Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Example, slope deflection with settlement

slope deflection with settlement

Harbour, typical layout showing dock,quay.jetties,turning circle,pier

typical layout showing dock,quay.jetties,turning circle,pier

Levelling, 1 advantages and disadvantages of rise and fall methodes

1 advantages and disadvantages of rise and fall methodes

Describe about the prestressed concrete, Describe about the Prestressed con...

Describe about the Prestressed concrete Civil engineering structures, such as buildings, bridges, dams, towers etc. and their structural components such as beams, columns, slab

RCC, WHAT IS RCC

WHAT IS RCC

Examine the state of stress at the junction of flange, Examine the state of...

Examine the state of stress at the junction of flange: A beam of I-section as shown in Figure (a) is subjected to a bending moment of 84.928 kN m and a shear force of 106.1 kN

Surface dressing - road pavements, Surface Dressing: Surface dressing...

Surface Dressing: Surface dressing is an application of a thin film of bituminous binder followed by a coat of aggregates of single size, rolled into position. Surface dressi

Timber, What is exogenous tree?

What is exogenous tree?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd