software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Application development for the multinational, Question: (a) What coul...

Question: (a) What could be the motivations for a large multinational to offshore its application development? (b) What could be the risks of offshoring application develo

Pmp exam, What is the best way to learn ITTOS?

What is the best way to learn ITTOS?

Relationship-reporting arrangements of manager with sponsor, What type of r...

What type of relationship and reporting arrangements must the project manager have with the sponsor? The sponsor of a project shows the management of the organisation which com

Iso 9000 certification, The international organization for standardization...

The international organization for standardization (ISO) is the specialized international agency for standardization and at present comprises the national standards bodies

Goal-strategy process, Goal A goal is a statement of where the organiza...

Goal A goal is a statement of where the organization wants to be at a specified time in the future. The purpose of goals is to provide direction to the organization. The steps

Illustrate the division of work in economics, Illustrate the division of wo...

Illustrate the division of work in Economics? Division of Work (or Labour): It s a famous principle of Economics, invented through the traditional economist as defined by

How to measures re-work for the product, Re-work effort (hours, as a percen...

Re-work effort (hours, as a percentage of the creative coding hours) Re-worked LOC (source lines of code, as a fraction of the total delivered LOC) Re-worked software compone

Structure, Differences between wbs and product breakdown structure, Project...

Differences between wbs and product breakdown structure, Project Management

Project risk manager , Project risk manager  As the project manager man...

Project risk manager  As the project manager manages the project, the project risk manager manages the project risks in the similar way. The responsibilities of project risk ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd