For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Indirect tensile strength in water-retaining structures, Q. Indirect tensil...

Q. Indirect tensile strength in water-retaining structures ? Crack width formation is dependent on the early tensile strength of concrete. Principle of critical steel ratio als

Trigo, A pole which leans 11o from the vertical toward the sun casts a shad...

A pole which leans 11o from the vertical toward the sun casts a shadow 12m long when the angle of elevation of the sun is 40o. Find the length of the pole

Compare the probabilities, Compare the probabilities: Use the central ...

Compare the probabilities: Use the central limit theorem to compute P (¦ X - μ ¦ ≥ k), k = 1, 2,3,4,5 where X and μ are as defined in Example. Compare the probabilities with t

Determine the limit states of collapse, Determine the Limit States of Colla...

Determine the Limit States of Collapse Those limit states which point out the failure or collapse of a structure based on certain critical conditions are known as limit states

Why do we need to control air pollution, Why do we need to control air poll...

Why do we need to control air pollution? a. It causes harmful effects on human health,  Materials and property,  Plants and Animals, Visibility, Global climate and others b.

Earth fill dams, Ask question #Minimum 100E. The regulations and specificat...

Ask question #Minimum 100E. The regulations and specifications that followed for compaction works for earth dam in Oman words accepted#

Simulink software, Using Matlab/ Simulink software to model the overall bui...

Using Matlab/ Simulink software to model the overall building fabric heat transmit characteristics, in order to estimate the maximum rate of heat loss (kW) from the building under

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd