For the project network shown, the late start time (day) for activity "Q" is most nearly:
Solution: List the paths leading to "Q" and calculate the duration for each.
L M = 4 + 7 = 11-days
L N P = 4 + 3 + 3 = 10-days
Q's early start time is 10-days
Q's late start time is 11-days
beam
Review of available Records - Preparation for Underwater Inspection? Before taking up the underwater inspection, a detailed review of drawings and past report should be carried
types mixing,curing,water cement ratio,qualities and workability
• The previous load analysis represents a first and necessary step in the analysis of the given structure but it does not tell us whether the given load can be safely supported (i.
Q. Diffrence between Hudsons and Van der Meer formula? Hudson's formula is usually adopted in preliminary design to attain rough initial estimate of rock size. This formula is
what does a civil engineer
resection
Question In determining effectual stress parameters of a soil sample, which test is good, consolidated undrained analysis or consolidated drained analysis? Answer Effec
why we perform survey work from whole to the part?
i need journals or articles of forensic structural engineering
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd