Determine the late start time for activity, Civil Engineering

Assignment Help:

For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Design of steel beam column with hot rolled steel built-up s, how to comput...

how to compute the compound elements particularly outstanding element of compression flange if 2-ismb300 are placed side by side

What is critical steel ratio, Q. What is Critical steel ratio? Critica...

Q. What is Critical steel ratio? Critical steel ratio - only consider 250mm of concrete from outer face The purpose of critical steel ratio is to control cracking pattern

Lifting of girders, Q. Lifting of girders? Lifting of girders : For gre...

Q. Lifting of girders? Lifting of girders : For greasing the bearings girders are required to be lifted. But the gap between the bottom flange of plate girders and the bed bloc

Surveying, description of instruments used transfer upper floors *plumb-bob...

description of instruments used transfer upper floors *plumb-bob method *theodolite method *theodolite and target method *optical plumbing method

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Solid block -calculating for design mix, Good evening sir, solid block''s d...

Good evening sir, solid block''s design mix calculated generally please explain and derive .

Prestressed concrete poles, Prestressed concrete poles In the past deca...

Prestressed concrete poles In the past decades, prestressed  concrete poles have become popular and have replaced the traditional poles made of timber, steel or reinforced  con

Maintenance of earth roads, Maintenance of Earth Roads: The main task...

Maintenance of Earth Roads: The main task in maintaining the earth road is to ensure that cross-section is intact and is free from rutting, depressions and corrugations, and

Energy absorbed in heeling during vessel berthing, Q. Energy absorbed in he...

Q. Energy absorbed in heeling during vessel berthing? When a vessel   berths on a fender system at a pier, point of contact of berthing ship can be below or above the centre of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd