Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Planning stage of the audit, Materiality is used only at the planning stage...

Materiality is used only at the planning stage of the audit. Ans: I disagree with the statement because: When planning the audit, the auditor considers what would make the fi

Structural analysis 1, derive equation of radial pressure and loop stresses...

derive equation of radial pressure and loop stresses of thick cylinder

How to calculate the coefficient of permeability, The discharge of water co...

The discharge of water collected from a constant head permeameter in a period of 15 minutes is 500 ml. The internal diameter of the permeameter is 5 cm and the measured difference

Airport lighting, Airport Lighting: Lighting of Approach to Runway ...

Airport Lighting: Lighting of Approach to Runway A good system of identification of the runway when landing is to provide six transverse cross-bars of lights placed a

Calculate uniform annual cost for maintenance and repair, A contractor purc...

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest

Load transfer mechanism, Question What is load transfer mechanism for p...

Question What is load transfer mechanism for paving blocks in pedestrian footway? Answer In Hong Kong, footway is as a rule designed with paving slabs or interlocking b

State the term - constant eccentricity, State the term - constant eccentric...

State the term - constant eccentricity A pre-stressed concrete beam has a width of 300 mm and an overall depth of 450 mm. The permissible stresses in tension and compression du

Example of magnetic dip, Example : Line AB was drawn with a magnetic ...

Example : Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd