software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

What are the techniques used for a post completion review, What are the tec...

What are the techniques used for a post completion review? Techniques used for a PC (post completion) review: a. End user satisfaction surveys regarding to the quality of th

Use of both innovative approach in development process, Q. Use of both inno...

Q. Use of both innovative approach in development process? There are many major aspects that will sway the future trends in the development of new products. In the new millenn

Textile industry, in what ways consumer changing tastes affecting textile i...

in what ways consumer changing tastes affecting textile industry?

Answer, summarise the argument for such a policy of partnering with a major...

summarise the argument for such a policy of partnering with a major supplier such as BAA and MACE HAVE DON HERE

Explain force field analysis techniques, Question 1: Choosing a social ...

Question 1: Choosing a social project of your choice, use the SWOT analysis and Force Field Analysis Techniques to scope the project explaining what are feasible and what are n

Effects and four types of risks in engineering projects, Question Using...

Question Using a project drawn from your own experience, discuss the following- (a) What are the two primary stages of risk management of a project? (b) What are the four

Concept of values to an individual, An organisation's capacity to maintain ...

An organisation's capacity to maintain a sustainable competitive advantage depends largely on its core competencies as well as the ability to refine and enhance them in the context

Mil standards, MIL standards were introduced in 1974. In 1975 BSI 517...

MIL standards were introduced in 1974. In 1975 BSI 5179 in these parts drawn from the contents of defiance standards 05-21 series. This standard was not written in man

System documentation project- automatic purchase requisition, Introduction ...

Introduction Ajax Corporation is a manufacturing firm with a sophisticated purchasing system.  The system is capable of automatically generating purchase requisitions for inven

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd