Q. What is the minimum prescribed track structure for LWR / CWR on Broad Gauge?

Ans.-

1. General - The minimum length of LWR depends upon -

i. Range of temporary variation.

ii. The section of rail.

iii. Resistance offered by ballast to the longitudinal movement of rail assembly.

2. Formation - Weak formation to be identified and stabilized suitable means cross slope should be 1 in 40. In heavy rainfall areas steeper grades can be provided as prescribed by CE.

3. Ballast - Minimum clean ballast cushion 250 mm for speeds up to 130 KmPH for speeds above 130 KmPH minimum depth of ballast cushion shall be 300 mm or 200 mm clean ballast over 150 mm sub ballast.


Related Discussions:- Track structure on broad gauge

Comparing speed, Question Comparing speed of "Formwork exceeding 300mm wide...

Question Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at

R.c.c square overhead tank, problems in estimating especially in reinforcem...

problems in estimating especially in reinforcement works

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Major bridge and important bridge, Major bridge - Major bridge is one of wh...

Major bridge - Major bridge is one of which has a total linear waterway of 18 m or more for multiple span and total linear water way of 12 m or more for single span. Important b

Road survay, how many programmes in road survey by level matichine and ts?

how many programmes in road survey by level matichine and ts?

Explain the purpose of embedding puddle flange, Purpose of embedding puddle...

Purpose of embedding puddle flange inside the walls of closed valve chambers When valves are closed to stop water flow in a pipeline, a thrust is produced along the direction o

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Surveying, sample problems with solutions for probable value

sample problems with solutions for probable value

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd