The software life cycle model that incorporates risk factor, Software Engineering

Assignment Help:

Explain the software life cycle model that incorporates risk factor.

 The problem with traditional software process models is that they do not deal adequately with the uncertainty, which is inherent to software projects. Significant software projects failed because project risks were neglected and nobody was ready when something unforeseen happened. Barry Boehm recognized this and tried to incorporate the " project risk" factor into a life cycle model. The results is the spiral model, which was presented in 1986  BOEH86 Every loop of the spiral from X-axis clockwise by 3600 represents one phase. Single phase is split roughly into four sectors of major activities.

  • Planning : Determination of objectives, alternatives and constraints
  • Risk Analysis : Analyze alternatives and attempts to recognize and resolve the risks involved
  • Development : Product development and testing product
  • Assessment : Customer evaluation

 


Related Discussions:- The software life cycle model that incorporates risk factor

What is equivalence partitioning, What is equivalence partitioning? Equ...

What is equivalence partitioning? Equivalence partitioning is a black box method that separates the input domain into classes of data. From this data test cases can be derived.

Software document, explain software document.create the necessary documents...

explain software document.create the necessary documents for employee management system.

Explain practical process quality, Practical process quality Explain pr...

Practical process quality Explain process standards such as how reviews should be conducted, configuration management, etc. Monitor the development process to make sure that

What is open box testing, Open box testing is similar as white box testing....

Open box testing is similar as white box testing. It's a testing approach that consider the application's program structure, and derives test cases from the application's program l

Advantages of re-engineering, Advantages of Re-Engineering:- 1)  Reduce...

Advantages of Re-Engineering:- 1)  Reduced risk - there is a huge risk in new software development. There might be development problems, staffing problems and specification pro

What are the controlling events between objects, What are the Controlling E...

What are the Controlling Events Between Objects Event is the specification of a important occurrence which has a location in time and space. Examples of events are flight l

Describe basic steps in software cost estimation, Question: (a) Describ...

Question: (a) Describe fully the first five basic steps in software cost estimation. (b) What are the main differences between COCOMO1 and COCOMO2 cost estimation models?

Different phases of spiral model, Four Different Phases of spiral model are...

Four Different Phases of spiral model are: 1) Planning  2) Risk analysis 3) Development 4) Assessment

What is equivalence class testing, Q. What is Equivalence class testing? ...

Q. What is Equivalence class testing? Equivalence class testing is based on the partitioning the input domain of a program into a number of equivalence classes so that the test

Modular software development, After studying the module you should understa...

After studying the module you should understand the principles and techniques associated with modular software development. After studying the module you should understand the c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd