Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Calculate the initial height of the stockpile, On a 5-acre level terrain bu...

On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft sub-g

Distomat., write a note on distomat

write a note on distomat

Show the excessive movement joints in bridges, Q. Show the Excessive moveme...

Q. Show the Excessive movement joints in bridges? Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from

Explain flocculation, Explain Flocculation Most important factor ef...

Explain Flocculation Most important factor effecting particle removal efficiency objective - to bring particles into contact so that they will collide, stick together

Estimate Bridge Pier Concrete, Takeoff the 3 elements for the following bri...

Takeoff the 3 elements for the following bridge pier components: 1. Pier Footing, 2. Pier Column, 3. Pier Cap (Top). • Misc Items to include Shear Key. • Misc Items to exclude Reba

Verify the coefficient of elastic uniform compression, Verify the coefficie...

Verify the coefficient of elastic uniform compression if a vibration test on a concrete block of 1 m cube gave a resonant frequency of 36 Hz in vertical vibration. The weight of

What will be the increase in horizontal thrust, A 9 metre high retaining wa...

A 9 metre high retaining wall retains a soil with the following properties: φ = 36°; γ = 18 kN/m 3 . What will be the enhance in horizontal thrust if the soil slopes up from the

Rcc and rbc, types mixing,curing,water cement ratio,qualities and workabili...

types mixing,curing,water cement ratio,qualities and workability

Concrete mix design for Volumetric site mix, Please advise what is the prop...

Please advise what is the proportion of mix to achieve 45N/sq. mm compressive strength with 370Kg.SR cement per cubic meter and 35N/Sq.mm strength with OPC cement 330 kg per cubic

Calculation of deformation, Calculation of deformation For calculation ...

Calculation of deformation For calculation of deformation at some stage before the total creep is reached,  it may be assumed that about half the total creep takes place  in  f

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd