software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Project sceening, explain the reason for the divergence of opinion from one...

explain the reason for the divergence of opinion from one technique to the next?

Process of delivering a presentation, Question : The process of deliver...

Question : The process of delivering a presentation is a systematic one that involves thorough planning as well as preparation and one of the main phases is preparing the prese

Define balance of payments, Balance of Payments A summary of balance o...

Balance of Payments A summary of balance of payments in the statement of international transactions between U.S. residents and residents of foreign nations serves as a measure

Assessing Infrastructure Project-Related Risks, The Three Gorges Dam is pot...

The Three Gorges Dam is potentially one of the largest, if not the largest infrastructure projects completed in the 21st century. Clearly, there were a number of key risks that the

Continuous improvement - total quality management, Do it Right First Tim...

Do it Right First Time : TQM adopt the policy of zero defect. There is no scope for rework and rejection. The right first time or zero defect is the result of an empha

Case study, two boss problem case study

two boss problem case study

Cost analysis, After analyzing the three models, and comparing all three us...

After analyzing the three models, and comparing all three using a paired-t test, we found out that the results of the modifications to the base model were statistically significant

Fixed position based layout, Fixed Position Based Layout As the term its...

Fixed Position Based Layout As the term itself implies, fixed layout involves the movement of men and machines to the product which remains stationary. In this type of layout th

Layout planning and analysis, Layout Planning and Analysis Designing a...

Layout Planning and Analysis Designing and installing a layout for the first time and subsequent revision may be looked after by the. Engineering or planning department. Not i

What is the conclusion about liberalization, What is the conclusion about l...

What is the conclusion about liberalization? As a conclusion, we can say only that liberalization is superior and desirable but which does not strengthen the case for privatiza

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd