For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Bituminous macadam, Bituminous Macadam: Bituminous Macadam (BM) is a ...

Bituminous Macadam: Bituminous Macadam (BM) is a base course in which coarse aggregates are mixed with a bituminous binder. The mix is open-graded with 20-25 per cent voids.

Cumulative error, diffrence between cumilative compensative error

diffrence between cumilative compensative error

Surveying, earthen dam and gravity dam

earthen dam and gravity dam

Determine the probable period of time, A clay stratum is 4.5 m thick and re...

A clay stratum is 4.5 m thick and rests on a rock surface. The coefficient of consolidation of a sample of this clay was found to be 4.5 × 10-8 m 2 /s in the laboratory. Verify pro

Explain the statements about construction contract process, Explain the Sta...

Explain the Statements about the Construction Contract Process I. Surety bond assures the project owner a guarantee of funds equivalent to a promissory note. The surety bond is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd