For the project network shown, the late start time (day) for activity "Q" is most nearly:

1829_Determine the Late Start Time for Activity.png

Solution:  List the paths leading to "Q" and calculate the duration for each.

 L M      = 4 + 7 = 11-days 

L N P     = 4 + 3 + 3 = 10-days  

Q's early start time is 10-days

Q's late start time is 11-days


Related Discussions:- Determine the late start time for activity

Geology class, I want to get answer of each questions that I Have in a sep...

I want to get answer of each questions that I Have in a separate paragraphs, and the information should be from sources so please fro each question that you answer write after it t

Cycle, what is motor cycle. please explain.

what is motor cycle. please explain.

What is the density index of the natural soil, A sand at a borrow pit is de...

A sand at a borrow pit is determined to have an  in-situ dry unit weight of 18.4 kN/m 3 . Laboratory tests indicate the maximum and  minimum unit weight values of 19.6 kN/m 3 and

Sub-surface drainage, Sub-surface Drainage: Sub-surface drainage is i...

Sub-surface Drainage: Sub-surface drainage is intended to take away the water seeping through the pervious layers of the soil, causing a high water table, or in cut slopes of

STRENTH OF MATERIAL, WHY WE ARE USING MAMENT OF INERTIA IN STRAIN ENERGY ST...

WHY WE ARE USING MAMENT OF INERTIA IN STRAIN ENERGY STRUCTURE

Inadequate pile founding level, Reasons of common occurrence of "inadequate...

Reasons of common occurrence of "inadequate pile founding level" in piles of piers The most severe load on piers usually is the horizontal load owing to berthing and mooring o

LOADS, what are the difference between UDL and UVL?

what are the difference between UDL and UVL?

Concrete cover to enhance fire resistance, Q. Concrete cover to enhance fir...

Q. Concrete cover to enhance fire resistance? In the event of exposing concrete structures to a fire, a temperature gradient is established across the cross section of concrete

Los angeles abrasion test, Los Angeles Abrasion Test: In which the agg...

Los Angeles Abrasion Test: In which the aggregates are placed in a rotating drum in which a certain number of cast iron cylindrical balls are also placed, and the drum rotated

Constraction, sir what is means by share force

sir what is means by share force

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd