Steam and power generation equipment, Mechanical Engineering

Assignment Help:

Q. Steam and Power Generation Equipment?

Locating steam and power generation equipment outside of the process areas ensures that critical facilities feeding major portions of the plant are protected from possible fires or explosions in the process areas. Non-critical steam generators (supplying less than 25% of total demand, or only supply a single plant) may be located within a process area with spacing as for fired heaters.

Central services, such as cooling towers, boilers, power stations and electrical substations shall be located centrally but away from hazardous areas so they will neither be affected by a fire or explosion within the plant nor provide a source of ignition for any potential flammable liquid or gas release. Maintain adequate separation between different utility services because utility losses could then lead to unsafe conditions in other plant units, possibly creating fires or explosions. Increase the reliability of utilities by keeping adequate spacing between boilers or generators. Refer to the Appendices for suggested adequate separation between different utilities.

Properly pressurize substations in accordance with NFPA 496 or install separate electrical substations and motor control centers. Locate substations away from hazardous areas to increase the reliability of the power supplies should an accident occur. Bury electrical distribution cables to limit their exposure to explosions, fires, storms and vehicles and to ease fire fighting accessibility.


Related Discussions:- Steam and power generation equipment

Potential deadlock, Suppose an interesting situation represented in followi...

Suppose an interesting situation represented in following figure (b). The Petri net somewhat shows a paradoxical situation. Intuitively we contain in our minds that by raising the

Burner management - discrete controls for steam generators, Q. Burner Manag...

Q. Burner Management - Discrete Controls for steam generators? The burner management system shall control the generator operation during pre-purge, light off, normal operation,

Motorcycle pulls to one side motorcycle problem, If Motorcycle Pulls to One...

If Motorcycle Pulls to One Side Causes of Problem Remedy Misaligned shock Absorber Front and rear wheels are not alig

Derive the finite element formulation-galerkin method, Derive the finite el...

Derive the finite element formulation  for a tapered bar element using Galerkin's method.                                                 1- Start with. 2- Use and as shap

Duty cycle rating, DUTY CYCLE RATING Since, arc welding power sources ...

DUTY CYCLE RATING Since, arc welding power sources are delivering high currents for welding; the components of such a system are bound to get heated. In order to have increase

Short circuiting transfer, Short Circuiting Transfer The short circuiti...

Short Circuiting Transfer The short circuiting transfer  occurs when the welding current and the arc voltage is low. Metal is transferred from the electrode to the work only wh

Analysis of trusses, State the assumptions in pin joined trusses?

State the assumptions in pin joined trusses?

Welding procedure specification (wps), WELDING PROCEDURE SPECIFICATION (WPS...

WELDING PROCEDURE SPECIFICATION (WPS)   The purpose of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) is to determine that weldment proposed

Calculate strength coefficient - true stress and true strain, Calculate str...

Calculate strength coefficient: A copper specimen of 64 mm gauge length and 12.80 mm dia. was tested in tension. Following two diameters were recorded in the plastic range of

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd