Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Engg surveying, what does mean by too short and too long in erroneous tape ...

what does mean by too short and too long in erroneous tape length?

How to calculate the vertical stress, A rectangular foundation, 2 m × 4 m, ...

A rectangular foundation, 2 m × 4 m, transmits a uniform pressure of 450 kN/m 2 to the underlying soil. Verify the vertical stress at a depth of 1 metre below the foundation at a

Define installation of pot bearings, Define Installation of Pot Bearings? ...

Define Installation of Pot Bearings? In a sliding POT bearing, positive fixing to the main structure may not be required if the bearing is always subjected to adequate vertical

Function of longitudinal joints in concrete road pavements, Question Wh...

Question What is function of longitudinal joints in concrete road pavements ? Answer A longitudinal joint consists of a tie bar located at mid-depth of a concrete pav

Steel structures, how does battening differ from lacing?

how does battening differ from lacing?

Bridge, how to account for density?

how to account for density?

WMM, GRADATION OF WMM

GRADATION OF WMM

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd