Time and cost analysis, Mechanical Engineering

Assignment Help:

Time and Cost Analysis

This discusses about certain basic activities that must be carried out in a factory to convert raw materials into finished products. These activities broadly are Processing and assembly operations, Material handling, Inspection and testing and Coordination and control.

The machining times for various machining processes and the importance of it is explained.

The machining time in turning (t) is as

t = L + L0 /2 f N

The machining time in milling T in minutes can be calculated as

T = (L × n)/ f Z N minutes

Time for drilling the hole = L/ f N     minutes

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work.

In boring operation the machining time is calculated the same manner as in turning. It is given by the following relation :

Machining Time = Depth of hole to be bored in mm minutes/ N × feed/rev

where, N = No. of revolutions per min. of machine spindle or work. Machining time for shaping can be calculated as below.

No. of cycles required (n) = Shaping width / Feed per cycle f

= B/f

Machining time = No. of cycles × time required for each cycle

1428_Time and Cost Analysis.png

The machining time (T) in cylindrical grinding can be calculated from the following relationship.

T = (L . P . K )/ ( f . N . t) min .

The total production cost of machined components is made up of the following components : material cost, labour cost, overhead cost, tool cost and cost of percent of the total cost. But the influence of tools on the other costs is considerable. It is often possible that the tool cost is increased but the total production cost is reduced considerably because of the influence of the tool on other aspects of cost.

The costs that go into machining a part can be broken into three categories as Material removal cost, Tool cost and Non-productive cost

Total machining cost = Material removal cost + Tool cost + Non-productive cost. The tool cost is made up of

(a) Tool change cost (TCC) or cost for indexing the insert

(b) Tool regrinding cost (TRC)         

(c)  Tool original cost (TOC)

(d) Tool inventory cost (TIC)

Total tool cost = TCC + TRC + TOC + TIC


Related Discussions:- Time and cost analysis

Welding, pre heating of casted material for welding

pre heating of casted material for welding

Product life-cycle management, Product life-cycle management: There ha...

Product life-cycle management: There have also been changes in the use of some pre-existing data formats. Open associations have been formed to encourage some formats to becom

Determine the interface temperature, A steel pipe with 50 mm OD is covered ...

A steel pipe with 50 mm OD is covered with a 6.4 mm asbestos insulation followed by a 25 mm layer of fiber-glass insulation [K = 0.0485 Wmk]. The pipe temperature is 393 K and the

Arc spot welding, Arc Spot Welding In this process, coalescence at the...

Arc Spot Welding In this process, coalescence at the overlapping surfaces is produced in one spot by heating with an electric arc between an electrode and the work. The weld i

Shut-off valves on major zone, Q. Shut-off valves on major zone? Are shu...

Q. Shut-off valves on major zone? Are shut-off valves on major zone branches and on the bottom and top of riser? Are balancing valves on return branches? Are control valves on

Rankine cycle with respect to p-v, Rankine cycle with respect to P-V, T dia...

Rankine cycle with respect to P-V, T diagrams: The steam having high pressure is expanded to a low pressure within a reciprocating engine or a turbine. If expansion is idea

(APPLIED THERMODYNAMICS, AA steam power plant operates on a reheat Rankine ...

AA steam power plant operates on a reheat Rankine cycle. Steam enters the high-pressure turbine at a pressure of 12.5 MPa and temperature of 550 oC at a rate of 15 kg/s. It leaves

Determine the smallest increment of strain hat, A 16-bit A/D board is arran...

A 16-bit A/D board is arranged to accept voltage signals ranging from -5V to +5V.  The A/D board is used to monitor the output from the Wheatstone bridge shown below.  The strain g

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd