software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Operating characteristic curve, O perating characteristic curve The op...

O perating characteristic curve The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage de

Project, Choose a claim at one of the projects from your organization or an...

Choose a claim at one of the projects from your organization or another one and discuss the following topics (giving reasons for your answers). Submit your answers using PowerPoint

Help on project from henley, The Integrated Management Project is a demandi...

The Integrated Management Project is a demanding piece of work requiring initiative, energy and application. It is our desire to support you and help you in this process as much as

Advantages of iso standards, ISO standards give tremendous advantages to ...

ISO standards give tremendous advantages to those holding their certification. Some of these advantages are briefly discussed below for different categories of groups ins

Degree of vertical integration, Degree of Vertical Integration Vertical ...

Degree of Vertical Integration Vertical integration is the amount of production and distribution chain, from suppliers of raw materials and components to the delivery of finishe

What do you meant by quality circles, Question 1: a. State the purposes...

Question 1: a. State the purposes of Malcolm Baldrige Quality Award b. Compare Balridge award criteria with TQM. A Purpose of MBNQA Question 1: What do you meant by qu

Stages of quality cost reduction, Stages of Cost Reduction The quality ...

Stages of Cost Reduction The quality costs are the costs which are associated with preventing, finding, and correcting the defective work. These costs are vast which runs 20% -

Usage of risk breakdown structure , Usage of RBS  Once an organisation ...

Usage of RBS  Once an organisation defines a Risk Breakdown Structure (RBS), then it can be used in a number of ways. These RBS is relevant across the project and helps in the

Wood, what is the maniipulated variable in a wood experiment

what is the maniipulated variable in a wood experiment

Briefly elaborate on the importance of a project charter, QUESTION (a) ...

QUESTION (a) Accurate estimation is crucial for effective planning and control and is associated with time, information, experience of estimator, techniques used and funding. D

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd