What is switch and expansion joint, Civil Engineering

Assignment Help:

Q. What is Switch and Expansion Joint?

Switch Expansion, Joint (SEJ) is an expansion joint installed at each end of LWR/CWR to permit expansion/contraction of the adjoining breathing lengths due to temperature variations.

The exact location of SEJ shall be fixed taking into account the location of various obligatory paints such as level crossings, girder bridges, points and crossings gradients, curves and insulated joints. SEJ with straight tongue and stock shall not be located on curves sharper than 0.5 degree (3500 m radius) as far as possible. SEJ shall not be located on transition of curves.


Related Discussions:- What is switch and expansion joint

Railway drawings, section of railway tracks in india ,all dimensions in met...

section of railway tracks in india ,all dimensions in meters

Explain the confined aquifer and piezometric surface, Explain the Confined ...

Explain the Confined Aquifer and Piezometric Surface Confined Aquifer Groundwater is confined by impervious geologic stratums on all sides. The water may be under pressure.

Explain plate jig, Explain Plate jig 1) The major parts of this jig is ...

Explain Plate jig 1) The major parts of this jig is plate from which it takes its name other necessary parts and drill bush and locating pins. 2) Plate jigs are general for

Statics, Applications of statics

Applications of statics

Determine the cost of compensation, The soil in a borrow pit has a void rat...

The soil in a borrow pit has a void ratio of 0.90. A fill-in-place volume of 20,000 m 3 is to be constructed with an in-place dry density of 18.84 kN/m 3 . If the owner of borr

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Couple, Properties of a couple

Properties of a couple

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

Addition of water to bored piles, Addition of water to bored piles In ...

Addition of water to bored piles In water bearing ground, some water head (about 1 m) above the existing ground water table is sustained to stabilize the bore at the time of e

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd