software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Explain to g the role of the project manager, P Company manufactures and se...

P Company manufactures and sells a range of children's clothing through its retail shops and is currently designing a website in order to allow customers to purchase products onlin

Explain about the term cost-benefit analyses, Explain about the term cost/b...

Explain about the term cost/benefit analyses. Cost/benefit analyse: Cost/benefit analysis is the procedure of knowing, and as far as probable quantifying, the costs of res

Tools and techniques of layout planning - line balancing, Tools and Techniq...

Tools and Techniques of layout planning - Line Balancing Line balancing is the phases of assembly line study that nearly equally divides the work to be done among the workers

Effects and four types of risks in engineering projects, Question Using...

Question Using a project drawn from your own experience, discuss the following- (a) What are the two primary stages of risk management of a project? (b) What are the four

What are the advantage of bottom-up decentralised approaches, What are the ...

What are the advantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager or

Basic tools used by a project manager, When someone says project managemen...

When someone says project management tool, the first thing that comes to mind is Microsoft Project. Microsoft Project is just one of the many tools available to and required by p

Risk management enhancement , Risk management enhancement  There is sco...

Risk management enhancement  There is scope for risk management scenario and the following are some of the methods suggested:   Bringing increased awareness of risks:  Imp

What is organisation structure in frame work of authority, What is organisa...

What is organisation structure in frame work of authority and responsibility? Organisation Structure: This structure is the systematic arrangement of the people working f

Describe standards of data quality, Question 1: Describe any two standa...

Question 1: Describe any two standards of data quality Any two of the following Governance and Leadership Policies and Procedures Systems and Processes People

What do you mean by variable costs, What do you mean by variable costs? ...

What do you mean by variable costs? Variable costs conversely, tend to vary directly along with the volume of output. Illustrations of variable cost are as given below: direct

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd