For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Total station, describe in detail the various parts of a total station

describe in detail the various parts of a total station

Stochastic calculus, Consider a market with one stock and one money market ...

Consider a market with one stock and one money market account, with the same assumptions on parameters (such as r, µ and s 2 ) as in the derivation of the Black-Scholes formula giv

Chemistry, What is the difference between scale and sludge

What is the difference between scale and sludge

Effect of concrete placing temperature, Effect of concrete placing temperat...

Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv

Computer programming, compare 2 numbers and print either the message identi...

compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal

Specification of water bound macadam road, Q. Specification of Water bound ...

Q. Specification of Water bound macadam road? Formation - The embankment for road shall be made to the cross section shown on the drawing. The bank shall be raised in regular

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd