Soil particles for geotechnical design, Civil Engineering

Assignment Help:

Question

Will it worthwhile to take out tests on particle density of soil particles for geotechnical design?

Answer

Particle density of soils is definite by ratio of soil particle mass and soil element volume. Depending on soil category, range of variation of soil particle thickness varies not drastically as in by percent. So, it might not be useful to order laboratory tests and incur additional expenditure just to decide particles density by recognizing that variation of particles density is not significant.

 

 


Related Discussions:- Soil particles for geotechnical design

Determine the required area of steel, A rectangular concrete beam is subjec...

A rectangular concrete beam is subjected to a factored moment (Mu) of 345 kip*ft.  The beam has the following properties: f'c = 5500 psi fy = 60,000 psi h = 39 in

Analyse and evaluate lightning strikes, Carry out research to Analyse and E...

Carry out research to Analyse and Evaluate: a.   The potential problems that lightning strikes to an aircraft in flight could create. b.   How design features and maintenance

Necessity of reinforcement in precast concrete manhole units, Necessity of ...

Necessity of reinforcement in precast concrete manhole units Precast concrete manholes are generally constructed by placing the bases of manholes firstly. Walls of precast man

N-type semiconductor is an example of what semiconductor, N-type semiconduc...

N-type semiconductor is an example of what semiconductor? Answer : N-type semiconductor is an example of extrinsic semiconductor.

Designing sewer pipes, Question While designing sewer pipes , why vitrifie...

Question While designing sewer pipes , why vitrified clay pipes commonly is used for pipe size less than 600mm still as precast concrete pipes with PVC lining is used for pipe

Analysis of the two stage construction, A County is planning to build a new...

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd