Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Elaborate the term - prestressed concrete pipes, Elaborate the term - Prest...

Elaborate the term - Prestressed concrete pipes Liquid retaining structures, such as circular pipes, tanks and pressure vessels are suited for circular prestressing. The circum

Determine condition of activity in the network flow diagram, Determine the ...

Determine the condition of each activity in the network flow diagram shown below   Ans: a. Activity C can be started only after the completion of activities A and

Designing of retaining walls, Question What is function of shear keys in d...

Question What is function of shear keys in designing of retaining walls ? Answer In formative external constancy of retaining walls, failure modes similar to bearing failure, s

Key reasons for conducting pull-out tests, Question What are key reason...

Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo

Motion in one dimension, An F-16 lands on aircraft carrier and its velocity...

An F-16 lands on aircraft carrier and its velocity is 63 m/sn. If its decceleration is assumed to be constant and it must stop in 2.0 sec. a) What is final position of plane if i

Potential advantages of segmental tunnelling, Q. Potential advantages of se...

Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking? In segmental tunnelling, jacks are installed at the shield so that itisn't necessar

PROJECT PROPOSAL, HOW CAN I INVESTIGATE THE PROPERTIES UNBURNT COMPRESSED C...

HOW CAN I INVESTIGATE THE PROPERTIES UNBURNT COMPRESSED CLAY BRICKS AND STABILIZED UNBURNT COMPRESSED BRICKS.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd