop drawings

Explain the equation for a suppressed rectangular weir, Explain the Equatio...

Explain the Equation for a Suppressed Rectangular Weir If the approach velocity is negligible, velocity head can be excluded and the equation becomes the Francis weir equation

Levelling, the cooke''s reversible level

the cooke''s reversible level

Highway Engineering, I am a Civil Engg student. Why CBR Values determined ...

I am a Civil Engg student. Why CBR Values determined only at 2.5 and 5 mm penetration ?.

Explain the term - non-bonded prestressed concrete, Explain the term - Non-...

Explain the term - Non-bonded Prestressed Concrete It is a method of construction in which the tendons are not bonded to the concrete. Ducts, housing the tendons, are not grout

What is the specimen thickness, The thickness of a saturated specimen of cl...

The thickness of a saturated specimen of clay under a consolidation pressure of 100 kN/m 2 of is 24 mm and its water content is 20%. On enhance of the consolidation pressure to 20

Bricks, BRICKS Brick is obtained by moulding good clay into a block, wh...

BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin

Softening point of bitumen, Hi, i need discussion for softening point of bi...

Hi, i need discussion for softening point of bitumen 7.5 ?C

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Explain the rippl diagram or mass diagram, Explain the Rippl Diagram or Mas...

Explain the Rippl Diagram or Mass Diagram For a potable water reservoir, it is the simultaneous plots of the cumulative inflow and cumulative water consumption/demand, termed "

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!