software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

PERT Network Analysis, Solve the following CPM/PERT Network Analysis proble...

Solve the following CPM/PERT Network Analysis problem: Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slac

Explain the time-cost optimization algorithm, Question 1: What do you m...

Question 1: What do you mean by crash duration? Explain the Time-Cost Optimization algorithm crash duration/crash time - explanation including figures  Steps of Time-C

Discuss the fundamental differences between qa and qc, Discuss the fundamen...

Discuss the fundamental differences between QA and QC and give examples of usage of each methodology - The notions of QC (Quality control) and QA (Quality Assurance) are deeme

Iso 9000 certification, The international organization for standardization...

The international organization for standardization (ISO) is the specialized international agency for standardization and at present comprises the national standards bodies

What if i need more money for my project, Q. What if I need more money? ...

Q. What if I need more money? The similar applies here as in Question 17. Though the options that are open will depend on how far the project has already advanced. In general t

Disadvantages of product layout - demerits of breakdown, Disadvantages of P...

Disadvantages of Product Layout - Demerits of Breakdown The production line is vulnerable to interruption and shutdowns. A breakdown of a machine will render the entire line i

Misconceptions and pitfalls, The followings is a list of some of the comm...

The followings is a list of some of the common misconceptions that should be understood by those claiming to have used quality by design: 1. Quality by design is not simult

Degree of vertical integration, Degree of Vertical Integration Vertical ...

Degree of Vertical Integration Vertical integration is the amount of production and distribution chain, from suppliers of raw materials and components to the delivery of finishe

Discuss the importance of proper design for a hospitality, Question 1: ...

Question 1: Discuss the importance of proper design for a hospitality unit of your choice. Support your answer with relevant examples from the appropriate industry. Q

Disadvantages of product layout - heavy capital expenditure, Disadvantages ...

Disadvantages of Product Layout - Heavy capital Expenditure This layout requires heavy capital investment in machines and equipment and for providing specialized facilities to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd