software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Input analyzer, After collecting random data located on a text file, we tes...

After collecting random data located on a text file, we tested our model to see the appropriateness of the data collected. We tried more than one method and ended up using the fit-

Project cost, why is project cost considered the most important factor in p...

why is project cost considered the most important factor in project management?

What do you mean by post completion report, What do you mean by post comple...

What do you mean by post completion report? The post completion (PC) report: This report would be created at the closing or finish stage of a project. Post completion rep

Calculate how much float/slack time, ST is the operations director of F Bak...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

What are the advantage of bottom-up decentralised approaches, What are the ...

What are the advantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager or

Short note acceptance theory-line organization, 1. Differentiate between 'A...

1. Differentiate between 'Administration' and 'Management'. 2. What were the common drawbacks in classical and Neo classical theories of management? 3. Write a short note on "Line

What is the conclusion about liberalization, What is the conclusion about l...

What is the conclusion about liberalization? As a conclusion, we can say only that liberalization is superior and desirable but which does not strengthen the case for privatiza

What is cost benefit analysis, What is Cost Benefit Analysis? Cost Be...

What is Cost Benefit Analysis? Cost Benefit Analysis: This analysis is a mathematical technique for decision-making. This is a quantitative technique used to calculate th

Elements of craft, Elements of CRAFT It reads the load summary (the nu...

Elements of CRAFT It reads the load summary (the number of loads carried between pairs of department), the costs for per unit load per unit distance for the handling of materi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd