Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Find the length of the chord, Q If the degree of curve is defined by the a...

Q If the degree of curve is defined by the angle at the center subtended by an arc (or chord) 20 meters, find the length of the chord in meters so that the versine measured in cm

Is codes for building design, IS CODES FOR BUILDING DESIGN The codes w...

IS CODES FOR BUILDING DESIGN The codes which help engineers to design buildings are following: 1. IS 456-2000. For the design of plain and reinforced concrete it is code

Analyse the state of stress, Analyse the state of stress: For the cros...

Analyse the state of stress: For the cross-section shown in above figure, let us take b = 100 mm, d = 300 mm and M = 9 × 10 7 N mm and Q = 18 × 10 4 N and analyse the state

Iron and steal, What does the term offset mean in relation to modulus of el...

What does the term offset mean in relation to modulus of elasticity?

Normal stress, how does wrong calculations in normal stress cause partial o...

how does wrong calculations in normal stress cause partial or total collapse of a building?

Highway engineering., history and development of indian road and planning

history and development of indian road and planning

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd