For the project network shown, the late start time (day) for activity "Q" is most nearly:
Solution: List the paths leading to "Q" and calculate the duration for each.
L M = 4 + 7 = 11-days
L N P = 4 + 3 + 3 = 10-days
Q's early start time is 10-days
Q's late start time is 11-days
slope deflection with settlement
typical layout showing dock,quay.jetties,turning circle,pier
1 advantages and disadvantages of rise and fall methodes
Describe about the Prestressed concrete Civil engineering structures, such as buildings, bridges, dams, towers etc. and their structural components such as beams, columns, slab
WHAT IS RCC
Examine the state of stress at the junction of flange: A beam of I-section as shown in Figure (a) is subjected to a bending moment of 84.928 kN m and a shear force of 106.1 kN
Surface Dressing: Surface dressing is an application of a thin film of bituminous binder followed by a coat of aggregates of single size, rolled into position. Surface dressi
hi
define of couple
What is exogenous tree?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd