software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Factors affecting process design - degree of automation, Factors affecting ...

Factors affecting Process Design - Degree of Automation The degree of automation  to be  adopted and  integrated into the  production  system is a key issue in process design,

Objectives of a work breakdown structure, Question: (a) Explain the typ...

Question: (a) Explain the typical contents of the project selection rationale document, drafted at the end of the conception phase. (b) (i) Describe the purpose and objecti

What do you mean by fixed costs, What do you mean by fixed costs? Fix...

What do you mean by fixed costs? Fixed Cost: Cost may be described as the amount of expenditure incurred upon, or attributable to a specified thing. Fixed costs are such

External factors of syringe management , External Factors Opportunit...

External Factors Opportunity This plan will build a good image for Maribyrnong Council, even Melbourne. The opportunity for Maribyrnong Council, there maybe will attrac

The type of culture to which s company now needs to change, S Company has f...

S Company has for many years been a long standing household name, designing and manufacturing electrical appliances for use in the kitchen. It has developed a strong culture over t

Upward communication from subordinate to superior, How must be the upward c...

How must be the upward communication from subordinate to superior ? Upward Communication moves through subordinate to the superior within the form of feedback. This takes th

What are the major characteristics of a project, Question : (a) Organi...

Question : (a) Organizations and individuals have studied a number of projects that have both succeeded and failed and some common factors emerge. Can you give some reasons fo

What types of problems solved by break even analysis helps, What types of p...

What types of problems solved by Break even Analysis Helps? Break even Analysis helps to solving the given types of problems as given below: 1. What volume of sales will be

What is buffering in risk management, What is Buffering in risk management?...

What is Buffering in risk management? Buffering: Buffering or slack is the allowance of additional cost, resources or time for example ‘just in case’ specific events or r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd