standerd costing, Managerial Accounting

Assignment Help:
Ask queThe standard cost of chemical mixture ~ PQ’ is as follows:
40% of material P @ Rs. 400 per kg.
60% of material Q @ Rs. 600 per kg.
A standard loss of 10% is normally anticipated in production. The following
particulars are available for the month of March, 2005.
180 kgs of material P have been used @ Rs. 680 per kg.
220 kgs of material Q have been used @ Rs. 360 per kg.
The actual of production of ‘PQ’ was 369 kgs.
Calculate the following variance:
a) Material Price Variance
b) Material Usage Variance
c) Material Mix Variance
d) Material Yield Variance
stion #Minimum 100 words accepted#

Related Discussions:- standerd costing

Predetermined Overhead Rate, Logan Products computes its predetermined over...

Logan Products computes its predetermined overhead rate annually on the basis of direct labor hours. At the beginning of the year, it estimated that 39,000 direct labor-hours would

Types of non-controlled variables, Types of Non-Controlled Variables a) ...

Types of Non-Controlled Variables a) Parameters: These are input variables that for a given simulation have a constant value. They are factors which help specify the relat

Transient analysis-absorbing state, Transient Analysis A state is said...

Transient Analysis A state is said to be transient if it is impossible to move to that state from any other state except itself. This state is temporary and eventually a stead

Accounting cycle, Accounting Cycle is the name given to the combined proces...

Accounting Cycle is the name given to the combined process of recording and processing the accounting proceedings of a company. The series of steps start when a transaction takes p

Analysis of credit file, Analysis of Credit File: Credit file is a compila...

Analysis of Credit File: Credit file is a compilation of each the relevant credit information of the customer. All the credit information collected throughout the credit informati

What does your analysis tell you about each firm, When the stock market is ...

When the stock market is going up over a long period of time, investors can become complacent about the risks of being a stockholder. After the significant decline of the stock mar

Quadratic loss function, Consider the following quality data for three diff...

Consider the following quality data for three different manufacturers of automobile weather-strips: Weather-strip Bulb Dimension Specification y=20 +or- 4mm

State the steps for standard costing system, State the steps for Standard c...

State the steps for Standard costing system standard costing system involves the following steps 1) Setting-up of standards for each element of cost: standards should be s

What is activity based management, ABM(Activity based management): ABM ...

ABM(Activity based management): ABM system is primary source of information for AM as a part of ABM identify value added and non-value added activity and management are also to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd