For the project network shown, the late start time (day) for activity "Q" is most nearly:
Solution: List the paths leading to "Q" and calculate the duration for each.
L M = 4 + 7 = 11-days
L N P = 4 + 3 + 3 = 10-days
Q's early start time is 10-days
Q's late start time is 11-days
what is influence diagram & use
Allowable Strength Design (ASD) Process: - Apply service loads with no load factors - Assume linear elastic analysis of structure - Calculated stresses shall not excee
slabs and beam formwork
how to establish temporary benchmark
What is the safe bearing capacity of a rectangular footing, 1 m × 2 m, placed at a depth of 2 m in an saturated clay having unit weight of 20 kN/m 3 and unconfined compression str
what is framework
Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by
how tofind centroid of cercular arc
Q. Knife edge loads – representation of wheel axles? In BS5400 traffic loads for HA loading are given by uniformly distributed loads along loaded length and a knife edge load.
#cv
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd