For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Explain the term - circular prestressing, Explain the term - Circular Prest...

Explain the term - Circular Prestressing This term refers to the case when tendon profile is provided in a round shape, such as in water tanks and pipes, etc.

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Moment of inertia, i dont know how to calculate moment of inerta

i dont know how to calculate moment of inerta

Roofs, Dimensions of trusses

Dimensions of trusses

AUTOCAD, do you people deal with autocad

do you people deal with autocad

Moisture-density relationship, Moisture-Density Relationship: Since va...

Moisture-Density Relationship: Since various compactive efforts result in varying degrees of compaction, it is necessary to standardize the compactive effort. The most well-kn

Surveying, what is the trignomerty leveling

what is the trignomerty leveling

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd