software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Evaluation of current organisational culture, It is gradually recognised th...

It is gradually recognised that culture, although difficult to measure precisely, it is a real and very powerful force in organisations. Organisational behaviour is related to cult

Benefits and caveats, (a) What are the benefits and caveats of adopting a ...

(a) What are the benefits and caveats of adopting a standard methodology (such as PRINCE2) for the management of an organization's projects? (b) How might the size of an organi

Explain the different service delivery gaps, Question: (a) The findings...

Question: (a) The findings of Parasuraman et al have demonstrated that there are gaps in the service delivery leading to several misunderstandings between customer expectations

External factors of syringe management , External Factors Opportunit...

External Factors Opportunity This plan will build a good image for Maribyrnong Council, even Melbourne. The opportunity for Maribyrnong Council, there maybe will attrac

Classical and neo-classical theory of of organisation, What are the differe...

What are the differences between classical theory and neo-classical theory of organisation? Difference between classical theory and neo-classical theory of organisation: The cl

How do i best control cost, Q. How do I best control cost? Several peop...

Q. How do I best control cost? Several people think that they are controlling cost when they approve invoices or sign cheques. In fact the cost is already long since committed

Turn key contracts, Ask question #Miniwhat circumstances that favor turn ke...

Ask question #Miniwhat circumstances that favor turn key contracts mum 100 words accepted#

Effective project control, Project control processes cannot be overemphasis...

Project control processes cannot be overemphasised in their significance to the success of a project. The project manager must continually take a pro-active approach in controlling

Work breakdown structure, Work breakdown structure: The work breakdown ...

Work breakdown structure: The work breakdown structure, as its name suggests, represents an organised and logical break down of the project into its component parts. Thus break

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd