For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

Maximum shear stress , the propane gas tank has an inner diameter of 1500mm...

the propane gas tank has an inner diameter of 1500mm and wall thickness of 15mm. If the wall is pressurized to 2MPa, determine the absolute maximum shear stress in the wall of tank

Cocrete, preparation and uses of concrete

preparation and uses of concrete

Solid block -calculating for design mix, Good evening sir, solid block''s d...

Good evening sir, solid block''s design mix calculated generally please explain and derive .

Plane table surveying, plane table surveying is used commonly to survey sma...

plane table surveying is used commonly to survey small areas because

Designing 10 story building, Hi need help with designing a 10 story concret...

Hi need help with designing a 10 story concrete building with basement car park. Need help with calculations in line with eurocodes. Is this something you can help with?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd