Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Scatter diagrams, S catter diagrams The possible relationships between...

S catter diagrams The possible relationships between two variables are identified using scatter diagrams. In order to understand data as a whole, it is very important to under

Total quality management, Total Quality Management is a philosophy gradual...

Total Quality Management is a philosophy gradually evolved from the management theories such as Management by objective quality circles strategic planning etc. To understand t

Define how you would estimate the quality control, Define how you would est...

Define how you would estimate the quality control and familiarisation activity. Quality control can be added like a percentage on top of all 'doing' activity like creating prog

Explain about the human relations skill, Explain about the Human Relations ...

Explain about the Human Relations skill. Human Relations skill refers to the capability to work effectively along with others and build cooperative work groups to attain organi

What is working of definition phase in project management, What is the work...

What is the working of definition phase in the project management? Definition phase: After the project plan that developed into the initiation phase, has been approved, a

Explain the scoring method for project selection, Question 1: Explain t...

Question 1: Explain the Scoring Method for project selection a) Un-weighted 0-1 factor method and Weighted factor scoring method b) Show the algorithm for solving the sh

Feasibility Study, Want to create a feasibility study for class assignment ...

Want to create a feasibility study for class assignment using consulting firm as my entrepreneur business located in Charlotte, North Carolina USA question..

Explain about the term cost-benefit analyses, Explain about the term cost/b...

Explain about the term cost/benefit analyses. Cost/benefit analyse: Cost/benefit analysis is the procedure of knowing, and as far as probable quantifying, the costs of res

Brand, contents for introduce a new brand.

contents for introduce a new brand.

How standards contribute and assist the business community, Question: (...

Question: (a) International standards are strategic tools and guidelines to help organisations to tackle some of the most demanding challenges of modern business. Given ISO sta

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd