Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Rectangular tie, how to perform a rectangular tie using optical square?

how to perform a rectangular tie using optical square?

Classification of bricks, Bricks may be broadly classified as following: ...

Bricks may be broadly classified as following: Paving bricks Building bricks Special bricks A.   Fire bricks B.   Building Bricks: These bricks are utilized fo

Define bank volume to be stockpiled and used for backfill, An earthwork con...

An earthwork contract was awarded to excavate and backfill the foundation of a proposed 50-ft by 50-ft office building.  The existing grade elevation is 437.5-ft while the sub-base

Chemical prestressing, Chemical prestressing In prestressed concrete, ...

Chemical prestressing In prestressed concrete, normally tendons are stretched and are retained in a stretched condition by concrete. Consequently, concrete comes under compres

Influence of pressure in the soil, Q. Influence of Pressure in the Soil? ...

Q. Influence of Pressure in the Soil? Figure shows the stress state beneath a footing. The steady state situation prior to footing as well as qualitative variation of pressure

Write important factors that affect permeability of a soil, Determine the i...

Determine the important factors that affect the permeability of a soil. A permeameter of 8.2 cm diameter having a sample of soil of length 35 cm. It can be used either for const

PRC, what is the bleeding of concrete?

what is the bleeding of concrete?

Seismic joints, is the seismic joints like falling joints ? thanks :)

is the seismic joints like falling joints ? thanks :)

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd