Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Degree, what classes do you have to take and what are some school options?

what classes do you have to take and what are some school options?

Extreme fiber stresses at the mid span section of the beam, Extreme fiber s...

Extreme fiber stresses at the mid span section of  the beam A pre-stressed concrete beam, of  cross section 300 mm x 500 mm and 8 m span, is pre-stressed with a parabolic tend

State the method of pre- tensioning, State the method of Pre- Tensioning ...

State the method of Pre- Tensioning It is a method of prestressing concrete in which tendons are stretched or tensioned before concreting. In this form of construction, concr

Define steel substructure - underwater inspection of bridge, Define Steel s...

Define Steel substructure - underwater inspection of bridge? Steel is used as a structural material and as external protective cladding on concrete foundation elements. Steel f

Importance of geotextiles and sand in reclamation works, Question What ...

Question What is main importance of geotextiles and sand in reclamation works? Answer For geotextiles used in recovery, they serve mainly subsequent two purposes

Surveying, what is the trignomerty leveling

what is the trignomerty leveling

Show the differences between GGBS and PFA, Q. Show the Differences Between ...

Q. Show the Differences Between GGBS and PFA? The use of GGBS as substitute of cement improves smaller reliance on PFA. Particularly GGBS is supposed to be more compatible with

Concrete technology, why strength of transition zone is less than bulk past...

why strength of transition zone is less than bulk paste

Calculate the percent change in load on the wall form tie, A concrete wall ...

A concrete wall form tie with an ultimate strength capacity of 2,400-lbs is designed for use in a concrete wall form with an 18-in center to center spacing. During formwork inspect

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd