Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

What are the principal stages of a project life cycle, Question 1: (a) ...

Question 1: (a) What are the principal stages of a project life cycle? (b) Describe fully the steps involved in the project planning process. Question 2: "Effective

Analysis of line balancing problems, Analysis of Line Balancing Problems ...

Analysis of Line Balancing Problems The procedure involves the followings steps: Determine the number of work stations and time available at each work stations.

Confidentiality, confidential document in civil project

confidential document in civil project

Precedence Diagrams, I know how to construct a precedence diagram but i am ...

I know how to construct a precedence diagram but i am asked the question :use the largest candidate rule to assign work elements to stations using a service time of 1.5 min how do

Costs of quality, Costs of Quality Quality management is not only c...

Costs of Quality Quality management is not only concerned with maintaining the quality characteristics of a product but also with doing the same at least cost. The

Developing a safe system of work, Question: (a) With reference to the ...

Question: (a) With reference to the Confined Space Regulations 1997. (i) Give the meaning of ‘confined space', providing TWO workplace examples (ii) What are the speci

What is project scheduling, Question 1 Briefly explain various activities ...

Question 1 Briefly explain various activities involved in project management Question 2 What is COCOMO? Write necessary steps for cost estimation Question 3 What is proj

Define the term risk in risk management, Define the term risk in risk manag...

Define the term risk in risk management. Risk: It is the probability or chance of something which may or may not arise; this is something that can be quantified by using s

Explain about the economic order quantity and total cost, Explain about the...

Explain about the Economic Order Quantity and Total Cost with diagram. Economic Order Quantity and Total Cost: The total of Inventory procurement cost and also inventory carryi

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd