For the project network shown, the late start time (day) for activity "Q" is most nearly:
Solution: List the paths leading to "Q" and calculate the duration for each.
L M = 4 + 7 = 11-days
L N P = 4 + 3 + 3 = 10-days
Q's early start time is 10-days
Q's late start time is 11-days
charring of timber
built in truss
Question What is function of shear keys in designing of retaining walls ? Answer In formative external constancy of retaining walls, failure modes similar to bearing failure, s
Q. Settlement due to Lowering of Water Table? Water table is encountered with, whenever any excavations are made for foundations. The water is to be out for working conditions.
how many scale are there and what are they use
An activated sludge tank treats 1 MGD from the primary clarify and has an X of 2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank and has
Explain the Normal Depth Equation The equation is derived from the Chezy-Manning equation. As written below it determines the diameter of a circular storm or sanitary sewer wh
Question Why are voids filled with lightweight infilling material in raft base of pumping stations ? Answer To decrease dead load and therefore to decrease settleme
what is the density of rcc
Common ways to present the project schedule include all except: a. Gantt charts b. Milestone charts c. PERT charts D. Project Network Diagrams with dates added So
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd