For the project network shown, the late start time (day) for activity "Q" is most nearly:
Solution: List the paths leading to "Q" and calculate the duration for each.
L M = 4 + 7 = 11-days
L N P = 4 + 3 + 3 = 10-days
Q's early start time is 10-days
Q's late start time is 11-days
what is meant by white topping cement
how to use mood diagram to get f and other Re
Question What is main dissimilarity among cement plaster , cement render and cement screed ? Under what state each of above can be used? Answer Purpose of plaster
what is importance of positioning in different types of engineering?
Pavement of evaluation
Q. Bleeding test for grout – an essential requirement? Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial st
Cleaning and greasing of Rocker & Roller bearings of open web through girders : In case of standard open web through girders, no separate jacking arrangement is required as the en
in colour working drawing what are the colour code?
how to use the revit program
Flash Point Test: The flash point is the temperature at which the bitumen gives off vapours which ignite in the presence of a flame. The flash point temperature gives the cri
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd