Q. Underwater problems in bridge construction?

The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding agent, have been used extensively for building bridges. Cast iron piles have been used as substructure in many bridges. These materials are prone to different types of failure and, therefore, require different inspection strategies. The major problem in steel bridges is corrosion. Concrete bridges are susceptible to spalling and scour. Bridges built in masonry have the problem of deterioration of brick / stone elements accompanied with loss of mortar. Aquatic environment has significant effects on bridges in addition to those mentioned above. Heavy current is especially destructive. Floods cause damage from rapidly moving water as well as from the impact of large moving debris. The bridge substructure can also get damaged due to accidental man inflicted causes and earthquakes.


Related Discussions:- Underwater problems in bridge construction

Torsional pendulum, define rigidity modulus and mention its units?

define rigidity modulus and mention its units?

What is stilling basins, Q. What is Stilling basins? Stilling basins ar...

Q. What is Stilling basins? Stilling basins are usually introduced to convert supercritical flow to subcritical flow before it reaches downstream. A typical stilling basin comp

Explain the term - untensioned reinforcement, Explain the term - Untensione...

Explain the term - Untensioned Reinforcement In prestressed concrete construction, use of untensioned reinforcement also has to be made alongwith tendons. This is essential as

Determine the term - lowering of stresses, Determine the term -  lowering ...

Determine the term -  lowering of stresses Due to creep of concrete, these compressive strains keep on increasing with time. it means that the length of the member keeps on red

Steel truss, size of steel truss for span of 5m

size of steel truss for span of 5m

Boundary ratio of weight of hammer to weight of pile, Question If n a n...

Question If n a number of codes, they boundary ratio of weight of hammer to weight of pile for pile driving. What will be the key reason for this? Answer As a hamm

Semi elliptical arch, how can i build a semi-elliptical arch out of bricks?...

how can i build a semi-elliptical arch out of bricks?

Curing, curing of brick masonry

curing of brick masonry

Calculate the total board feet, A project engineer has ordered 100 hardwood...

A project engineer has ordered 100 hardwood boards, 1-1/4-in thick by 8-in wide and 8-ft long.  The total board feet ordered is most nearly:  Solution: 1.25" x 8" x 8' x 100

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd