software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Give an example of critical path by activity and duration, Give an example ...

Give an example of demonstrating a network or critical path by given activity and duration. Activity                      Duration (Wks)                   Preceded by

Introduction to syringe management plan, Introduction The project 'Syri...

Introduction The project 'Syringe Management Plan' is created to protect the community against misplace of syringe that causes accidental needle injury. This project is introdu

Brown &b hyer, Chapter 6 presents several tools that can be useful when ass...

Chapter 6 presents several tools that can be useful when assessing for project uncertainties. Compare and contrast risk mapping, FMEA, and the gut-feeling method. Which method do y

Histograms, H i stograms Histograms show a visual summary of the data...

H i stograms Histograms show a visual summary of the data, which is simple to understand. Raw data is difficult to understand and a pictorial representation helps to understa

Levels of strategy, Levels of strategy There are three levels of strate...

Levels of strategy There are three levels of strategy: Corporate strategy is the overall (grand) strategy for the organization as a whole. Business strategy refers to

Stages involved in the formal/rational approach to strategy, RF and JT are ...

RF and JT are both former international rugby players who, when they retired, formed their own business, WFH Trading Company.  The company that they established initially manufactu

Risk type, Risk type  To identify specific problems in your project, yo...

Risk type  To identify specific problems in your project, you first need to categorise the risks.  The project constraints are  well-organised in the PERIL database, which are

Confidentiality, Certain aspects of your project may be sensitive. Henley i...

Certain aspects of your project may be sensitive. Henley is aware that confidentiality may be a concern. When you submit your report it will only be made available to staff that ne

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd