Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Explain the properties of poly tetra fluoro ethylene, Explain the Propertie...

Explain the Properties of Poly Tetra Fluoro Ethylene? PTFE is a linear chain polymer of great molecular strength, known for its chemical inertness and low coefficient of fricti

Stormwater, Design of the stormwater drainage system for the sub-division ...

Design of the stormwater drainage system for the sub-division Work needed: The following tasks require to be performed for the drainage network: Compute stormwater r

I have a take home quiz, Hello I have a take home final needs be ordered, d...

Hello I have a take home final needs be ordered, do you have very well skilled professionals to make it?

Retardation of fresh concrete, Retardation of fresh concrete has numerous b...

Retardation of fresh concrete has numerous benefits as below: (i)  A rapid hydration process leads to loss in concrete strength since concrete will have a poorer structure with

Surveying, What is the least count of prismatic and surveyor compass

What is the least count of prismatic and surveyor compass

Find the youngs modulus of the rod, Find the Youngs modulus of the rod: ...

Find the Youngs modulus of the rod: A composite rod is made by joining a copper rod end to end with a second rod of different material but of same cross-section. At 25oC, the

Deterioration in steel, How abrasion and earthquake causes deterioration in...

How abrasion and earthquake causes deterioration in steel structures

Contour interpolation, given A,B,C,and D are four plotted points at 2 centi...

given A,B,C,and D are four plotted points at 2 centimeter apart and their ground reduced levels are 57.5 meter 63.2 meter 68.2 meter and 59.2 respectively.it is required to draw co

Unloaded propped, Ask questa) In an unloaded propped cantilever, the proppe...

Ask questa) In an unloaded propped cantilever, the propped end sinks vertically relative to the fixed end by an amount ? due to poor construction of the foundation of the prop. Wha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd