Q. What is Rapid Sand Filter?

A Rapid Sand Filter is a water treatment plant that includes provision for pre treating the water by coagulation and sedimentation for settlement of suspended solids before filtration with sterilization in the final process.

Rapid Sand Filter consists of layers of course sand with an effective size of 0.35 to 0.50 mm is used. The depth of sand layer is 0.60 to 0.75m. This sand is supported on a gravel layer of depth 0.45m in 5 to 6 layers. The effective size of gravel is 2 to 50 mm. Gravel is under by an under drainage system consisting CI central manifold with strainers & lateral.

Plan area of these tank s is 10 to 80 m2 or 6 x 8 m or 8 x 10 m. Rate of filtration of these filter is 3000 to 6000 Lit. /hrs/ m2. The cleaning of Rapid Sand Filter is effected by reversal flow. First air is passed at the rate of 600 - 900 lpm/ m2 at the pressure of 0.35 kg/cm2 for 5 minutes in the reverse direction. After this water is passed which removes the dirt by bubbling action. Water required for back wash 300 to 900 Lit. / hrs/ m2. Cleaning must be done after every 1 to 3 days.


Related Discussions:- What is rapid sand filter

Structural analysis and design, Scenario You are working as a structural...

Scenario You are working as a structural technician and have been charged with a range of jobs   involving analysis and design of a number of structural members. Task 1 a)

Define the spalling - underwater inspection of bridge, Define the Spalling ...

Define the Spalling - underwater inspection of bridge? A spall is a roughly circular or oval depression in the concrete. Corroding reinforcement can cause spalls and reinforcin

#surveying & levelling, expressions for calculating corrections for earth c...

expressions for calculating corrections for earth curvature

Define in biref about the final prestress, Define in biref about the Final ...

Define in biref about the Final Prestress The stress which exists after all losses of prestress have occurred substantially is known as final prestress. This may be calculated

Show the side clearance of pipes in trenches, Side clearance of pipes in tr...

Side clearance of pipes in trenches From the design point of view, it's predominant to minimize the width of pipe trenches due to thebelow reasons: (i)  Higher cost of exca

Determine the stage of cracking moment of pre-stress, Determine the stage o...

Determine the stage of Cracking moment of pre-stress  At the stage of transfer of pre-stress in the pre-stressed beam element, only the pre-stressing force and the self weight

Sieve analysis - soil mechanics and foundations, Sieve Analysis - Soil Mech...

Sieve Analysis - Soil Mechanics and Foundations a. Sieve Analysis used to obtain the grain size distribution of coarse-grained soils (sands and gravels) larger than 0.075 mm (r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd