Question
What is key disparity between working stress approach and limit state approach?
Answer
Working stress approach, service loads are used in whole plan and strength of material is not utilized in full extent. In this means of plan, stresses acting on structural members are intended based on flexible way and they are designed not to beat certain acceptable values. In fact, whole structure during lifespan may only knowledge loading stresses far below ultimate state and that is reason why this means is known as working stress approach. In such scenario, most economical plan can hardly be obtained by using working stress advance that is now commonly used in design of temporary works.
For maximum state approach, for each material and load, a biased safety factor is assigned independently depending on material properties and load lands. So, each element of load and material properties is exactly assessed resulting in an extra refined and accurate analysis of structure. In this relation, material strength be capable of be utilized to its greatest value during its lifespan and loads be capable of be assessed with practical probability of occurrence. Boundary state approach is frequently used for majority of reinforced concrete design as it ensures utilization of material strength with least construction price input.
Finding distances in tacheometric survey
Magnitude of torque - bending moment: A prismatic bar of hollow circular cross-section along with outer and inner diameters 100 mm and 80 mm correspondingly, carries a bending
A retaining wall with a vertical back 5 m high supports cohesion less backfill of unit weight of 19 kN/m 3 . The upper surface of the backfill rises at an angle of 10° with the hor
design a tension member subjected to a pull of 300KN using a channel section. the length of a joint available is only 400mm.check the condition of using lug angle for end connecti
Minimum volume of sump volume for pumps Maximum pumping rate = Q P Volume of sump = V Inflow Rate = Q i Cycle Time T c = t 1 + t 2 t 1 = V / Q P - Q i t 2
i want a complete flow chart of dry process of cement
Fluid Mechanics or Properties - Specific Gravity Dimensionless ratio of a fluid's density to some standard reference density. For liquids and solids, the reference density is p
Q. Function of prime coat in bituminous pavement? The main function of prime coat in bituminous pavement is to protect the subgrade from weathering andmoisture. Because the pre
what is distomat
Q. Show the Purpose of granular bedding for concrete pipes? When designing the bedding for concrete drainage pipes, granular materials are generally specified in place of soils
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd